Agreement No. CE 63/2016 (EP)
Environmental Monitoring and Audit
for Disposal Facility to the East of Sha Chau (2017-2020) - Investigation
MONTHLY
EM&A REPORT FOR fEBRuary 2019
1.1
Background
1.1.1
The
Civil Engineering and Development Department (CEDD) is managing a number of
marine disposal facilities in Hong Kong waters, including the Contaminated Mud
Pits (CMPs) to the South of The Brothers (SB) and to the East of Sha Chau (ESC)
for the disposal of contaminated sediment, and open-sea disposal grounds
located to the South of Cheung Chau (SCC), East of Tung Lung Chau (ETLC) and
East of Ninepins (ENP) for the disposal of uncontaminated sediment. Two
Environmental Permits (EPs), EP-312/2008/A and EP-427/2011/A, were issued by
the Environmental Protection Department (EPD) to the CEDD, the Permit Holder,
on 28 November 2008 and 23 December 2011 for the Dredging, Management and
Capping of Contaminated Sediment Disposal Facilities at ESC CMP V and SB CMPs,
respectively.
1.1.2
Under
the requirements of the two EPs
for
ESC CMP V and SB CMPs, EM&A programmes which encompass water and sediment
chemistry, fisheries assessment, tissue and whole body analysis, sediment
toxicity and benthic recolonisation studies as set out in the EM&A Manuals
are required to be implemented. EM&A programmes
have been continuously carried out during the operation of the CMPs at ESC and
SB. A review of the collection and analysis of such environmental
data from the monitoring programme demonstrated that there had not been any adverse
environmental impacts resulting from disposal activities () (). The current programme will assess the impacts resulting
from dredging, disposal and capping operations of CMP V as well as capping
operations of SB CMPs.
1.1.3
The
present EM&A programme under Agreement No. CE 63/2016 (EP) covers the dredging,
disposal and capping operations of the ESC CMP V as well as the capping
operations of the SB CMPs (see Annex A for the EM&A
programme). The
scheduled EM&A programme for SB CMPs was completed in December 2018.
Detailed works schedule for ESC CMP V is shown in Figure 1.1. In
February 2019, disposal of contaminated mud at ESC CMP Vd was undertaken.
Figure
1.1 Works Schedule for ESC CMP V and SB CMPs
1.2
Reporting Period
1.2.1
This
Monthly EM&A
Report for
February 2019 covers the EM&A activities for the reporting month of
February 2019.
1.3
Details of Sampling
and Laboratory Testing Activities
1.3.1
The
following monitoring activities were undertaken for ESC CMP V in February 2019:
·
Water Column
Profiling
of ESC CMP Vd;
·
Routine Water
Quality Monitoring of ESC CMPs;
·
Pit Specific
Sediment Chemistry of ESC CMP Vd;
·
Cumulative
Impact Sediment Chemistry of ESC CMPs;
·
Sediment Toxicity
Tests of ESC CMPs;
and
·
Demersal
Trawling for ESC CMPs.
1.4
Details of Outstanding
Sampling and/or Analysis
1.4.1
No
outstanding
sampling
remained for February 2019.
1.4.2
The
following analyses are in progress and will be presented in the corresponding
quarterly report:
·
Species
identification of
the biota samples collected from Demersal Trawling for ESC CMPs in January and February 2019;
and
·
Sediment
Toxicity Tests of ESC CMPs
in February 2019.
1.5
Brief Discussion of
the Monitoring Results for ESC CMP V
1.5.1
Brief discussion
of the monitoring results of the following activities for ESC CMP V is
presented in this Monthly
EM&A Report for February 2019:
·
Water Column
Profiling of ESC CMP Vd in
February 2019;
·
Routine Water
Quality Monitoring of ESC CMPs in February 2019;
·
Pit Specific Sediment
Chemistry of ESC CMP Vd in
February 2019;
and
·
Cumulative Impact
Sediment Chemistry of ESC CMPs in
February 2019.
1.5.2
Water Column
Profiling of ESC CMP Vd – February 2019
1.5.3
Water
Column Profiling was undertaken at a total of two sampling stations
(Upstream and Downstream stations) on 14 February 2019. The
monitoring results have been assessed for compliance with the Water
Quality Objectives (WQOs) set by Environmental Protection Department
(EPD). This consists of a review of the EPD routine water quality
monitoring data for the dry season period (November to March) of 2008 - 2017
from stations in the Northwestern Water Control Zone (WCZ), where the ESC CMPs
are located (). For Salinity, the
averaged value obtained from the Reference (Upstream) station was used for the
basis as the WQO. Levels of Dissolved Oxygen (DO) and Turbidity were also
assessed for compliance with the Action and Limit Levels (see Table B1 of Annex B for details).
