Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
37th MONTHLY PROGRESS REPORT FOR September
2015
1.1.1
Since early 1990s, contaminated sediment ([1])
arising from various construction works (e.g. dredging and reclamation
projects) in Hong Kong has been disposed of at
a series of seabed pits at East of Sha Chau (ESC). In late
2008, a review indicated that the existing and planned facilities at ESC would
not be able to meet the disposal demand after 2012. In order to meet this demand, the Hong Kong Special Administrative Region
Government (HKSARG) decided to implement a new contained aquatic disposal (CAD)
([2])
facility at the South of The Brothers (SB CMPs) which
had been under consideration for a number of years.
1.1.2
The environmental acceptability of the
construction and operation of the Project had been confirmed by findings of the
associated Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact
Assessment Ordinance (Cap. 499) (EIAO) in
September 2005 (EIA Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA
recommendation, prior to commencement of construction works for the SB CMPs, the Civil Engineering and Development Department
(CEDD) undertook a detailed review and update of the EIA findings for the SB
site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had
been predicted to be environmentally acceptable.
1.1.4
Environmental Permits (EPs) (EP-312/2008/A and EP-427/2011A) were
issued by the Environmental Protection Department (EPD) to the CEDD, the Permit
Holder, on 28 November 2008 for ESC CMP V and on 23 December 2011 for SB CMPs, respectively. Under the requirements of the EPs, an
Environmental Monitoring and Audit (EM&A) programme as set out in the
EM&A Manuals ()
()
is required to be implemented for the CMPs.
1.1.5
The present EM&A programme under Agreement No. CE
23/2012 (EP) covers the dredging, disposal and capping operations of the
SB CMPs as well
as ESC CMPs. Detailed works
schedule for both CMPs is shown in Figure 1.1. In September 2015,
the following works were being undertaken at the CMPs:
· Dredging operation at ESC CMP Vd;
· Capping operations at ESC CMP Va; and
· Disposal of contaminated mud at SB CMP 2.
Figure 1.1 Works
Schedule for ESC CMPs and SB CMPs
1.2
Reporting Period
1.2.1
This 37th Monthly Progress
Report covers the EM&A activities for
the reporting month of September 2015.
1.3
Details of
Sampling and Laboratory Testing Activities
1.3.1
The following monitoring activities have
been undertaken for ESC CMPs in September 2015:
·
Impact Water Quality Monitoring during Dredging Operations of ESC CMPs
was undertaken on 24, 26, 28 and 30 September 2015.
1.3.2
The following monitoring activities have
been undertaken for SB CMPs in September 2015:
·
Pit Specific Sediment Chemistry of CMP 2 was undertaken on
1 September 2015; and
·
Water Column Profiling of CMP 2 was undertaken on
2 September 2015.
1.4
Details of
Outstanding Sampling and/or Analysis
1.4.1
No outstanding sampling remained for September 2015.
1.4.2
A summary of field activities conducted are presented in Annex A.
The following
laboratory analyses were still in progress during the preparation of this
monthly report and hence are not presented in this monthly report:
·
Laboratory analyses of sediment samples collected for Cumulative Impact Sediment Chemistry of SB
CMP 2 in August 2015; and
·
Laboratory analyses of sediment samples collected for Pit Specific
Sediment Chemistry of SB CMP 2 in September 2015.
1.5
Brief Discussion
of the Monitoring Results for ESC CMPs
1.5.1
Brief discussion of the monitoring results of the
Impact Water Quality Monitoring
during Dredging Operations of ESC CMP
Vd conducted in September 2015 is
presented below.
1.5.2
Impact Water Quality
Monitoring during Dredging Operations of ESC CMP Vd – 24 to 30 September 2015
1.5.3
Dredging operation of ESC CMP Vd commenced
on 8 September 2015 and dredging activities were not carried out on 15, 16, 17
and 19 September 2015. Impact Water Quality Monitoring during Dredging
Operations of ESC CMP Vd was conducted three times per week in
September 2015 starting from 24 September 2015. On each survey day, monitoring was conducted
during both mid-ebb and mid-flood tides at two Reference (Upstream) stations
and five Impact (Downstream) stations of the dredging operations at ESC CMP Vd. Monitoring was
also conducted at one Sensitive Receiver Station situated in Ma Wan. A total of eight (8) stations were monitored
and locations of the sampling stations are shown in Figure 1.2.
1.5.4
Monitoring results are presented in Table B1 of Annex B.
Daily dredging volume in September 2015 is reported in Annex C.
Levels of Dissolved Oxygen (DO), Turbidity and Suspended Solid (SS)
generally complied with the Action and Limit Levels (see Table B2 of Annex B for details) set in the Baseline Monitoring Report (),
except for the following occasion of exceedances discussed
in Table 1.1 below.
1.5.5
As presented in Table 1.1, the results indicated that the dredging operations at ESC
CMP Vd did not appear to cause any unacceptable
deterioration in water quality during this reporting period. Therefore, no further action, except for
those recommended in the Environmental Permit (EP-312/2008/A), are considered necessary for the dredging operations.
