Agreement No. CE
23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
53rd MONTHLY PROGRESS REPORT FOR January 2017
1.1.1
Since
early 1990s, contaminated sediment ([1]) arising from various construction works
(e.g. dredging and reclamation projects) in Hong Kong has been disposed of at a
series of seabed pits at East of Sha Chau (ESC). In late 2008, a review indicated that
the existing and planned facilities at ESC would not be able to meet the
disposal demand after 2012. In
order to meet this demand, the Hong Kong Special Administrative Region
Government (HKSARG) decided to implement a new contained aquatic disposal (CAD)
([2]) facility at the South of The Brothers
(SB CMPs) which had been under consideration for a number of years.
1.1.2
The
environmental acceptability of the construction and operation of the Project
had been confirmed by findings of the associated Environmental Impact
Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact Assessment
Ordinance (Cap.
499) (EIAO) in
September 2005 (EIA
Register No.: AEIAR-089/2005).
1.1.3
In
accordance with the EIA recommendation, prior to commencement of construction
works for the SB CMPs, the Civil Engineering and Development Department (CEDD)
undertook a detailed review and update of the EIA findings for the SB site ([4]).
Findings of the EIA review undertaken in 2009/ 2010 confirmed that the
construction and operation of the SB site had been predicted to be
environmentally acceptable.
1.1.4
Environmental Permits (EPs) (EP-312/2008/A and EP-427/2011/A) were
issued by the Environmental Protection Department (EPD) to the CEDD, the Permit
Holder, on 28 November 2008 for ESC CMP V and on 23 December 2011 for SB CMPs,
respectively. Under the
requirements of the
EPs, an Environmental Monitoring and Audit (EM&A) programme as set out
in the EM&A
Manuals ()
()
is required to be implemented for the CMPs.
1.1.5
The
present EM&A programme under Agreement No. CE 23/2012 (EP) covers the
dredging, disposal and capping operations of the SB CMPs as well as ESC CMPs. Detailed works schedule for ESC CMPs and
SB CMPs is shown in Figure
1.1. In January 2017, the following works
were being undertaken:
¡P Disposal of contaminated mud at
ESC CMP Vd.
Figure 1.1 Works Schedule for ESC CMPs and SB
CMPs
1.2
Reporting
Period
1.2.1
This 53rd
Monthly Progress Report covers the EM&A activities for
the reporting month of January 2017.
1.3
Details of Sampling and
Laboratory Testing Activities
1.3.1
The following monitoring
activities have been undertaken for ESC CMPs in January 2017:
¡P
Water Column Profiling of ESC CMP Vd was undertaken on 3 January 2017;
¡P
Demersal Trawling of ESC CMPs was undertaken on 4 and 5 January 2017;
¡P
Routine Water Quality Monitoring of ESC CMPs was undertaken on 5 January 2017; and
¡P
Pit Specific Sediment Chemistry of ESC CMP Vd was undertaken on 12 January 2017.
1.3.2
No monitoring activities were
scheduled to be undertaken for SB CMPs in January 2017.
1.4.1
No outstanding sampling remained for January 2017.
1.4.2
A summary of field activities
conducted are presented in Annex
A. The
following analyses are in progress and will be presented in the corresponding
quarterly report:
¡P
Species
identification of the biota samples collected from Demersal Trawling for ESC CMPs
in January 2017.
1.4.3
The following laboratory analyses are in progress during the
preparation of this monthly report and will be presented in the next monthly
report once the data are available:
¡P
Laboratory
analyses of sediment samples collected for Pit Specific
Sediment Chemistry of ESC CMP Vd in January 2017.
1.5.1
Brief discussion of the monitoring
results of the following activities for ESC CMPs is presented in this 53rd
Monthly Progress Report:
¡P
Water Column Profiling of ESC CMP Vd in January 2017;
¡P
Routine Water Quality Monitoring of ESC CMPs in January 2017; and
¡P
Cumulative Impact Sediment Chemistry of ESC CMPs in
December 2016.
1.5.2
Water
Column Profiling of ESC CMP Vd
¡V January 2017
1.5.3
Water
Column Profiling was undertaken at a total of two
sampling stations (Upstream and Downstream stations) on 3 January 2017. The monitoring results have been assessed for
compliance with the Water Quality Objectives (WQOs) set by Environmental
Protection Department (EPD). This consists of a review of the EPD routine water quality monitoring
data for the dry season period (November to March) of 2006 - 2015 from stations in the Northwestern
Water Control Zone (WCZ), where the ESC CMPs are located (). For Salinity, the averaged value
obtained from the Reference (Upstream) station was used for the basis as the WQO. Levels of Dissolved Oxygen (DO) and Turbidity were also assessed for
compliance with the Action and Limit Levels (see Table B1 of Annex
B for details).
In-situ
Measurements
1.5.4
Analyses of results for January 2017 indicated that levels
of DO and pH complied
with the WQOs at both Downstream and Upstream stations
(Table B2 of Annex B). In addition, DO and
Turbidity at all stations complied with the Action and Limit Levels (Tables
B1 and B2 of Annex
B).
Laboratory
Measurements for Suspended Solids (SS)
1.5.5
Analyses of results for January 2017 indicated that the SS
levels compiled with the WQO at both Upstream and Downstream stations. In addition, SS levels for both Upstream
and Downstream stations complied with the Action and Limit Levels (Tables
B1 and B2 of Annex
B).
