Agreement No. CE 63/2016 (EP)
Environmental Monitoring and Audit
for Disposal Facility to the East of Sha Chau
(2017-2020) - Investigation
MONTHLY EM&A REPORT FOR December 2019
1.1
Background
1.2
Reporting Period
1.3
Details of
Sampling and Laboratory Testing Activities
1.4
Details of
Outstanding Sampling and/or Analysis
1.5
Brief
Discussion of the Monitoring Results for ESC CMP V
1.6
Activities
Scheduled for the Next Month
1.7
Study Programme
Annexes
Annex A Sampling Schedule
Annex B Water Quality Monitoring Results
Annex C Graphical Presentations
Annex D Dredging Record
Annex E Study Programme
1.1
Background
1.1.1
The Civil
Engineering and Development Department (CEDD) is managing a number of marine
disposal facilities in Hong Kong waters, including the Contaminated Mud Pits (CMPs)
to the South of The Brothers (SB) and to the East of Sha
Chau (ESC) for the disposal of contaminated sediment, and open-sea disposal
grounds located to the South of Cheung Chau (SCC), East of Tung Lung Chau
(ETLC) and East of Ninepins (ENP) for the disposal of uncontaminated
sediment. Two Environmental Permits (EPs), EP-312/2008/A and
EP-427/2011/A, were issued by the Environmental Protection Department (EPD) to
the CEDD, the Permit Holder, on 28 November 2008 and 23 December 2011 for the
Dredging, Management and Capping of Contaminated Sediment Disposal Facilities
at ESC CMP V and SB CMPs, respectively.
1.1.2
Under the
requirements of the two EPs for ESC CMP V and SB CMPs, EM&A
programmes which encompass water and sediment chemistry, fisheries assessment,
tissue and whole body analysis, sediment toxicity and benthic recolonisation studies as set out in the EM&A Manuals
are required to be implemented. EM&A programmes
have been continuously carried out during the operation of the CMPs at ESC and
SB. A review of the collection and analysis of such environmental
data from the monitoring programme demonstrated that there had not been any
adverse environmental impacts resulting from disposal
activities ([1])([2]).
The current programme will assess the impacts
resulting from dredging, disposal and capping operations of CMP V as well as
capping operations of SB CMPs.
1.1.3
The present
EM&A programme under Agreement
No. CE 63/2016 (EP) covers the dredging, disposal and capping operations of the ESC CMP V
as well as the capping operations of the SB CMPs (see Annex A for the EM&A programme). The scheduled EM&A programme for SB CMPs was completed in
December 2018. Detailed works schedule for ESC CMP V is shown in Figure 1.1. In December 2019, dredging of accumulated
natural deposits at ESC CMP Vb and disposal of
contaminated mud at ESC CMP Vd were undertaken.
Figure 1.1 Works Schedule for ESC CMP V
1.2
Reporting Period
1.2.1
This Monthly EM&A Report for December 2019 covers the EM&A
activities for the reporting month of December 2019.
1.3
Details of Sampling and Laboratory Testing Activities
1.3.1
The following
monitoring activities were undertaken for ESC CMP V in December 2019:
·
Water Column Profiling of ESC CMP Vd;
·
Cumulative Impact Sediment Chemistry of of ESC
CMPs;
·
Pit Specific Sediment Chemistry of ESC CMP Vd; and
·
Water Quality Monitoring During Dredging of ESC CMP Vb.
1.4
Details of Outstanding Sampling and/or Analysis
1.4.1
No outstanding sampling remained for December
2019.
1.5
Brief Discussion of the Monitoring Results for ESC CMP V
1.5.1
Brief discussion of the monitoring
results of the following activities for ESC CMP V is presented in this Monthly EM&A Report for December 2019:
·
Water Column Profiling of ESC CMP Vd in December 2019;
·
Cumulative Impact Sediment Chemistry of of ESC
CMPs in December 2019;
·
Pit Specific Sediment Chemistry of ESC CMP Vd in December 2019; and
·
Water Quality Monitoring During Dredging of ESC CMP Vb in December 2019.
