Agreement No. CE
23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
55th MONTHLY PROGRESS REPORT FOR March 2017
1.1.1
Since early 1990s, contaminated sediment ([1]) arising from various
construction works (e.g. dredging and reclamation projects) in Hong Kong has
been disposed of at a series of seabed pits at East of Sha Chau (ESC). In late 2008, a review indicated that
the existing and planned facilities at ESC would not be able to meet the
disposal demand after 2012. In
order to meet this demand, the Hong Kong Special Administrative Region
Government (HKSARG) decided to implement a new contained aquatic disposal (CAD)
([2]) facility at the South of The Brothers
(SB CMPs) which had been under consideration for a number of years.
1.1.2
The environmental acceptability of the construction and
operation of the Project had been confirmed by findings of the associated
Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact Assessment
Ordinance (Cap.
499) (EIAO) in
September 2005 (EIA
Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA recommendation, prior to
commencement of construction works for the SB CMPs, the Civil Engineering and
Development Department (CEDD) undertook a detailed review and update of the EIA
findings for the SB site ([4]).
Findings of the EIA review undertaken in 2009/ 2010 confirmed that the
construction and operation of the SB site had been predicted to be
environmentally acceptable.
1.1.4
Environmental
Permits (EPs) (EP-312/2008/A and EP-427/2011/A) were
issued by the Environmental Protection Department (EPD) to the CEDD, the Permit
Holder, on 28 November 2008 for ESC CMP V and on 23 December 2011 for SB CMPs,
respectively. Under the
requirements of the
EPs, an Environmental Monitoring and Audit (EM&A) programme as set out
in the EM&A
Manuals ()
()
is required to be implemented for the CMPs.
1.1.5
The present EM&A programme under Agreement No. CE 23/2012
(EP) covers the dredging, disposal and capping operations of the SB CMPs as well as ESC CMPs. Detailed works schedule for ESC CMPs and
SB CMPs is shown in Figure 1.1. In March 2017, the following works were
being undertaken:
¡P Disposal of contaminated mud at
ESC CMP Vd.
Figure 1.1 Works Schedule
for ESC CMPs and SB CMPs
1.2
Reporting Period
1.2.1
This 55th
Monthly Progress Report covers the EM&A activities for
the reporting month of March 2017.
1.3
Details of Sampling and
Laboratory Testing Activities
1.3.1
The following monitoring activities
have been undertaken for ESC CMPs in March 2017:
¡P
Water Column Profiling of ESC CMP Vd was
undertaken on 16 March 2017; and
¡P
Pit Specific Sediment Chemistry of ESC CMP Vd was
undertaken on 17 March 2017.
1.3.2
No monitoring activities were
scheduled to be undertaken for SB CMPs in March 2017.
1.4.1
No outstanding sampling and analysis remained for March
2017.
1.5
Brief Discussion of the
Monitoring Results for ESC CMPs
1.5.1
Brief discussion of the monitoring
results of the following activities for ESC CMPs is presented in this 55th
Monthly Progress Report:
¡P
Water Column Profiling of ESC CMP Vd in March 2017;
¡P
Pit Specific Sediment Chemistry of ESC CMP Vd in
January, February and March 2017; and
¡P
Cumulative Impact Sediment Chemistry of ESC CMPs in February 2017.
1.5.2
Water
Column Profiling of ESC CMP Vd
¡V March 2017
1.5.3
Water Column Profiling was undertaken at a total of two sampling stations (Upstream and
Downstream stations) on 16 March 2017.
The monitoring results have been assessed for compliance with the Water Quality Objectives (WQOs) set by Environmental
Protection Department (EPD). This consists of a review of the EPD routine water quality monitoring
data for the dry season period (November to March) of 2006 - 2015 from stations in the Northwestern
Water Control Zone (WCZ), where the ESC CMPs are located (). For Salinity, the averaged value
obtained from the Reference (Upstream) station was used for the basis as the WQO. Levels of Dissolved Oxygen (DO) and Turbidity were also assessed for
compliance with the Action and Limit Levels (see Table B1 of Annex
B for details).
In-situ
Measurements
1.5.4
Analyses of results for March 2017
indicated that levels of DO and pH complied with the WQOs at both Downstream
and Upstream stations (Table B2 of Annex B). In addition, DO and
Turbidity at all stations complied with the Action and Limit Levels (Tables
B1 and B2 of Annex
B).