1.6.1
Brief discussion of the monitoring results of
the following activities for SB CMPs is presented in
this 37th
Monthly Progress Report:
· Pit Specific Sediment Chemistry of CMP 2 in August
2015; and
·
Water Column Profiling of CMP 2 in September 2015;
1.6.2
Pit Specific Sediment
Chemistry of CMP 2 – August 2015
1.6.3
Monitoring locations for Pit Specific Sediment
Chemistry for CMP 2 are shown in Figure 1.3.
A total of six (6) monitoring stations were sampled in August 2015.
1.6.4
Copper exceeded
the Upper Chemical Exceedance Level (UCEL) at Active
Pit stations SB-NPBA and SB-NPBB (Figure
1 of Annex D). Mercury exceeded the Lower Chemical Exceedance
Level (LCEL) at Active Pit
station SB-NPBB and Near Pit station SB-NNBA (Figure 2 of Annex D). Exceedances of UCEL
were also recorded for Silver at Active Pit station SB-NPBA (Figure 2 of Annex D). The concentrations of other inorganic
contaminants (Arsenic, Cadmium, Chromium, Nickel, Lead and Zinc) were lower than the LCEL
at all stations (Figures
1 and 2
of Annex D).
1.6.5
Higher Copper
and Silver concentrations were recorded within the Active Pit station only
which were receiving contaminated mud during the reporting month. Higher Mercury concentrations were recorded at
one Active Pit station and one Near Pit station while the stations between
them, Pit Edge stations, was recorded with lower concentration. Therefore, there is no evidence indicating any dispersal of
contaminants from the active pit due to the disposal activities.
1.6.6
For
organic contaminants, the concentrations of Total Organic Carbon (TOC) were
similar at all stations, except lower concentration was recorded in Pit Edge
station NEBB (Figure 3 of Annex D). Tributyltin (TBT) concentrations were observed to be
higher at Active Pit station SB-NPBA (Figure 4
of Annex D).
Low and High Molecular Weight Polycyclic Aromatic Hydrocarbons (PAHs), Total Polychlorinated Biphenyls (PCBs),
4,4’-dichlorodiphenyldichloroethylene (DDE) and Total
dichlorodiphenyltrichloroethane (DDT) concentrations were below the limit of
reporting at most stations, except High MW PAHs at Active
Pit stations SB-NPBA and SB-NPBB and Low MW PAHs at
Active Pit station SB-NPBB (Figure 5 of Annex D).
1.6.7
Overall,
there is no evidence indicating any unacceptable environmental impacts to
sediment quality as a result of the contaminated mud disposal operations at CMP
2 in August 2015.
Statistical analysis will be undertaken and presented in the quarterly
report to investigate whether there are any unacceptable impacts in the area
caused by the contaminated mud disposal.
1.6.8
Water
Column Profiling of CMP 2 – September 2015
1.6.9
Water
Column Profiling was
undertaken at a total of two sampling stations (Upstream and Downstream
stations) on 2
September 2015. The monitoring results have been assessed for
compliance with the Water Quality Objectives (WQOs) set by Environmental Protection Department (EPD).
This consists
of a review of the EPD routine water quality monitoring data for the wet season
period (April to October) of 2004 - 2013 from stations in the Northwestern
Water Control Zone (WCZ), where the CMPs are located (). For Salinity, the averaged value obtained
from the Reference stations was used for the basis as the WQO. Levels of DO and Turbidity were
also assessed for compliance with the Action and Limit Levels (see Table B3 of Annex B for details).
In-situ
Measurements
1.6.10
Analyses of results for September 2015 indicated that levels of Salinity, DO and pH complied with the WQOs at both Downstream and Upstream stations (Table B4 of Annex B).
In addition, DO and Turbidity at all stations
complied with the Action and Limit Levels (Tables B3 and B4 of Annex B).
Laboratory
Measurements for SS
1.6.11
Analyses of results for September 2015 indicated that the SS levels at both Upstream and
Downstream stations complied with the WQO.
Both Upstream and Downstream stations also complied with the Action and Limit Levels (Tables B3
and B4 of Annex B).
Overall, the monitoring results indicated that the mud
disposal operation at CMP 2 did not appear to cause any deterioration in water
quality during this reporting period.
1.7
Activities
Scheduled for the Next Month
1.7.1
The following monitoring activities will be conducted in the
next monthly period of October 2015 for SB CMPs:
·
Pit Specific Sediment Chemistry of CMP 2;
·
Routine Water Quality Monitoring of CMP 2; and
·
Water Column Profiling of CMP 2.
1.7.2
The following monitoring activities will be
conducted in the next monthly period of October 2015 for ESC CMPs:
·
Impact Monitoring during
Dredging Operations of ESC CMP Vd.
1.7.3
The sampling schedule is presented in Annex A.
1.8.1
A summary of the Study programme is presented in Annex E.