Agreement No. CE
23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
52nd MONTHLY PROGRESS REPORT FOR December 2016
1.1.1
Since
early 1990s, contaminated sediment ([1]) arising from various construction works
(e.g. dredging and reclamation projects) in Hong Kong has been disposed of at a
series of seabed pits at East of Sha Chau (ESC). In late 2008, a review indicated that
the existing and planned facilities at ESC would not be able to meet the
disposal demand after 2012. In
order to meet this demand, the Hong Kong Special Administrative Region
Government (HKSARG) decided to implement a new contained aquatic disposal (CAD)
([2]) facility at the South of The Brothers
(SB CMPs) which had been under consideration for a number of years.
1.1.2
The
environmental acceptability of the construction and operation of the Project
had been confirmed by findings of the associated Environmental Impact
Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact Assessment
Ordinance (Cap.
499) (EIAO) in
September 2005 (EIA
Register No.: AEIAR-089/2005).
1.1.3
In
accordance with the EIA recommendation, prior to commencement of construction
works for the SB CMPs, the Civil Engineering and Development Department (CEDD)
undertook a detailed review and update of the EIA findings for the SB site ([4]).
Findings of the EIA review undertaken in 2009/ 2010 confirmed that the
construction and operation of the SB site had been predicted to be environmentally
acceptable.
1.1.4
Environmental Permits (EPs) (EP-312/2008/A and EP-427/2011/A) were
issued by the Environmental Protection Department (EPD) to the CEDD, the Permit
Holder, on 28 November 2008 for ESC CMP V and on 23 December 2011 for SB CMPs,
respectively. Under the
requirements of the
EPs, an Environmental Monitoring and Audit (EM&A) programme as set out
in the EM&A
Manuals ()
()
is required to be implemented for the CMPs.
1.1.5
The
present EM&A programme under Agreement No. CE 23/2012 (EP) covers the
dredging, disposal and capping operations of the SB CMPs as well as ESC CMPs. Detailed works schedule for ESC CMPs and
SB CMPs is shown in Figure
1.1. In December 2016, the following works
were being undertaken:
¡P Dredging operation at ESC CMP Vb;
¡P Disposal of contaminated mud at
ESC CMP Vd; and
¡P Capping operation at SB CMP 2.
Figure 1.1 Works Schedule for ESC CMPs and SB
CMPs
1.2
Reporting Period
1.2.1
This 52nd Monthly
Progress Report covers the EM&A activities for
the reporting month of December 2016.
1.3
Details of Sampling and
Laboratory Testing Activities
1.3.1
The following monitoring activities have been undertaken for
ESC CMPs in December 2016:
¡P
Water Column Profiling of ESC CMP Vd was undertaken on 1 December 2016;
¡P
Water Quality Monitoring During
Dredging of ESC CMP Vb was undertaken on 2, 5, 7, 9, 12, 14, 16, 19, 21, 23, 27 and 29 December 2016;
¡P
Pit Specific Sediment Chemistry of ESC CMP Vd was undertaken on 8 December 2016;
¡P
Benthic Recolonisation
Studies of ESC CMP IV was
undertaken on 15 December 2016; and
¡P
Cumulative Impact Sediment Chemistry of ESC CMPs was undertaken on 20 and 22 December 2016.
1.3.2
The following monitoring activities have been undertaken for SB CMPs in
December 2016:
¡P
Water Quality Monitoring During Capping of SB
CMPs was undertaken on 6
December 2016; and
¡P
Benthic Recolonisation
Studies of SB CMP 1 was undertaken on 13
December 2016.
1.4.1
No outstanding sampling remained for
December 2016.
1.4.2
A summary of field activities conducted are presented in Annex A. The
following analyses are in progress and will be presented in the corresponding
quarterly report:
¡P
Laboratory
analyses of sediment samples collected for Benthic Recolonisation
Studies of ESC CMPs and SB CMP 1 in December 2016.
1.4.3
The
following laboratory analyses are in progress during the preparation of this
monthly report and will be presented in the next monthly report once the data
are available:
¡P
Laboratory analyses of sediment samples
collected for Cumulative Impact
Sediment Chemistry of ESC CMPs
in December 2016.
