Agreement No. CE 63/2016 (EP)
Environmental Monitoring and Audit
for Disposal Facility to the East of Sha Chau (2017-2020) - Investigation
MONTHLY
EM&A REPORT FOR December 2018
1.1.1
The Civil Engineering and
Development Department (CEDD) is managing a number of marine disposal
facilities in Hong Kong waters, including the Contaminated Mud Pits (CMPs) to
the South of The Brothers (SB) and to the East of Sha Chau (ESC) for the
disposal of contaminated sediment, and open-sea disposal grounds located to the
South of Cheung Chau (SCC), East of Tung Lung Chau (ETLC) and East of Ninepins
(ENP) for the disposal of uncontaminated sediment. Two Environmental
Permits (EPs), EP-312/2008/A and EP-427/2011/A, were issued by the
Environmental Protection Department (EPD) to the CEDD, the Permit Holder, on 28
November 2008 and 23 December 2011 for the Dredging, Management and Capping of
Contaminated Sediment Disposal Facilities at ESC CMP V and SB CMPs,
respectively.
1.1.2
Under the requirements of the
two EPs for ESC CMP
V and SB CMPs, EM&A programmes which encompass water and sediment
chemistry, fisheries assessment, tissue and whole body analysis, sediment
toxicity and benthic recolonisation studies as set out in the EM&A Manuals
are required to be implemented. EM&A programmes
have been continuously carried out during the operation of the CMPs at ESC and
SB. A review of the collection and analysis of such environmental
data from the monitoring programme demonstrated that there had not been any
adverse environmental impacts resulting from disposal activities () (). The current programme will assess the impacts resulting from
dredging, disposal and capping operations of CMP V as well as capping
operations of SB CMPs.
1.1.3
The present EM&A programme
under Agreement
No. CE 63/2016 (EP) covers the dredging, disposal and capping operations of the
ESC
CMP V as well as the capping operations of the SB CMPs (see Annex A for the EM&A programme). Detailed
works schedule for ESC CMP V and SB CMPs is shown in Figure 1.1. In
December 2018, the following work was being undertaken:
·
Disposal
of contaminated mud at ESC CMP Vd.
Figure 1.1 Works
Schedule for ESC
CMP V and SB CMPs
1.2
Reporting Period
1.2.1
This Monthly
EM&A Report for
December 2018 covers the EM&A
activities for the reporting month of December 2018.
1.3
Details of Sampling
and Laboratory Testing Activities
1.3.1
The following monitoring activities were
undertaken for ESC CMP V in December 2018:
·
Water
Column Profiling
of ESC CMP Vd;
·
Pit
Specific Sediment Chemistry of ESC CMP Vd;
and
·
Cumulative
Impact Sediment Chemistry of ESC CMPs.
1.3.2
The following monitoring activity was undertaken for SB CMP
in December 2018:
·
Benthic
Recolonisation Studies of SB CMPs.
1.4
Details of Outstanding
Sampling and/or Analysis
1.4.1
No outstanding sampling remained for December 2018.
1.4.2
The following analyses are in progress and will be presented
in the corresponding quarterly report:
·
Species
identification and analyses of sediment samples
collected for Benthic Recolonisation Studies of SB CMPs in December
2018.
1.5.1
Brief discussion
of the monitoring results of the following activities for ESC CMP V is
presented in this Monthly
EM&A Report for December
2018:
·
Water
Column Profiling of ESC CMP Vd in December
2018;
·
Pit
Specific Sediment Chemistry of ESC CMP Vd in December 2018; and
·
Cumulative
Impact Sediment Chemistry of ESC CMPs in December 2018.
1.5.2
Water
Column Profiling of ESC CMP Vd – December 2018
1.5.3
Water
Column Profiling was undertaken at a total of two sampling stations
(Upstream and Downstream stations) on 6 December 2018. The monitoring results
have been assessed for compliance with the Water Quality
Objectives (WQOs) set by Environmental Protection Department (EPD). This
consists of a review of the EPD routine water quality monitoring data for the
dry season period (November to March) of 2007 - 2016 from
stations in the Northwestern Water Control Zone (WCZ), where the ESC CMPs are
located (). For
Salinity, the averaged value obtained from the Reference (Upstream) station
was used for the basis as the WQO. Levels of Dissolved
Oxygen (DO) and Turbidity were also assessed for compliance with the Action and
Limit Levels (see Table
B1 of Annex B for details).
In-situ Measurements
1.5.4
Analyses of results for
December 2018 indicated that levels of Salinity, pH and DO complied
with the WQOs at both Downstream and Upstream stations (Table B2 of Annex B). Levels of DO and Turbidity at all stations complied with the Action
and Limit Levels (Tables
B1 and B2 of Annex B).