In-situ
Measurements
1.5.4
Analyses
of results for February 2019 indicated that levels of Salinity, pH and DO
complied with the WQOs at both Downstream and Upstream stations (Table B2 of Annex B). Levels of DO and Turbidity at all stations complied
with the Action and Limit Levels (Tables B1 and B2 of Annex B).
Laboratory Measurements for Suspended
Solids (SS)
1.5.5
Analyses
of results for February 2019 indicated that the SS levels at both Downstream
and Upstream stations complied with the WQO and the Action and Limit Levels at both
Downstream and Upstream stations (Tables B1 and
B2 of Annex B).
1.5.6
Overall,
the monitoring results indicated that the mud disposal operation at ESC CMP Vd
did not appear to cause any deterioration in water quality during this
reporting period.
1.5.7
Routine Water
Quality Monitoring of ESC CMPs – February 2019
1.5.8
Routine
Water Quality Monitoring of
ESC CMPs was undertaken on 19 February 2019. The
monitoring results have been assessed for compliance with the WQOs (see Section 1.5.3 for
details). The monitoring results are shown in Tables B3 and B4 of Annex B and Figures 1 - 10 of Annex C. A total of sixteen (16) monitoring stations were
sampled in February 2019 as shown in Figure 1.2.
In-situ Measurements
1.5.9
Graphical
presentation of the monitoring results (Temperature, DO, pH, Salinity and
Turbidity) is shown in Figures
1 - 6 of Annex C. Analyses of
results for February 2019 indicated that the levels of pH, Salinity
and DO complied with the WQOs at all stations (Impact, Intermediate, Reference
and Ma Wan stations) in February 2019.
1.5.10
The
levels of DO and Turbidity also complied with the Action and Limit Levels at
all stations (Table
B3 of Annex B; Figures 3 and 6 of Annex C).
1.5.11
Overall,
in-situ
measurement results of the Routine
Water Quality Monitoring indicated that the disposal operation at ESC CMP Vd did not
appear to cause any unacceptable impacts in water quality in February
2019.
Laboratory Measurements
1.5.12 Laboratory
analysis of February 2019 results indicated that concentrations of
Silver were below their limit of reporting at all stations. Arsenic,
Cadmium, Chromium, Copper Lead, Mercury, Nickel and Zinc were detected in February
2019 samples at all stations and the concentrations of these metals and
metalloids were similar amongst the stations (Table B4 of Annex B; Figure
7 of Annex C).
1.5.13 For
nutrients, concentrations of Total Inorganic Nitrogen (TIN) at Reference,
Impact and Intermediate stations were higher than the WQO (0.5 mg/L) in
February 2019 (Table
B4 of Annex B; Figure 8 of Annex C). It should be noted that due to the effect of the
Pearl River, the North Western WCZ has historically experienced higher levels
of TIN ([4]). Therefore, the exceedances of TIN WQO at these
stations are unlikely to be caused by the disposal operation at ESC CMP
Vd. Concentrations of Ammonia Nitrogen (NH3-N) and 5-day
Biochemical Oxygen Demand (BOD5) were generally similar amongst the
stations in February 2019 (Table B4 of Annex B; Figure
8
and 9 of Annex C).
1.5.14 Analyses of results
for February 2019 indicated that the SS levels were complied with the WQO (13.6 mg/L
for dry season) and the Action and Limit Levels at all stations (Tables B1 and B4 of Annex B; Figure
10 of Annex C).
1.5.15 Overall,
results of the Routine Water Quality Monitoring indicated that the disposal
operation at ESC CMP Vd did not appear to cause any unacceptable deterioration
in water quality in February 2019. Detailed statistical analysis
will be presented in the Quarterly Report to investigate any spatial and
temporal trends of potential concern.
1.5.16
Pit Specific
Sediment Chemistry of ESC CMP Vd – February 2019
1.5.17
Monitoring
locations for Pit
Specific Sediment Chemistry for ESC CMP Vd are shown in Figure 1.3. A
total of six (6) monitoring stations were sampled on 11 February 2019.