1.5.1
Brief discussion of the monitoring
results of the following activities for ESC CMPs is presented in this 52nd
Monthly Progress Report:
¡P
Water Quality Monitoring During
Dredging of ESC CMP Vb in December 2016;
¡P
Water Column Profiling of ESC CMP Vd in December 2016; and
¡P
Pit Specific Sediment Chemistry of ESC CMP Vd in November and December 2016.
1.5.2
Impact
Water Quality Monitoring during Dredging Operations of ESC CMP Vb ¡V December 2016
1.5.3
Water quality monitoring was conducted three times per week during the
reporting period on 2, 5, 7,
9, 12, 14, 16, 19, 21, 23, 27 and 29 December
2016. During each survey day,
monitoring was conducted during both mid-ebb and mid-flood tides at two
Reference (Upstream) stations and five Impact (Downstream) stations around the dredging operations at ESC CMP
Vb. Monitoring was also conducted
at one Sensitive Receiver station situated in Ma Wan.
A total of eight (8) stations were monitored and locations of the
sampling stations are shown in Figure
1.2.
1.5.4
Monitoring results are presented in Table B1 of Annex
B. Daily dredging volume in December 2016 is
reported in Annex
C. Levels of Dissolved Oxygen (DO),
Turbidity and Suspended Solid (SS) generally
complied with the Action and Limit Levels (see Table
B2 of Annex B for details) set in the Baseline
Monitoring Report (),
except for the following occasions discussed in Table 1.1 below.
1.5.5
The results indicated that the dredging operations at ESC
CMP Vb did not appear to cause any unacceptable
deterioration in water quality during this reporting period. Therefore, no further action, except for
those recommended in the Environmental Permit (EP-312/2008/A), are considered necessary for the dredging operations.
1.5.6
Water
Column Profiling of ESC CMP Vd
¡V December 2016
1.5.7
Water
Column Profiling was undertaken at a total of two
sampling stations (Upstream and Downstream stations) on 1 December 2016. The monitoring results have been assessed for
compliance with the Water Quality Objectives (WQOs) set by Environmental
Protection Department (EPD). This consists of a review of the EPD routine water quality monitoring
data for the dry season period (November to March) of 2006 - 2015 from stations in the Northwestern
Water Control Zone (WCZ), where the ESC CMPs are located (). For Salinity, the averaged value
obtained from the Reference (Upstream) station was used for the basis as the WQO. Levels of DO and Turbidity were also assessed for compliance with the
Action and Limit Levels (see Table B2 of Annex B for details).
In-situ
Measurements
1.5.8
Analyses of results for December 2016 indicated that levels of DO and pH complied
with the WQOs at both Downstream and Upstream stations
(Table B3 of Annex B). In addition, DO and
Turbidity at all stations complied with the Action and Limit Levels (Tables
B2 and B3 of Annex
B).
Laboratory
Measurements for Suspended Solids (SS)
1.5.9
Analyses of results for December 2016 indicated that the SS
levels were higher than the WQO at both Upstream and Downstream stations. However, both Upstream and Downstream
stations complied with the Action and Limit Levels (Tables B2 and B3 of Annex
B).
1.5.10
Overall, the monitoring results indicated that the mud
disposal operation at ESC CMP Vd did not appear to
cause any deterioration in water quality during this reporting period.
1.5.11
Pit
Specific Sediment Chemistry of ESC CMP Vd
¡V November and
December 2016
1.5.12
Monitoring locations for Pit Specific
Sediment Chemistry for ESC CMP Vd are shown in Figure 1.3. A total of six
(6) monitoring stations were sampled in November and December 2016.
1.5.13
The concentrations of all inorganic contaminants were
lower than the Lower Chemical Exceedance Level (LCEL) at all stations in November and December 2016 (Figures 1, 2,
5 and 6 of Annex D).
1.5.14
For organic contaminants, the concentrations of Total
Organic Carbon (TOC) were similar amongst the stations in November and December
2016 (Figures 3 and 7 of Annex
D). Tributyltin (TBT) concentrations were higher at Active Pit
station ESC-NPAA and Active Pit station ESC-NPAB in November and December 2016,
respectively (Figures 4 and 8 of Annex
D). Low and High Molecular Weight Polycyclic
Aromatic Hydrocarbons (PAHs), Total Polychlorinated Biphenyls (PCBs), Total dichloro-diphenyl-trichloroethane
(DDT) and 4,4¡¦-dichlorodiphenyldichloroethylene (DDE) concentrations were below
the limit of reporting at all stations in November and December 2016.