Laboratory Measurements for
Suspended Solids (SS)
1.5.5
Analyses of results for December
2018 indicated that the SS levels at both Downstream and Upstream stations
complied with the WQO and the Action and Limit Levels at both Downstream and
Upstream stations (Tables
B1 and B2 of Annex B).
Overall, the monitoring
results indicated that the mud disposal operation at ESC CMP Vd did not appear
to cause any deterioration in water quality during this reporting period.
1.5.6
Pit
Specific Sediment Chemistry of ESC CMP Vd – December 2018
1.5.7
Monitoring
locations for Pit
Specific Sediment Chemistry for ESC CMP Vd are shown in Figure 1.2. A
total of six (6) monitoring stations were sampled on 3 December 2018.
1.5.8
The
concentrations of all inorganic contaminants were lower than the Lower Chemical
Exceedance Level (LCEL) at all stations in December
2018 (Figures 1
and 2 of Annex C).
1.5.9
For organic
contaminants, the concentrations of Total Organic Carbon (TOC) varied between
stations and were generally higher at Pit-Edge ESC-NEAA and Active-Pit ESC-NPAA
stations, while generally lower at Near-Pit ESC-NNAA and Pit-Edge ESC-NEAB
stations in December 2018 (Figure 3 of Annex C). Tributyltin (TBT), Low and High Molecular Weight Polycyclic
Aromatic Hydrocarbons (PAHs), Total Polychlorinated Biphenyls (PCBs) Total
dichloro-diphenyl-trichloroethane (DDT) and
4,4’-dichlorodiphenyldichloroethylene (DDE) concentrations were below the limit
of reporting at all stations in December 2018.
1.5.10
Overall,
there is no evidence indicating any unacceptable environmental impacts to
sediment quality as a result of the contaminated mud disposal operations at ESC
CMP Vd in December 2018. Statistical analysis will be undertaken and
presented in the corresponding quarterly report to investigate whether there
are any unacceptable impacts in the area caused by the contaminated mud
disposal.
1.5.11
Cumulative
Impact Sediment Chemistry of ESC CMP V – December 2018
1.5.12
Monitoring
locations for Cumulative
Impact Sediment Chemistry for
ESC CMP V are shown
in Figure 1.3. A
total of nine (9) monitoring stations were sampled on 3 and 4 December 2018.
1.5.13
Analyses of
results for the Cumulative
Impact Sediment Chemistry Monitoring indicated that the concentrations of most inorganic
contaminants were below the LCEL at all stations in December
2018, except concentrations of Arsenic were higher than the LCEL at Mid-field
stations ESC-RMA and ESC-RMB (Figures
4 and 5 of Annex C). Whilst the average concentration of Arsenic in the Earth’s
crust is generally ~2 mg/kg, significantly higher Arsenic concentrations
(median = 14 mg/kg) have been recorded in Hong Kong’s onshore sediments ([4]). It is
presumed that the natural concentrations of Arsenic are similar in onshore and
offshore sediments ([5]),
and relatively high Arsenic levels may thus occur throughout Hong Kong.
Therefore, the LECL exceedances of Arsenic are unlikely to be caused by the
disposal operations at ESC CMP Vd but rather as a result of naturally occurring
deposits.
1.5.14
For organic contaminants, the
concentrations of TOC varied between stations in December 2018, with the
generally lower concentrations of TOC recorded at Far-field station ESC-RFB (Figure 6 of Annex C). The concentrations of TBT were
generally higher at Near-field station ESC-RNB (Figure 7 of Annex C). Low and High Molecular Weight PAHs, PCBs, DDT
and DDE concentrations were below the limit of reporting at all stations
in December 2018.
1.5.15
Overall, there is no evidence
indicating any unacceptable environmental impacts to sediment quality as a
result of the contaminated mud disposal operations at ESC CMP Vd in December 2018. Statistical
analysis will be undertaken and presented in the corresponding quarterly report
to investigate whether there are any unacceptable impacts in the area caused by
the contaminated mud disposal.
1.6
Activities Scheduled
for the Next Month
1.6.1
The following monitoring activities will be conducted
in the next monthly period of January 2019 for ESC CMP V (see
Annex A for the sampling
schedule):
·
Water
Column Profiling
of ESC CMP Vd;
·
Routine Water Quality Monitoring of ESC CMPs;
·
Pit
Specific Sediment Chemistry of ESC CMP Vd; and
·
Demersal
Trawling for ESC CMPs.
1.7
Study Programme
1.7.1
A summary of the Study Programme is
presented in Annex D.