Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
28th MONTHLY PROGRESS REPORT FOR December
2014
1.1 Background
1.1.1 Since early 1990s, contaminated sediment ([1])
arising from various construction works (e.g. dredging and reclamation
projects) in Hong Kong has been disposed of at a series of seabed pits at East
of Sha Chau (ESC). In late 2008, a review
indicated that the existing and planned facilities at ESC would not be able to
meet the disposal demand after 2012. In order to meet this demand, the
Hong Kong Special Administrative Region Government (HKSARG) decided to
implement a new contained aquatic disposal (CAD) ([2])
facility at the South of The Brothers (SB CMPs) which had been under
consideration for a number of years.
1.1.2 The environmental acceptability of the construction and
operation of the Project had been confirmed by findings of the associated
Environmental Impact Assessment (EIA) study completed in 2005 under
Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection (DEP) approved this EIA
report under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) in September 2005 (EIA Register
No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA recommendation, prior to
commencement of construction works for the SB CMPs, the Civil Engineering and
Development Department (CEDD) undertook a detailed review and update of the EIA
findings for the SB site ([4]). Findings of the EIA review
undertaken in 2009/ 2010 confirmed that the construction and operation of the
SB site had been predicted to be environmentally acceptable.
1.1.4 Environmental
Permits (EPs) (EP-312/2008/A and EP-427/2011A) were issued
by the Environmental Protection Department (EPD) to the CEDD, the Permit
Holder, on 28 November 2008 for ESC CMP V and on 23 December 2011 for SB CMPs,
respectively. Under the requirements of the EPs, an Environmental Monitoring and Audit (EM&A) programme
as set out in the EM&A Manuals ()
() is required
to be implemented for the CMPs.
1.1.5 The present EM&A programme under Agreement
No. CE 23/2012 (EP) covers the dredging, disposal and
capping operations of the SB CMPs as well as ESC CMPs. Detailed works
schedule for both CMPs is shown in Figure 1.1. In December 2014, the following works were being
undertaken at the CMPs:
¡P
Capping was being undertaken at ESC CMPs ;
¡P
Disposal of contaminated mud at SB CMP 2; and
¡P
Capping operations at
SB CMP 1.
Figure
1.1 Works Schedule for ESC CMPs and SB CMPs
1.2 Reporting Period
1.2.1 This 28th Monthly Progress Report covers the EM&A activities for the
reporting month of December 2014.
1.3 Details of Sampling and Laboratory Testing Activities
1.3.1 The following monitoring activities have been undertaken for
ESC CMPs in December 2014.
¡P
Water Quality Monitoring during Capping Operations of ESC CMPs was
undertaken on 9 December 2014; and
¡P
Benthic Recolonisation Studies of ESC CMPs was
undertaken on 16 December 2014.
1.3.2
The following monitoring activities have been
undertaken for SB CMPs in December 2014:
¡P
Pit Specific Sediment Chemistry of CMP 2 was undertaken
on 11 December 2014;
¡P
Cumulative Impact Sediment Chemistry of CMP 2 was
undertaken on 3 December 2014;
¡P
Water Column Profiling of CMP 2 was undertaken
on 4 December 2014; and
¡P
Water Quality Monitoring during Capping Operations of CMP 1
was undertaken on 9 December 2014.
1.4 Details of Outstanding Sampling and/or Analysis
1.4.1 No outstanding sampling remained for December 2014. The following laboratory
analyses were still in progress during the preparation of this monthly report
and hence are not presented in this monthly report:
¡P
Laboratory analyses of sediment samples collected for Benthic Recolonisation Studies of ESC CMPs in December
2014;
¡P
Laboratory analyses of sediment samples collected for Pit Specific
Sediment Chemistry in December; and
¡P
Laboratory analyses of suspended solids in samples collected for Water
Quality Monitoring during Capping of CMP 1.
1.4.2 A summary of field activities conducted are presented in Annex A.
1.5 Brief Discussion of the
Monitoring Results for ESC CMPs
1.5.1 A brief discussion of the monitoring results of the Water
Quality Monitoring during Capping of ESC
CMPs conducted on 9 December 2014 is
presented below.
1.5.2 Water
Quality Monitoring during Capping ¡V December 2014
1.5.3 The monitoring results obtained during December 2014
sampling in the dry season have been assessed for compliance with the Water
Quality Objectives (WQOs) through a review of the Environmental Protection
Department (EPD) routine water quality monitoring data for the dry season
period (November to March) of 2003-2013 from stations in the North Western
Water Control Zone (WCZ), where ESC CMPs are located. For Salinity, the
average value obtained from the Reference stations was used for the basis as
the WQO. A total of sixteen (16) monitoring stations were sampled in
December 2014 as shown in Figure 1.2. Graphical presentation of the monitoring results is provided
in Annex B.
In-situ
Measurements
1.5.4 Graphical presentation of the monitoring results is shown in
Figures 1-6 of Annex B. Levels
of Dissolved Oxygen (DO), pH and Salinity at all stations in December 2014 complied
with the WQO.
Laboratory
Measurements for Suspended Solids (SS)
1.5.5 Concentrations of SS complied with the WQO at all stations
in December 2014 (Figure 7 of Annex B). There
did not appear to be any spatial trend of increasing SS levels towards the
capping operations. Further statistical analysis will be undertaken in
the quarterly report to investigate whether the capping operations at ESC CMPs
is causing any unacceptable deterioration in water quality of the area.