1.5.18
The
concentrations of all inorganic contaminants were lower than the Lower Chemical
Exceedance Level (LCEL) at Pit-Edge and Near-Pit stations in February
2019. The concentrations of Arsenic were higher than the LCEL at Active
Pit station ESC-NPAA. The concentrations of Chromium were higher than the
LCEL at Active Pit station ESC-NPAB and the concentrations of Copper, Lead,
Mercury, Nickel, Silver and Zinc were higher than the Upper Chemical Exceedance
Level (UCEL) at Active Pit station ESC-NPAB (Figures
11 and 12
of Annex C).
1.5.19
For
organic contaminants, the concentrations of Total Organic Carbon (TOC) varied
between stations and were higher at Active-Pit station ESC-NPAB in February
2019 (Figure 13
of Annex C). The concentrations of Tributyltin (TBT) were higher
at Active-Pit station ESC-NPAB (Figure 14 of Annex C). Total
Polychlorinated Biphenyls (PCBs), Total dichloro-diphenyl-trichloroethane (DDT)
and 4,4’-dichlorodiphenyldichloroethylene (DDE) concentrations were below the
limit of reporting at all stations, while Low and High Molecular Weight
Polycyclic Aromatic Hydrocarbons (PAHs) exceeded the UCEL at Active-Pit
ESC-NPAB station in February 2019 (Figure 15 of Annex C).
1.5.20
Whilst
the average concentration of Arsenic in the Earth’s crust is generally ~2
mg/kg, significantly higher Arsenic concentrations (median = 14 mg/kg) have
been recorded in Hong Kong’s onshore sediments ([5]). It is presumed that the natural concentrations of
Arsenic are similar in onshore and offshore sediments ([6]), and relatively high Arsenic levels may thus occur
throughout Hong Kong. Therefore, the LECL exceedances of Arsenic are
unlikely to be caused by the disposal operations at ESC CMP Vd but rather as a
result of naturally occurring deposits.
1.5.21
Considering
that the higher levels of other contaminants occurred within one Active-Pit
station ESC-NPAB only but not at the Pit-Edge and Near-Pit stations, there is
no evidence indicating any unacceptable environmental impacts to sediment
quality as a result of the contaminated mud disposal operations at ESC CMP Vd
in February 2019. Statistical analysis will be undertaken and
presented in the corresponding quarterly report to investigate whether there
are any unacceptable impacts in the area caused by the contaminated mud
disposal.
1.5.22
Cumulative
Impact Sediment Chemistry of ESC CMPs – February 2019
1.5.23
Monitoring
locations for Cumulative
Impact Sediment Chemistry for
ESC CMPs are shown in Figure 1.4. A
total of nine (9) monitoring stations were sampled on 12 and 13 February
2019.
1.5.24
Analyses
of results for the Cumulative
Impact Sediment Chemistry Monitoring indicated that the concentrations of
most inorganic contaminants were below the LCEL at all stations in February
2019, except concentrations of Arsenic were higher than the LCEL at Mid-field
stations ESC-RMA and ESC-RMB and Near-filed station ESC-RNA (Figures 16 and 17 of Annex C). As discussed in Section 1.5.20, the LECL
exceedances of Arsenic are unlikely to be caused by the disposal operations at
ESC CMP Vd but rather as a result of naturally occurring deposits.
1.5.25
For
organic contaminants, the concentrations of TOC varied between stations in
February 2019, with the generally lower concentrations of TOC recorded at
Far-field stations ESC-RFA and ESC-RFB (Figure 18 of Annex C). The concentrations of TBT were
higher at Ma Wan station (Figure
19 of Annex C). Low and High Molecular
Weight PAHs, PCBs, DDT and DDE concentrations were below the limit
of reporting at all stations in February 2019.
1.5.26
Overall,
there is no evidence indicating any unacceptable environmental impacts to
sediment quality as a result of the contaminated mud disposal operations at ESC
CMP Vd in February 2019. Statistical analysis will be undertaken and
presented in the corresponding quarterly report to investigate whether there
are any unacceptable impacts in the area caused by the contaminated mud
disposal.
1.6
Activities Scheduled
for the Next Month
1.6.1
The
following monitoring activities will be conducted in the next monthly
period of March 2019 for ESC CMP V (see Annex A for the sampling schedule ()):
·
Water Column
Profiling
of ESC CMP Vd;
and
·
Pit Specific Sediment
Chemistry of ESC CMP Vd.
1.7
Study Programme
1.7.1
A
summary of the Study Programme is presented in Annex D.