Laboratory
Measurements for Suspended Solids (SS)
1.5.5
Analyses of results for March 2017
indicated that the SS levels complied with the WQO and the Action and Limit
Levels at Downstream station (Tables B1 and B2 of
Annex B). SS levels at Upstream station were higher than the WQO, however the SS
levels at Upstream station complied with the Action and Limit Levels.
1.5.6
Overall, the monitoring results
indicated that the mud disposal operation at ESC CMP Vd
did not appear to cause any deterioration in water quality during this
reporting period.
1.5.7
Pit Specific Sediment Chemistry of ESC CMP Vd ¡V January, February
and March 2017
1.5.8
Monitoring locations for Pit Specific Sediment Chemistry for ESC CMP Vd are shown in Figure
1.2. A total of six (6)
monitoring stations were sampled in January, February
and March 2017.
1.5.9
The concentrations of all inorganic contaminants were lower than the Lower Chemical Exceedance Level (LCEL) at all stations in February and March 2017 (Figures 1, 2, 5, 6, 8 and 9 of Annex C).
1.5.10
For organic contaminants, the
concentrations of Total Organic Carbon (TOC) were similar amongst the stations in January, February and
March 2017 (Figures
3, 7 and 10 of Annex
C). The concentrations of tributyltin (TBT) were similar
amongst the stations in January and March 2017 (Figures 4 and 7 of Annex C) whilst the concentrations of TBT were below the limit of
reporting at all stations in February 2017. Low and High Molecular Weight Polycyclic
Aromatic Hydrocarbons (PAHs), Total Polychlorinated Biphenyls (PCBs), Total dichloro-diphenyl-trichloroethane
(DDT) and 4,4¡¦-dichlorodiphenyldichloroethylene (DDE) concentrations were below
the limit of reporting at all stations in January, February and March 2017.
1.5.11
Overall, there is no evidence
indicating any unacceptable environmental impacts to sediment quality as a
result of the contaminated mud disposal operations at ESC CMP Vd in January, February and March 2017. Statistical analysis will be undertaken
and presented in the corresponding quarterly report to investigate whether
there are any unacceptable impacts in the area caused by the contaminated mud
disposal.
1.5.12
Cumulative
Impact Sediment Chemistry of ESC CMPs ¡V February 2017
1.5.13
Monitoring locations for Cumulative Impact Sediment Chemistry for ESC CMPs are shown in Figure 1.3. A total of
nine (9) monitoring stations were sampled in
February 2017.
1.5.14
Analyses of results for the Cumulative Impact Sediment Chemistry Monitoring indicated that the concentrations
of all inorganic contaminants were below
the LCEL in February 2017 (Figures
12 and 13 of Annex C).
1.5.15
For organic contaminants, concentrations of TOC were observed to be similar
amongst all stations (Figure
14 of Annex C).
Concentrations of TBT were
recorded to be higher at Ma Wan station (Figure
15 of Annex C). Low and High Molecular Weight PAHs,
PCBs, DDT and DDE concentrations were
recorded below the limit of reporting at all stations.
1.5.16
Overall, there is no evidence
indicating any unacceptable environmental impacts to sediment quality as a
result of the contaminated mud disposal operations at ESC CMP Vd in February 2017. Statistical analysis will be
undertaken and presented in the corresponding quarterly report to investigate
whether there are any unacceptable impacts in the area caused by the
contaminated mud disposal.
1.6
Activities Scheduled for the Next Month
1.6.1
The following monitoring activities will be conducted in the next monthly period of April
2017 for ESC CMPs (see Annex
A for the sampling schedule):
¡P
Water Column Profiling of ESC CMP Vd;
¡P
Routine Water Quality Monitoring of ESC CMPs; and
¡P
Pit Specific Sediment Chemistry of ESC CMP Vd.
1.6.2
No monitoring activities are scheduled in the next monthly period of April
2017 for SB CMPs.
1.6.3
The monitoring activities starting
in April 2017 will be reported under a new consultancy Agreement No.
CE 63/2016 (EP) Environmental Monitoring and Audit for Disposal Facility to the
East of Sha Chau (2017-2020) ¡V Investigation.
1.7.1
A summary of the Study programme is
presented in Annex
D.