1.1 Background
1.2 Reporting Period
1.3 Details of Sampling
and Laboratory Testing Activities
1.4 Details of Outstanding
Sampling and/or Analysis
1.5 Brief Discussion of
the Monitoring Results for ESC CMP V
1.6 Activities Scheduled
for the Next Month
1.7 Study Programme
Annexes
Annex A Sampling Schedule
Annex B Water Quality
Monitoring Results
Annex C Graphical
Presentations
Annex D Study
Programme
Agreement No. CE 63/2016 (EP)
Environmental Monitoring and Audit
for Disposal Facility to the East of Sha Chau (2017-2020) - Investigation
MONTHLY
EM&A REPORT FOR MARCH 2019
1.1
Background
1.1.1
The Civil Engineering and Development Department (CEDD) is
managing a number of marine disposal facilities in Hong Kong waters, including
the Contaminated Mud Pits (CMPs) to the South of The Brothers (SB) and to the
East of Sha Chau (ESC) for the disposal of contaminated sediment, and open-sea
disposal grounds located to the South of Cheung Chau (SCC), East of Tung Lung
Chau (ETLC) and East of Ninepins (ENP) for the disposal of uncontaminated
sediment. Two Environmental Permits (EPs), EP-312/2008/A and EP-427/2011/A,
were issued by the Environmental Protection Department (EPD) to the CEDD, the
Permit Holder, on 28 November 2008 and 23 December 2011 for the Dredging,
Management and Capping of Contaminated Sediment Disposal Facilities at ESC CMP
V and SB CMPs, respectively.
1.1.2
Under the requirements of the two EPs for ESC CMP V and SB
CMPs, EM&A programmes which encompass water and sediment chemistry,
fisheries assessment, tissue and whole body analysis, sediment toxicity and
benthic recolonisation studies as set out in the EM&A Manuals are required
to be implemented. EM&A programmes have
been continuously carried out during the operation of the CMPs at ESC and
SB. A review of the collection and analysis of such environmental
data from the monitoring programme demonstrated that there had not been any
adverse environmental impacts resulting from disposal activities () (). The current programme will assess the impacts resulting
from dredging, disposal and capping operations of CMP V as well as capping
operations of SB CMPs.
1.1.3
The present EM&A programme under Agreement No. CE 63/2016 (EP) covers the
dredging, disposal and capping operations of the ESC CMP V as well as
the capping operations of the SB CMPs (see Annex A for the
EM&A programme).
The scheduled EM&A programme for SB CMPs was completed in
December 2018. Detailed works schedule for ESC CMP V is shown in Figure 1.1. In
March 2019, disposal of contaminated mud at ESC CMP Vd was undertaken.
Figure 1.1 Works
Schedule for ESC CMP V and SB CMPs
1.2
Reporting Period
1.2.1
This Monthly EM&A Report for March 2019 covers the EM&A
activities for the reporting month of March 2019.
1.3
Details of Sampling
and Laboratory Testing Activities
1.3.1
The following monitoring activities were
undertaken for ESC CMP V in March 2019:
·
Water
Column Profiling
of ESC CMP Vd;
and
·
Pit
Specific Sediment Chemistry of ESC CMP Vd.
1.4
Details of Outstanding
Sampling and/or Analysis
1.4.1
No outstanding sampling remained for March 2019.
1.5
Brief Discussion of
the Monitoring Results for ESC CMP V
1.5.1
Brief discussion of the monitoring results of
the following activities for ESC CMP V is presented in this Monthly EM&A Report for March 2019:
·
Water
Column Profiling of ESC CMP Vd in March
2019; and
·
Pit
Specific Sediment Chemistry of ESC CMP Vd in March 2019.