1.5.2
Water Column Profiling of ESC CMP Vd – December 2019
1.5.3
Water Column Profiling was undertaken at a total of two
sampling stations (Upstream and Downstream stations) on 12 December 2019.
The monitoring
results have been assessed for compliance with the Water Quality Objectives (WQOs) set
by Environmental Protection Department (EPD). This consists of a review
of the EPD routine water quality monitoring data for the dry season period
(November to March) of 2009 - 2018 from stations in the Northwestern
Water Control Zone (WCZ), where the ESC CMPs are located ([3]).
For Salinity, the averaged value obtained from the Reference (Upstream) station
was used for the basis as the WQO. Levels of Dissolved Oxygen (DO) and
Turbidity were also assessed for compliance with the Action and Limit Levels
(see Table B1 of Annex B for
details).
In-situ
Measurements
1.5.4
Analyses of
results for December 2019 indicated that levels of Salinity, pH and DO complied
with the WQOs at both Downstream and Upstream stations (Table B2 of Annex B). Levels of DO and Turbidity
at all stations complied with the Action and Limit Levels (Tables B1 and B2 of Annex B).
Laboratory
Measurements for Suspended Solids (SS)
1.5.5
Analyses of
results for December 2019 indicated that the SS levels at both Downstream and Upstream stations were complied with the WQO and the Action
and Limit Levels (Tables B1 and B2 of Annex B).
1.5.6
Overall, the
monitoring results indicated that the mud disposal operation at ESC CMP Vd did not appear to cause any deterioration in water quality
during this reporting period.
1.5.7
Cumulative Impact Sediment Chemistry
of ESC CMPs – December 2019
1.5.8
Monitoring
locations for Cumulative Impact Sediment Chemistry for ESC CMPs are shown in Figure 1.2. A total of nine (9) monitoring stations were sampled on 3 and 5
December 2019.
1.5.9
Analyses of
results for the Cumulative
Impact Sediment Chemistry Monitoring indicated that the concentrations of most inorganic
contaminants were below the Lower Chemical Exceedance Levels (LCEL) at most stations in December 2019, except
concentrations of Arsenic were higher than the LCEL at Near-field station
ESC-RNB, Mid-field stations ESC-RMA and ESC-RMB, Far-field station ESC-RFB and
Ma Wan station (Figures 1 and 2 of Annex C).
1.5.10
Whilst the average concentration of Arsenic in the Earth’s crust is generally
~2mg/kg, significantly higher Arsenic concentrations (median = 14 mg/kg) have
been recorded in Hong Kong’s onshore sediments ([4]). It is presumed that the natural concentrations of Arsenic are
similar in onshore and offshore sediments ([5]), and relatively high Arsenic levels may thus occur throughout Hong
Kong. Therefore, the LECL exceedances of Arsenic are unlikely to be
caused by the disposal operations at ESC CMP Vd but
rather as a result of naturally occurring deposits.
1.5.11
For organic contaminants, the concentrations of Total Organic Carbon (TOC) varied between stations in
December 2019, with the generally higher concentrations of TOC recorded at
Capped Pit station ESC-RCA (Figure 3 of Annex C). The concentrations of Tributyltin (TBT) were generally similar across
stations, except at Ma Wan Station where higher concentrations were recorded (Figure 4 of Annex C). The concentrations of
Low Molecular Weight and High Molecular Weight Polycyclic Aromatic Hydrocarbons (PAHs) were below the LCEL at all stations in December 2019 (Figure 5 of Annex C). Total Polychlorinated
Biphenyls (PCBs), Total dichloro-diphenyl-trichloroethane (DDT) and 4,4’-dichlorodiphenyldichloroethylene
(DDE) concentrations were below the limit of reporting at all stations.
