Agreement No. CE
23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
51st MONTHLY PROGRESS REPORT FOR November 2016
1.1.1 Since
early 1990s, contaminated sediment ([1]) arising from various
construction works (e.g. dredging and reclamation projects) in Hong Kong has
been disposed of at a series of seabed pits at East of Sha Chau (ESC). In late 2008, a review indicated that
the existing and planned facilities at ESC would not be able to meet the
disposal demand after 2012. In
order to meet this demand, the Hong Kong Special Administrative Region
Government (HKSARG) decided to implement a new contained aquatic disposal (CAD)
([2]) facility at the South of The Brothers
(SB CMPs) which had been under consideration for a number of years.
1.1.2 The
environmental acceptability of the construction and operation of the Project
had been confirmed by findings of the associated Environmental Impact
Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact Assessment
Ordinance (Cap.
499) (EIAO) in
September 2005 (EIA
Register No.: AEIAR-089/2005).
1.1.3 In
accordance with the EIA recommendation, prior to commencement of construction
works for the SB CMPs, the Civil Engineering and Development Department (CEDD)
undertook a detailed review and update of the EIA findings for the SB site ([4]).
Findings of the EIA review undertaken in 2009/ 2010 confirmed that the
construction and operation of the SB site had been predicted to be
environmentally acceptable.
1.1.4 Environmental Permits (EPs) (EP-312/2008/A and EP-427/2011/A) were
issued by the Environmental Protection Department (EPD) to the CEDD, the Permit
Holder, on 28 November 2008 for ESC CMP V and on 23 December 2011 for SB CMPs,
respectively. Under the
requirements of the
EPs, an Environmental Monitoring and Audit (EM&A) programme as set out
in the EM&A
Manuals ()
()
is required to be implemented for the CMPs.
1.1.5 The
present EM&A programme under Agreement No. CE 23/2012 (EP) covers the
dredging, disposal and capping operations of the SB CMPs as well as ESC CMPs. Detailed works schedule for ESC CMPs and
SB CMPs is shown in Figure
1.1. In November 2016, the following works
were being undertaken:
¡P
Dredging
operation at ESC CMP Vb;
¡P
Disposal
of contaminated mud at ESC CMP Vd; and
¡P
Capping
operation at SB CMP 2.
Figure
1.1 Works
Schedule for ESC CMPs and SB CMPs
1.2
Reporting Period
1.2.1
This 51st
Monthly Progress Report covers the EM&A activities for
the reporting month of November 2016.
1.3
Details of Sampling and
Laboratory Testing Activities
1.3.1
The following monitoring
activities have been undertaken for ESC CMPs in November 2016:
¡P
Routine Water Quality Monitoring of ESC CMPs was undertaken on 1 November 2016;
¡P
Water Quality Monitoring During
Dredging of ESC CMP Vb was undertaken on 2, 4, 8, 10, 12, 14, 16, 18, 21, 23, 25, 28 and 30 November 2016;
¡P
Pit Specific Sediment Chemistry of ESC CMP Vd was undertaken on 7 November 2016; and
¡P
Water Column Profiling of ESC CMP Vd was undertaken on 9 November 2016.
1.3.2
No monitoring activities were
scheduled to be undertaken for SB CMPs in November 2016.
1.4.1
No outstanding sampling remained for November 2016.
1.4.2
The following laboratory analyses are in progress during the
preparation of this monthly report and will be presented in the next monthly
report once the data are available:
¡P
Laboratory analyses
of sediment samples collected for Pit
Specific
Sediment Chemistry of ESC CMP Vd
in November 2016.
1.5
Brief Discussion of the Monitoring Results for ESC
CMPs
1.5.1
Brief discussion of the monitoring results
of the following activities for ESC CMPs is presented in this 51st
Monthly Progress Report:
¡P
Water Quality Monitoring During
Dredging of ESC CMP Vb in November 2016;
¡P
Water Column Profiling of ESC CMP Vd in November 2016;
¡P
Routine Water Quality Monitoring of ESC CMPs in November 2016; and
1.5.2
Impact
Water Quality Monitoring during Dredging Operations of ESC CMP Vb ¡V November 2016
1.5.3 Water quality monitoring was conducted three times per week
during the reporting period on 2, 4, 8, 10,
12, 14, 16, 18, 21, 23, 25, 28 and 30 November
2016. During each survey day,
monitoring was conducted during both mid-ebb and mid-flood tides at two
Reference (Upstream) stations and five Impact (Downstream) stations around the dredging operations at ESC CMP
Vb. Monitoring was also conducted
at one Sensitive Receiver station situated in Ma Wan.
A total of eight (8) stations were monitored and locations of the
sampling stations are shown in Figure
1.2.
1.5.4 Monitoring results are presented in Table B1 of Annex
B. Daily dredging volume in November 2016 is
reported in Annex
C. Levels of Dissolved Oxygen (DO),
Turbidity and Suspended Solid (SS) complied with the Action and Limit Levels
(see Table B2 of Annex B for details) set in the Baseline
Monitoring Report (),
except for the following occasion of exceedances discussed in Table
1.1 below.
1.5.5 The results indicated that the dredging operations at ESC
CMP Vb did not appear to cause any unacceptable
deterioration in water quality during this reporting period. Therefore, no further action, except for
those recommended in the Environmental Permit (EP-312/2008/A), are considered necessary for the dredging operations.