1.5.2
Water
Column Profiling of ESC CMP Vd – March 2019
1.5.3
Water Column Profiling was
undertaken at a total of two sampling stations (Upstream and Downstream
stations) on 5 March 2019. The monitoring results
have been assessed for compliance with the Water Quality
Objectives (WQOs) set by Environmental Protection Department (EPD). This
consists of a review of the EPD routine water quality monitoring data for the
dry season period (November to March) of 2008 - 2017 from
stations in the Northwestern Water Control Zone (WCZ), where the ESC CMPs are
located (). For
Salinity, the averaged value obtained from the Reference (Upstream) station
was used for the basis as the WQO. Levels of Dissolved
Oxygen (DO) and Turbidity were also assessed for compliance with the Action and
Limit Levels (see Table
B1 of Annex B for
details).
In-situ Measurements
1.5.4
Analyses of results for March 2019 indicated
that levels of Salinity, pH and DO complied with the WQOs at both
Downstream and Upstream stations (Table B2 of Annex B). Levels of DO and
Turbidity at all stations complied with the Action and Limit Levels (Tables B1 and B2 of Annex B).
Laboratory Measurements for Suspended
Solids (SS)
1.5.5
Analyses of results for March 2019 indicated
that the SS levels at both Downstream and Upstream stations complied with the
WQO and the Action and Limit Levels at both Downstream and Upstream stations (Tables B1 and B2 of Annex B).
1.5.6
Overall, the monitoring results indicated that
the mud disposal operation at ESC CMP Vd did not appear to cause any
deterioration in water quality during this reporting period.
1.5.7
Pit Specific Sediment
Chemistry of ESC CMP Vd – March 2019
1.5.8
Monitoring locations for Pit Specific Sediment Chemistry
for ESC CMP Vd are shown in Figure
1.2. A total of six (6) monitoring stations were sampled
on 4 March 2019.
1.5.9
The concentrations of all inorganic contaminants were lower
than the Lower Chemical Exceedance Level (LCEL) at
most stations, except the concentrations of Arsenic and Copper were higher than
the LCEL at Active Pit stations ESC-NPAA and ESC-NPAB, respectively (Figures 1 and 2 of Annex C).
1.5.10
For organic contaminants, the concentrations of Total
Organic Carbon (TOC) varied between stations and were higher at Active-Pit
station ESC-NPAB in March 2019 (Figure 3 of Annex C). The
concentrations of Tributyltin (TBT) and Low and High Molecular Weight
Polycyclic Aromatic Hydrocarbons (PAHs) were higher at Active-Pit station
ESC-NPAB in March 2019 (Figures 4 and 5 of Annex C).
Total Polychlorinated Biphenyls (PCBs), Total dichloro-diphenyl-trichloroethane
(DDT) and 4,4’-dichlorodiphenyldichloroethylene (DDE) concentrations were below
the limit of reporting at all stations.
1.5.11
Whilst the average concentration of Arsenic in
the Earth’s crust is generally ~2 mg/kg, significantly higher Arsenic
concentrations (median = 14 mg/kg) have been recorded in Hong Kong’s onshore
sediments ([4]). It is
presumed that the natural concentrations of Arsenic are similar in onshore and
offshore sediments
([5]), and
relatively high Arsenic levels may thus occur throughout Hong Kong.
Therefore, the LECL exceedances of Arsenic are unlikely to be caused by the
disposal operations at ESC CMP Vd but rather as a result of naturally occurring
deposits.
1.5.12
Considering that the higher levels of Copper
occurred within one Active-Pit station ESC-NPAB only but not at the Pit-Edge
and Near-Pit stations, there is no evidence indicating any unacceptable
environmental impacts to sediment quality as a result of the contaminated mud
disposal operations at ESC CMP Vd in March 2019. Statistical
analysis will be undertaken and presented in the corresponding quarterly report
to investigate whether there are any unacceptable impacts in the area caused by
the contaminated mud disposal.
1.6
Activities Scheduled
for the Next Month
1.6.1
The following monitoring activities
will be conducted in the next monthly period of April 2019 for ESC CMP V (see
Annex A for the
sampling schedule ()):
·
Water
Column Profiling
of ESC CMP Vd;
·
Routine
Water Quality Monitoring of ESC CMPs; and
·
Pit
Specific Sediment Chemistry of ESC CMP Vd.
1.7
Study Programme
1.7.1
A summary of the Study Programme is
presented in Annex D.