1.5.6
Overall, the monitoring results indicated that the mud
disposal operation at ESC CMP Vd did not appear to cause
any deterioration in water quality during this reporting period.
1.5.7
Routine
Water Quality Monitoring of ESC CMPs ¡V January 2017
1.5.8
Routine
Water Quality Monitoring of ESC CMPs was undertaken on 5 January 2017. The monitoring results have been assessed for
compliance with the WQOs (see Section 1.5.3 for details). The monitoring results are shown in Tables B3 and
B4 of Annex
B and Figures 1 - 10 of Annex
C. A total of ten (10) monitoring stations
were sampled in January 2017 as shown in Figure 1.2.
In-situ Measurements
1.5.9
Graphical presentation of the monitoring results
(Temperature, DO, pH, Salinity and Turbidity) is shown in Figures
1 - 6 of Annex C. Analyses of results for January 2017 indicated that the levels of pH,
Salinity and DO complied with the WQOs at all stations
(Impact, Intermediate, Reference and Ma Wan stations) in January 2017 (Table B3 of Annex
B; Figures 1, 3 and 5 of Annex C).
1.5.10
The levels of DO and Turbidity complied with the Action and
Limit Levels at all stations (Table B3 of Annex B; Figures
3 and 6 of Annex C).
1.5.11
Overall, in-situ measurement
results of the Routine Water Quality Monitoring indicated that the disposal operation at ESC CMP Vd did not appear to cause any unacceptable impacts in water quality in January 2017.
Laboratory Measurements
1.5.12
Laboratory analysis of January 2017 results indicated that
concentrations of Cadmium, Chromium, Lead, Silver and Mercury were below their
limit of reporting at all stations.
Arsenic, Nickel, Copper and Zinc were detected in January 2017 samples and the concentrations of these metals and metalloids were similar amongst stations (Table B4 of Annex
B; Figure 7 of Annex
C).
1.5.13
For nutrients, concentrations of Total Inorganic Nitrogen
(TIN) at Reference and Intermediate stations in January 2017 were higher than the WQO (0.5
mg/L) (Table B4 of Annex B; Figure 8 of Annex C). It should be
noted that due to the effect of Pearl River, the North Western WCZ has
historically experienced higher levels of TIN ([8]).
Therefore, the exceedances of TIN WQO at these stations are unlikely to
be caused by the disposal operation at ESC CMP Vd. Concentrations of Ammonia Nitrogen (NH3-N)
were relatively similar amongst all stations (Table B4 of Annex
B; Figure 8 of Annex
C). Levels of 5-day Biochemical Oxygen
Demand (BOD5) appear to be higher at Impact stations in January 2017 (Table B4 of Annex
B; Figure 9 of Annex
C).
1.5.14
Analyses of results for January 2017 indicated
that the SS levels at Reference stations
were higher than the WQO (13.2 mg/L for dry season), however SS levels at all stations complied with the
Action and Limit Levels (Tables B1
and B4 of Annex B; Figure 10 of Annex C).
1.5.15
Overall, results of the Routine
Water Quality Monitoring indicated that the disposal
operation at ESC CMP Vd did not appear to cause any
unacceptable deterioration in water quality in January 2017. Detailed statistical analysis will be
presented in the Quarterly Report to investigate any spatial and temporal
trends of potential concern.
1.5.16
Cumulative
Impact Sediment Chemistry of ESC CMPs ¡V December 2016
1.5.17
Monitoring locations for Cumulative
Impact Sediment Chemistry for ESC
CMPs are shown in Figure 1.3. A total of nine (9) monitoring stations
were sampled in
December 2016.
1.5.18
Analyses of results for the Cumulative
Impact Sediment Chemistry Monitoring indicated that
the concentrations of all inorganic contaminants were below
the Lower Chemical Exceedance Level (LCEL) in December 2016 (Figures 11
and 12 of Annex C).
1.5.19
For
organic contaminants, concentrations of Total Organic Carbon (TOC) were observed to be similar amongst all
stations (Figure
13 of Annex C). Concentrations of Tributyltin (TBT) were recorded to be higher at Ma Wan station (Figure 14 of Annex C). Low and High Molecular Weight Polycyclic Aromatic Hydrocarbons (PAHs),
Total Polychlorinated Biphenyls (PCBs), Total dichloro-diphenyl-trichloroethane (DDT) and
4,4¡¦-dichlorodiphenyldichloroethylene (DDE) concentrations were
recorded below the limit of reporting at all stations.
1.5.20
Overall, there is no evidence indicating any unacceptable
environmental impacts to sediment quality as a result of the contaminated mud
disposal operations at ESC CMP Vd in December
2016. Statistical
analysis will be undertaken and presented in the quarterly report to
investigate whether there are any unacceptable impacts in the area caused by
the contaminated mud disposal.
1.6.1
The following monitoring activities will be conducted in the next monthly period of February
2017 for ESC CMPs:
¡P
Water Column Profiling of ESC CMP Vd;
¡P
Routine Water Quality Monitoring of ESC CMPs;
¡P
Cumulative Impact Sediment Chemistry of ESC CMPs;
¡P
Pit Specific Sediment Chemistry of ESC CMP Vd;
¡P
Sediment Toxicity Test of ESC
CMPs; and
¡P
Demersal Trawling of ESC CMPs.
1.6.2
No monitoring activities are scheduled
in the next monthly period of February 2017 for SB CMPs.
1.6.3
The sampling schedule is presented
in Annex A.
1.7.1
A summary of the Study programme is
presented in Annex
D.