Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits at the South of The Brothers
and at East Sha Chau (2012-2017) -
Investigation
4th MONTHLY
PROGRESS REPORT FOR DECEMBER 2012
1.1.1
Since early 1990s, contaminated
sediment ([1]) arising from
various construction works in Hong Kong has
been disposed of at a series of seabed pits at East of Sha Chau (ESC). In late 2008, a review indicated that
the existing and planned facilities at ESC would not be able to meet the
disposal demand after 2012. In
order to meet this demand, the Hong Kong Special Administrative Region
Government (HKSARG) decided to implement a new contained aquatic disposal
(CAD) ([2]) facility at the
South of The Brothers (SB CMPs) (hereafter referred to as ¡§the Project¡¨) which
had been under consideration for a number of years.
1.1.2
The environmental acceptability of the
construction and operation of the Project had been confirmed by findings of the
associated Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO) in September
2005 (EIA
Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA
recommendation, prior to commencement of construction works for the SB CMPs,
the Civil Engineering and Development Department (CEDD) undertook a detailed
review and update of the EIA findings for the SB site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had
been predicted to be environmentally acceptable.
An Environmental
Permit (EP-427/2011) was issued by the Environmental
Protection Department (EPD) to the CEDD, the Permit Holder, on 3 November 2011
and varied on 23 December 2011 (EP-427/2011/A). Under the requirements of Condition 4 of
the EP (EP-427/2011/A), an
Environmental Monitoring and Audit (EM&A) programme as set out in the
EM&A Manual is required to be implemented for the SB CMPs. The present EM&A
programme undertaken under Agreement No. CE 23/2012 (EP)
covers the dredging, disposal and capping operations of the SB CMPs.
1.2
Reporting Period
1.2.1
This Monthly Progress Report covers the
EM&A activities for the reporting month of
December 2012.
1.3
Details of Sampling and Laboratory Testing Activities
1.3.1
Impact Water Quality Monitoring
during Dredging Operations of CMP 1 was
conducted three times per week (ie 1, 4, 6, 8, 11,
13, 15, 18, 20, 22, 24, 27, 29 and 31 December 2012) in this reporting month.
1.4.1
No outstanding sampling and laboratory analysis remained from December
2012. A summary of field activities
are presented in Annex
A.
1.5.1
All monitoring data
collected for SB CMPs in December 2012 will be presented in this monthly
report. Detailed discussion will be
presented in the corresponding Quarterly Report.
1.5.2
Impact Water Quality Monitoring during Dredging
Operations of CMP 1 ¡V November 2012
1.5.3
Impact Water Quality Monitoring
during Dredging Operations of CMP 1 was
conducted three times per week in a total of fourteen sampling days in December
2012. On the survey day, sampling
was conducted during both mid-ebb and mid-flood tides at two Reference (Upstream)
stations upstream and five Impact (Downstream) stations downstream of the
dredging operations at CMP 1.
Monitoring was also conducted at five Sensitive Receiver Stations (Ma
Wan, Shum Shui Kok, Tai Mo To and Tai Ho Bay). A total of twelve stations were
monitored and locations of the sampling stations are shown in Figure 1.1.
1.5.4
Monitoring
results are presented in Table B1 of Annex
B.
Levels of Dissolved Oxygen (DO), Turbidity and Suspended Solids (SS)
generally complied with the Action and Limit Levels set in the Baseline
Monitoring Report (), except on 15, 29 and 31 December 2012 during the mid-flood
tide.
1.5.5
On 15 December
2012, level of turbidity exceeded the Action Level at Sensitive Receiver
Station WSR46 while level of SS exceeded the Action Level at Downstream
Stations DS2, DS4 and DS5 and Sensitive Receiver Stations WSR45C and
WSR46. On 29 December 2012, level
of turbidity exceeded the Action Level at Downstream Station DS5 and levels of
SS exceeded the Action Level at Downstream Stations DS4 and DS5 and Sensitive
Receiver Station WSR46. Exceedance
of Action Level of SS was recorded at Station WSR46 on 31 December 2012.
1.5.6
Stations DS2,
DS4, DS5, WSR45C and WSR46 are located further away from the works area of CMP
1 when compared to Station DS1 at which the levels of SS and Turbidity did not exceed
the Action and Limit Levels. Hence,
it is unlikely that the exceedances are caused by the dredging operations of
CMP 1. In addition, high levels of
SS and turbidity were occasionally recorded and such fluctuations were also
observed during baseline monitoring.
The high SS and turbidity levels recorded are thus considered to be
sporadic events and characteristic of water quality in this area of Hong
Kong.
1.5.7
Overall, the
results indicated that the dredging operations at CMP 1 of SB did not appear to
cause any unacceptable deterioration in water quality during this reporting
period. Therefore, no further mitigation
measures, except for those recommended in the Environmental Permit (EP-427/2011/A), are considered necessary for the dredging operations.
1.6
Activities Scheduled for the Next Month
1.6.1
Impact Water Quality Monitoring
during Dredging Operations for CMP 1 will be
conducted three times per week in the next monthly period of January 2013. The sampling schedule is presented in
Annex A.
1.7.1
A summary of the
Study programme is presented in Annex C.