1.6 Brief Discussion of the Monitoring Results for SB CMPs
1.6.1 A brief discussion of the monitoring
results of the following activities for SB CMPs is presented in this 28th
Monthly Progress Report:
¡P
Cumulative Impact Sediment Chemistry of CMP 2
conducted on 3 December 2014;
¡P
Water Column Profiling of CMP 2 conducted on
4 December 2014 ; and
¡P
Water Quality Monitoring during Capping Operations of CMP 1
conducted on 9 December 2014.
1.6.2 Cumulative Impact Sediment
Chemistry of CMP 2 ¡V December 2014
1.6.3 Monitoring
locations for Cumulative
Impact Sediment Chemistry for CMP 2 are shown in Figure
1.3. A total of eleven (11) monitoring stations were sampled in
December 2014.
1.6.4 Analyses
of results for the Cumulative
Impact Sediment Chemistry Monitoring indicated that the concentrations of
all metals, except Arsenic at Capped Pit SB-RCA Station, were below the
Lower Chemical Exceedance Level (LCEL) in December 2014 (Figure 8 and 9 of Annex
B).
1.6.5 Whilst
the average concentration of Arsenic in the Earth¡¦s crust is generally ~
2mg/kg, significantly higher Arsenic concentrations (median = 14 mg/kg) have
been recorded in Hong Kong¡¦s onshore sediments (). It is presumed
that the natural concentrations of Arsenic are similar in onshore and offshore
sediments (),
and relatively high Arsenic levels may thus occur throughout Hong Kong.
Therefore, the LCEL exceedance of Arsenic at the Capped Pit SB-RCA
Station is unlikely to be caused by the disposal operations at CMP 1 but rather
as a result of naturally occurring deposits.
1.6.6 For
organic contaminants, concentration of Total Organic Carbon (TOC) at Tai Ho Bay
Station 2 (THB2) was recorded to be higher than other stations (Figure 10 of Annex
B). Concentrations of Tributyltin (TBT) were recorded
to be higher at Near-field station SB-RNB station (Figure 11 of Annex
B). Total Dichloro-diphenly-trichloroethane
(DDT) and 4,4¡¦-Dichloro-diphenly-dichloroenthylene
(4,4¡¦-DDE) were recorded below the limit of detection at allstations
with no apparent spatial trend . Concentrations of Total Polychlorinated
Biphenyls (PCBs) as well as Low and High Molecular Weight Polycyclic Aromatic
Hydrocarbons (Low and High MW PAHs) were recorded below the limit of reporting
at all the stations.
1.6.7 Overall,
there is no evidence indicating any unacceptable environmental impacts to
sediment quality as a result of the contaminated mud disposal operations at CMP
2 during this monthly period.
1.6.8 Water
Column Profiling of CMP 2 ¡V December 2014
1.6.9 Water
Column Profiling was undertaken at a total of two
sampling stations (Upstream and Downstream stations) on 4 December 2014. The water quality monitoring results have been assessed for
compliance with the WQO. The monitoring results were also compared with the Action and Limit Levels set in Baseline
Monitoring Report (see Table C2 of Annex C for details).
In-situ
Measurements
1.6.10 Analyses of results for December 2014 indicated that levels
of Salinity, turbidity, DO and pH complied with the WQOs at both Downstream and
Upstream stations (Table C1 of Annex C).
Laboratory
Measurements for SS
1.6.11
Analyses of results for December 2014 indicated that
the SS levels at both Upstream and Downstream stations complied with the WQO.
SS levels at all stations complied with the Action and Limit Levels (Table
C1 of Annex C).
1.6.12 Overall, the monitoring results indicated that the mud
disposal operation at CMP 2 did not appear to cause any deterioration in water
quality during this reporting period.
1.6.13 Water
Quality Monitoring during Capping Operations of CMP 1¡V December 2014
1.6.14 The monitoring results obtained during December 2014
sampling in the dry season have been assessed for compliance with the WQOs
through a review of the EPD routine water quality monitoring data for the dry
season period (November to March) of 2003-2013 from stations in the North
Western WCZ, where SB CMP 1 is located. For Salinity, the average value
obtained from the Reference stations was used for the basis as the WQO. A
total of fourteen (14) monitoring stations were sampled in December 2014 as
shown in Figure 1.4. Graphical presentation of the monitoring results is provided
in Annex B.
In-situ
Measurements
1.6.15 Graphical presentation of the monitoring results in shown in
Figure 12-17 of Annex B. Levels
of Dissolved Oxygen (DO), pH and Salinity at all stations in December 2014
complied with the WQO.
1.7 Activities Scheduled for the Next Month
1.7.1 The following monitoring activities will be conducted in the
next monthly period of January 2015 for SB CMPs:
¡P
Pit Specific Sediment Chemistry of CMP 2;
¡P
Demersal Trawling for CMP2;
¡P
Routine Water Quality Monitoring for CMP2;
¡P
Water Column Profiling of CMP 2; and
¡P
Water Quality Monitoring during Capping Operations of CMP 1.
1.7.2 No monitoring activities will be conducted in the next
monthly period of January 2015 for ESC CMPs.
1.7.3 The sampling schedule is presented in Annex A.
1.8 Study Programme
1.8.1 A summary of the Study programme is presented in Annex D.
() Sewell
RJ (1999) Geochemical Atlas of Hong Kong. Geotechnical Engineering Office, Government of the Hong Kong Special
Administrative Region
() Whiteside
PGD (2000) Natural geochemistry and contamination of marine sediments in Hong
Kong. In: The Urban Geology of Hong Kong (ed Page A & Reels SJ).
Geological Society of Hong Kong Bulletin No. 6, p109-121