1.5.15
Overall, there is no evidence indicating any unacceptable
environmental impacts to sediment quality as a result of the contaminated mud
disposal operations at ESC CMP Vd in November
and December 2016. Statistical analysis will be undertaken
and presented in the quarterly report to investigate whether there are any
unacceptable impacts in the area caused by the contaminated mud disposal.
1.6.1
Brief discussion of the monitoring
results of the following activities for SB CMPs is presented in this 52nd
Monthly Progress Report:
¡P
Water Quality Monitoring during Capping Operations of SB CMPs
in December 2016.
1.6.2
Water
Quality Monitoring during Capping of SB CMPs ¡V December
2016
1.6.3
The monitoring results obtained during
December 2016 sampling in the dry season have
been assessed for compliance with the WQOs (see Section 1.5.7 for details). Levels of DO and Turbidity were also assessed for compliance with the
Action and Limit Levels (see Table B4 of Annex
B for details). A total of fourteen (14) monitoring stations were sampled in December 2016 as
shown in Figure 1.4. Graphical presentation of the monitoring
results is provided in Annex
D.
In-situ Measurements
1.6.4
Graphical presentation of the monitoring results
(Temperature, DO, pH, Salinity and Turbidity) is shown in Figures
9 - 14 of Annex D. The levels of pH at all stations in December 2016 complied with
the WQO (Table B5 of Annex B; Figure 9 of Annex
D). The
levels of Turbidity at all stations complied
with the Action and Limit levels in December 2016 (Table B5 of Annex
B; Figure 10 of Annex D). The levels of DO at all stations complied with the WQO and the Action and Limit
levels in December 2016 (Table B5 of Annex
B; Figure 12 of Annex D). The
levels of Salinity at all stations complied
with the WQO in December 2016 (Table B5 of Annex B; Figure 14 of Annex
D).
Laboratory Measurement
1.6.5
The concentrations of SS were higher than the WQO (13.2 mg/L for dry season) at Tai Ho Bay 1 station in December 2016 (Table B5 of Annex B; Figure 15 of Annex D). However, levels of SS at all stations complied with the Action and Limit Levels (Table B5 of
Annex B).
1.6.6
For nutrients, concentrations of Ammonia (NH3) were relatively
similar amongst all stations (Table B5 of Annex
B; Figure 16 of Annex D). The levels of Total Inorganic Nitrogen (TIN) at Tai Ho Bay 1, Tai Ho Bay 2,
Sham Shui Kok and Tai Mo To
stations were higher the WQO of
0.5 mg/L (Table B5 of Annex B; Figure 17 of Annex
D). It should be noted that due to the
effect of Pearl River, the North Western WCZ has historically experienced
higher levels of TIN ([9]) and such exceedances of TIN WQO at all
stations are unlikely to be caused by the capping operation at CMP 2. Levels of 5-Day Biochemical Oxygen Demand (BOD5) were relatively
similar amongst all stations (Table B5 of Annex B; Figure 18
of Annex
D).
1.6.7
Overall, the monitoring results indicated that the capping operation at CMP 2 did not appear
to cause any unacceptable deterioration in water quality in December 2016. Statistical analysis will be undertaken and presented in the quarterly
report to investigate whether the capping operations at CMP 2 is causing any
unacceptable impacts in water quality of the area.
1.7.1
The following monitoring activities will be conducted in the next monthly period of January
2017 for ESC CMPs:
¡P
Water Column Profiling of ESC CMP Vd;
¡P
Routine Water Quality Monitoring of ESC CMPs;
¡P
Water Quality Monitoring During
Dredging of ESC CMP Vb;
¡P
Pit Specific Sediment Chemistry of ESC CMP Vd; and
¡P
Demersal Trawling of ESC CMPs.
1.7.2
No monitoring activities will be
scheduled in the next monthly period of January 2017 for SB CMPs.
1.7.3
The sampling schedule is presented
in Annex A.
1.8.1
A summary of the Study programme is
presented in Annex
E.