1.5.12
Overall, there is
no evidence indicating any unacceptable environmental impacts to sediment
quality as a result of the contaminated mud disposal operations at ESC CMP Vd in December 2019. Statistical analysis will be
undertaken and presented in the corresponding quarterly report to investigate
whether there are any unacceptable impacts in the area caused by the
contaminated mud disposal.
1.5.13
Pit Specific Sediment Chemistry of
ESC CMP Vd – December 2019
1.5.14
Monitoring
locations for Pit Specific
Sediment Chemistry for ESC CMP Vd are shown in Figure 1.3. A total of six (6) monitoring stations were sampled on 16 December 2019. It is noted that one of the sample
replicates collected at Active-Pit station ESC-NPAA showed abnormally high readings and thus it
was considered as an outlier and excluded in the result presentation.
1.5.15
The concentrations
of most inorganic contaminants were lower than the LCEL at most stations, except for Copper having
concentrations higher than LCEL at Active-Pit station ESC-NPAA (Figures 6 and 7 of Annex C).
1.5.16
Considering that
the higher levels of Copper occurred within Active-Pit station ESC-NPAA only
but not at the Pit-Edge and Near-Pit stations, there is no evidence indicating
any unacceptable environmental impacts to sediment quality as a result of the
contaminated mud disposal operations at ESC CMP Vd in
December 2019.
1.5.17
For organic contaminants, the concentrations of TOC were lowest at
Pit-Edge stations and were highest at Active-Pit stations in December 2019 (Figure 8 of Annex
C). The
concentrations of TBT were generally similar across all stations, except it was
higher at Active-Pit stations ESC-NPAA in December 2019 (Figure 9 of Annex
C). PCBs, DDT
and DDE concentrations were below the limit of reporting at all stations.
The concentrations of Low Molecular Weight and High Molecular Weight PAHs were
below LCEL at all the stations and were higher at Active-Pit Stations ESC-NPAA
and ESC-NPAB. (Figure 10 of
Annex C).
1.5.18
There is no evidence indicating any unacceptable environmental impacts to
sediment quality as a result of the contaminated mud disposal operations at ESC
CMP Vd in December 2019. Statistical analysis
will be undertaken and presented in the corresponding quarterly report to
investigate whether there are any unacceptable impacts in the area caused by
the contaminated mud disposal.
1.5.19
Impact Water Quality Monitoring
during Dredging Operations of ESC CMP Vb – December
2019
1.5.20
Dredging operation
at ESC CMP Vb commenced on 11 November 2019 and was
completed on 5 December 2019. Water quality monitoring during dredging
operations was conducted on 2 and 4 December 2019 during the reporting
period. During each survey day, monitoring was conducted during both
mid-ebb and mid-flood tides at two Reference (Upstream) stations and five Impact
(Downstream) stations around the dredging operations at ESC CMP Vb.
Monitoring was also conducted at one Sensitive Receiver station situated in Ma
Wan. A total of eight (8) stations were monitored and locations of the
sampling stations are shown in Figure 1.4.
1.5.21
Monitoring results
are presented in Table B3 of Annex B. Daily dredging volume in
December 2019 is reported in Annex D. Levels of DO, Turbidity and
SS complied with the Action and Limit Levels (see Table B1 of Annex B for details). The results indicated that the dredging operations
at ESC CMP Vb did not appear to cause any
unacceptable deterioration in water quality during this reporting period.
Therefore, no further action, except for those recommended in the Environmental
Permit (EP-312/2008/A), are considered necessary for the dredging operations.
1.6
Activities Scheduled for the Next Month
1.6.1
The following monitoring activities will be conducted
in the next monthly period of January 2020 for ESC CMP V (see Annex A for the sampling schedule ([6])
·
Water Column Profiling of ESC CMP Vd;
·
Routine Water Quality Monitoring of ESC CMPs;
·
Pit Specific Sediment Chemistry of ESC CMP Vd; and
·
Demersal Trawling for ESC CMPs.
1.7
Study Programme
1.7.1
A summary of the
Study Programme is presented in Annex E.