1.5.6
Water
Column Profiling of ESC CMP Vd
¡V November 2016
1.5.7 Water
Column
Profiling was undertaken at a total of two
sampling stations (Upstream and Downstream stations) on 9 November 2016. The monitoring results have been assessed for
compliance with the Water Quality Objectives (WQOs) set by Environmental
Protection Department (EPD). This consists of a review of the EPD routine water quality monitoring
data for the dry season period (November to March) of 2006 - 2015 from stations in the Northwestern
Water Control Zone (WCZ), where the ESC CMPs are located (). For Salinity, the averaged value
obtained from the Reference stations was used for the basis as the WQO. Levels of DO and Turbidity were also assessed for compliance with the
Action and Limit Levels (see Table B2 of Annex B for details).
In-situ Measurements
1.5.8 Analyses of results for November 2016 indicated that levels of DO and pH complied
with the WQOs at both Downstream and Upstream stations
(Table B3 of Annex B). In addition, DO and
Turbidity at all stations complied with the Action and Limit Levels (Tables
B2 and B3 of Annex B).
Laboratory
Measurements for Suspended Solids (SS)
1.5.9 Analyses of results for November 2016 indicated that the SS
levels at all stations complied with the WQOs and the Action and Limit Levels (Tables B2 and B3 of Annex
B).
1.5.10 Overall, the monitoring results indicated that the mud
disposal operation at ESC CMP Vd did not appear to
cause any deterioration in water quality during this reporting period.
1.5.11 Routine Water Quality Monitoring of ESC CMPs ¡V November 2016
1.5.12 Routine Water Quality Monitoring of ESC CMPs was undertaken
on 1 November 2016. The monitoring results have been assessed for
compliance with the WQOs (see Section 1.5.7 for details) The monitoring results are shown in Tables B4 and
B5 of Annex
B and Figures 1 - 10 of Annex
D. A total of sixteen (16) monitoring
stations were sampled in November 2016 as shown in Figure 1.3.
In-situ Measurements
1.5.13 Graphical presentation of the
monitoring results (Temperature, DO, pH, Salinity and Turbidity) is shown in Figures
1 - 6 of Annex D. Analyses of results for November 2016 indicated
that the levels of pH, Salinity and DO complied with the WQOs at all stations (Impact, Intermediate, Reference
and Ma Wan stations) in November 2016 (Table
B4 of Annex
B; Figures 1, 3 and 5 of Annex D).
1.5.14
The levels of DO and Turbidity
complied with the Action and Limit Levels at all stations (Table
B4
of Annex
B; Figures
3 and 6 of Annex D).
1.5.15 Overall, in-situ measurement
results of the Routine Water Quality Monitoring indicated that the disposal operation at ESC CMP Vd did not appear to cause any unacceptable impacts in water quality in November 2016.
Laboratory Measurements
1.5.16 Laboratory analysis of November 2016 results indicated that
concentrations of Cadmium, Silver and Mercury were below their limit of
reporting at all stations. Arsenic,
Chromium, Nickel, Copper, Lead and Zinc were detected in November 2016 samples and the
concentrations of these metals and metalloids were similar amongst stations (Table B5 of Annex
B; Figure 7 of Annex
D).
1.5.17 For nutrients, concentrations of Total Inorganic Nitrogen
(TIN) at all stations except Ma Wan station in November 2016 were higher than the WQO
(0.5 mg/L) (Table B5 of Annex B; Figure 8 of Annex D). It should be
noted that due to the effect of Pearl River, the North Western WCZ has
historically experienced higher levels of TIN ([9]). Therefore, the exceedances of TIN WQO at
these stations are unlikely to be caused by the disposal operation at ESC CMP Vd.
Concentrations of Ammonia Nitrogen (NH3-N) were relatively
similar amongst all stations (Table B5 of Annex B; Figure 8 of Annex D). Levels of
5-day Biochemical Oxygen Demand (BOD5) appear to be higher at Reference stations in November 2016 (Table B5 of Annex
B; Figure 9 of Annex
D).
1.5.18 Analyses of results for November 2016 indicated
that the SS levels at Intermediate and Ma
Wan stations were higher than the WQO (13.2 mg/L
for dry season), however SS levels at all
stations complied with the Action and Limit Levels (Tables B2 and B5 of Annex
B; Figure 10 of Annex
D).
1.5.19 Overall, results of the Routine Water Quality Monitoring indicated that the disposal operation at ESC CMP Vd did not appear to cause any unacceptable deterioration
in water quality in November 2016. Detailed statistical analysis will be
presented in the Quarterly Report to investigate any spatial and temporal trends
of potential concern.
1.6
Activities Scheduled for the
Next Month
1.6.1
The following monitoring activities will be conducted in the next monthly period of December
2016 for ESC CMPs:
¡P
Water Column Profiling of ESC CMP Vd;
¡P
Routine Water Quality Monitoring of ESC CMPs;
¡P
Water Quality Monitoring During
Dredging of ESC CMP Vb;
¡P
Pit Specific Sediment Chemistry of ESC CMP Vd;
¡P
Cumulative Impact
Sediment Chemistry
of ESC CMPs; and
¡P
Benthic Recolonisation
Studies of ESC CMP IV.
1.6.2
The following monitoring activities will be conducted in the next monthly period of December
2016 for SB CMPs:
¡P
Water Quality Monitoring During
Capping of SB CMPs;
¡P
Benthic Recolonisation
Studies of SB CMP 1.
1.6.3
The sampling schedule is presented
in Annex A.
1.7.1
A summary of the Study programme is
presented in Annex
E.