Project Background

Since early 1990s, contaminated sediment(1)arising from various construction works in Hong Kong has been disposed of at a series of seabed pits at East of Sha Chau (ESC). The latest sets of the Contaminated Mud Pits (CMPs), located at ESC and at the South of The Brothers (SB) have been constructed to meet the disposal demand.


The environmental acceptability of the construction and operation of the Project had been confirmed by findings of the associated Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP)(2). The Director of Environmental Protection (DEP) approved this EIA report under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) in September 2005 (EIA Register No.: AEIAR-089/2005).


In accordance with the EIA recommendation, prior to commencement of construction works for CMPs at SB, the Civil Engineering and Development Department (CEDD) undertook a detailed review and update of the EIA findings for the SB site(3). Findings of the EIA review undertaken in 2009/ 2010 confirmed that the construction and operation of the SB site had been predicted to be environmentally acceptable.


Two Environmental Permits (EPs) (EP-312/2008/A and EP-427/2011/A) were issued by the Environmental Protection Department (EPD) to the CEDD, the Permit Holder, on 28 November 2008 for ESC CMP V and on 23 December 2011 for SB CMPs, respectively. Under the requirements of the EPs, Environmental Monitoring and Audit (EM&A) programme as set out in the respective EM&A Manuals(4)(5) are required to be implemented for the CMPs.


This website contains environmental monitoring data and Project information including the Project Profile, EIA report, Environmental Permit and finalized submissions and plans required under the EPs.

----------------------------------------------------------------------------------------------------------------------------------------------------------------

 (1) According to the Management Framework of Dredged/ Excavated Sediment of ETWB TC(W) No. 34/2002, contaminated sediment in general shall mean those sediment requiring Type 2 ¡V Confined Marine Disposal as determined according to this TC(W).
 (2) Detailed Site Selection Study for a Proposed Contaminated Mud Disposal Facility within the Airport East/ East of Sha Chau Area (Agreement No. CE 12/2002(EP))
 (3) Under the CEDD study Contaminated Sediment Disposal Facility to the South of The Brothers (Agreement No. FM 2/2009)
 (4) ERM (2012) Environmental Monitoring and Audit (EM&A) Manual. Final First Review. Environmental Monitoring and Audit for Contaminated Mud Pits to the South of the Brothers and at East Sha Chau (2012-2017) ¡V Investigation. Agreement No. CE 23/2012(EP). Submitted to EPD in November 2012.
 (5) ERM (2017) Updated Environmental Monitoring and Audit (EM&A) Manual. Environmental Monitoring and Audit for Contaminated Mud Pit at Sha Chau (2017-2020) ¡V Investigation. Agreement No. CE 63/2016(EP). Submitted to EPD in July 2017.