Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits at the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
8TH MONTHLY
PROGRESS REPORT FOR APRIL 2013
1.1.1
Since early 1990s, contaminated
sediment ([1]) arising from
various construction works in Hong Kong has
been disposed of at a series of seabed pits at East of Sha
Chau (ESC). In
late 2008, a review indicated that the existing and planned facilities at ESC
would not be able to meet the disposal demand after 2012. In order to meet this demand, the Hong Kong
Special Administrative Region Government (HKSARG) decided to implement a new
contained aquatic disposal (CAD) ([2])
facility at the South of The Brothers (SB CMPs)
(hereafter referred to as “the Project”) which had been under consideration for
a number of years.
1.1.2
The environmental acceptability of the
construction and operation of the Project had been confirmed by findings of the
associated Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO) in September
2005 (EIA
Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA
recommendation, prior to commencement of construction works for the SB CMPs, the Civil Engineering and Development Department
(CEDD) undertook a detailed review and update of the EIA findings for the SB
site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had
been predicted to be environmentally acceptable.
1.1.4
An Environmental Permit (EP-427/2011) was
issued by the Environmental Protection Department (EPD) to the CEDD, the Permit
Holder, on 3 November 2011 and varied on 23 December 2011 (EP-427/2011/A). Under the requirements of Condition 4 of
the EP (EP-427/2011/A), an
Environmental Monitoring and Audit (EM&A) programme as set out in the
EM&A Manual () is required
to be implemented for the SB CMPs. The present EM&A
programme undertaken under Agreement No. CE 23/2012 (EP)
covers the dredging, disposal and capping operations of the SB CMPs.
1.2
Reporting Period
1.2.1
This Monthly Progress Report covers the EM&A activities for the reporting month of April 2013.
1.3
Details of Sampling and Laboratory Testing Activities
1.3.1
Impact Water Quality Monitoring
during Dredging Operations of CMP 1 was
conducted three times per week (ie 1, 3, 5, 8, 10, 12,
15, 17, 19, 22, 24, 26 and 29 April 2013) in this reporting month in accordance
with the EM&A Manual.
1.4.1
No outstanding sampling remained from April 2013. Laboratory analysis of Suspended Solids (SS)
collected after 24 April 2013 was still in progress during the preparation of
this monthly report. A summary of field
activities conducted are presented in Annex A.
1.5.1
Monitoring data
collected for SB CMPs from 27 March to 24 April 2013 are
presented in this monthly report.
Detailed discussion will be presented in the corresponding Quarterly
Report.
1.5.2
Impact Water Quality Monitoring during Dredging
Operations of CMP 1 – March and April 2013
1.5.3
Impact Water Quality Monitoring
during Dredging Operations of CMP 1 was
conducted three times per week with a total of thirteen (13) sampling days from
27 March to 24 April 2013. On each survey
day, sampling was conducted during both mid-ebb and mid-flood tides at two
Reference (Upstream) stations upstream and five Impact (Downstream) stations
downstream of the dredging operations at CMP 1.
Monitoring was also conducted at five Sensitive Receiver Stations (Ma Wan,
Shum Shui Kok, Tai Mo To
and Tai Ho Bay). A total of twelve
stations were monitored and locations of the sampling stations are shown in Figure 1.1.
1.5.4
Monitoring results
from 27 March to 24 April 2013 are presented in Table B1 of Annex B. It should be noted that sampling at station
THB2 during mid-flood tide of 5 April 2013, all sampling during mid-ebb tide of
5 April 2013 and all sampling during mid-flood tide of 19 April 2013 were not
carried out due to adverse weather. Levels
of Dissolved Oxygen (DO), Turbidity and SS generally complied with the Action
and Limit Levels (see Table B2 for details) set in the Baseline Monitoring Report (), except for the following occasions of exceedances
shown in Table 1.1 below.
Table 1.1 Details
of exceedances recorded at CMP 1 between 27 March and
24 April 2013
Date
|
Tide
|
Parameter
|
Station
|
Type
|
27 March
2013
|
Ebb
|
Turbidity
|
WSR46
|
Action
|
27 March
2013
|
Ebb
|
SS
|
WSR46
|
Limit
|
27 March
2013
|
Flood
|
SS
|
DS2
|
Action
|
27 March
2013
|
Flood
|
SS
|
DS3
|
Action
|
29 March
2013
|
Ebb
|
SS
|
DS2
|
Action
|
29 March
2013
|
Flood
|
Turbidity
|
WSR46
|
Limit
|
29 March
2013
|
Flood
|
SS
|
WSR46
|
Action
|
10 April
2013
|
Ebb
|
Turbidity
|
WSR46
|
Action
|
10 April
2013
|
Ebb
|
SS
|
WSR46
|
Limit
|
10 April
2013
|
Flood
|
SS
|
DS4
|
Action
|
10 April
2013
|
Flood
|
SS
|
WSR45C
|
Action
|
12 April
2013
|
Flood
|
SS
|
WSR45C
|
Action
|
12 April
2013
|
Flood
|
Turbidity
|
WSR46
|
Action
|
12 April
2013
|
Flood
|
SS
|
WSR46
|
Action
|
1.5.5
Stations DS2,
DS3, DS4, WSR45C and WSR46 are located further away from the works area of CMP
1 when compared to station DS1 at which the levels of SS and Turbidity did not
exceed the Action and Limit Levels. As
such, the exceedances at these stations (ie DS2, DS3, DS4, WSR45C and WSR46) are not likely to be
caused by the dredging works at CMP 1. It
should be noted that high levels of Turbidity and SS were occasionally recorded
during baseline monitoring which are considered to be sporadic events and
characteristic of water quality in this area of Hong Kong. In addition, relatively higher levels of
Turbidity and SS were recorded at all stations during the tidal periods when exceedances were recorded.
Therefore, the Action and Limit Level exceedances
may be caused by natural background variation in water quality of the
area.
1.5.6
Overall, the
results indicated that the dredging operations at CMP 1 of SB did not appear to
cause any unacceptable deterioration in water quality during this reporting
period. Therefore, no further mitigation
measures, except for those recommended in the Environmental Permit (EP-427/2011/A), are considered necessary for the dredging operations.
1.6
Activities Scheduled for the Next Month
1.6.1
Impact Water Quality Monitoring during
Dredging Operations for CMP 1 will be
conducted three times per week in the next monthly period of May 2013. The sampling schedule is presented in
Annex A.
1.7
Study
Programme
1.7.1
A summary of the Study
programme is presented in Annex C.