Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
48th MONTHLY PROGRESS REPORT FOR August 2016
1.1.1
Since early 1990s, contaminated sediment ([1]) arising from various construction works
(e.g. dredging and reclamation projects) in Hong Kong
has been disposed of at a series of seabed pits at East of Sha
Chau (ESC). In
late 2008, a review indicated that the existing and planned facilities at ESC
would not be able to meet the disposal demand after 2012. In order to meet this demand, the Hong Kong
Special Administrative Region Government (HKSARG) decided to implement a new
contained aquatic disposal (CAD) ([2]) facility at the South of The Brothers
(SB CMPs) which had been under consideration for a
number of years.
1.1.2
The environmental acceptability of the construction and
operation of the Project had been confirmed by findings of the associated
Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]).
The Director of Environmental Protection (DEP) approved this EIA report
under the Environmental
Impact Assessment Ordinance (Cap. 499) (EIAO) in September 2005 (EIA Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA recommendation, prior to
commencement of construction works for the SB CMPs,
the Civil Engineering and Development Department (CEDD) undertook a detailed
review and update of the EIA findings for the SB site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had
been predicted to be environmentally acceptable.
1.1.4
Environmental
Permits (EPs)
(EP-312/2008/A and EP-427/2011A) were issued by the Environmental
Protection Department (EPD) to the CEDD, the Permit Holder, on 28 November 2008
for ESC CMP V and on 23 December 2011 for SB CMPs,
respectively. Under the requirements of
the EPs, an Environmental
Monitoring and Audit (EM&A) programme as set out in the EM&A Manuals ()
()
is required to be implemented for the CMPs.
1.1.5
The present EM&A programme under Agreement No. CE 23/2012 (EP) covers the dredging,
disposal and capping operations of the SB CMPs
as well as ESC CMPs. Detailed works schedule for ESC CMPs and SB CMPs is shown in Figure
1.1. In August
2016, the following works were being undertaken:
· Disposal of contaminated mud at ESC CMP Vd; and
· Capping operation at SB CMP 2.
Figure 1.1 Works
Schedule for ESC CMPs and SB CMPs
1.2
Reporting
Period
1.2.1
This 48th Monthly Progress Report covers the EM&A activities for the reporting month of August 2016.
1.3
Details
of Sampling and Laboratory Testing Activities
1.3.1
The following monitoring
activities have been undertaken for ESC CMPs in August 2016:
· Benthic Recolonisation Studies of ESC CMP IV was undertaken on 5 August 2016;
· Sediment Chemistry
after a Major Storm of ESC CMPs was undertaken on 5 August 2016;
·
Routine Water Quality Monitoring of ESC CMPs was undertaken on 8 August 2016;
· Pit Specific Sediment
Chemistry of ESC CMP Vd was
undertaken on 9 August 2016;
· Demersal Trawling of ESC CMPs
was undertaken on 10 and 11 August 2016.
·
Water Column Profiling of ESC CMP Vd was undertaken on 15 August 2016;
· Cumulative Impact Sediment
Chemistry of ESC CMPs was
undertaken on 11 and 12 August 2016;
· Sediment Toxicity Test of
ESC CMPs was
undertaken on 11 and 12 August 2016; and
1.3.2
The following monitoring
activities have been undertaken for SB CMPs in August 2016:
·
Water Quality Monitoring During Capping of SB CMPs was undertaken on 20 August 2016; and
·
Benthic Recolonisation
Studies of SB CMP 1 was undertaken on
23 August 2016.
1.4
Details
of Outstanding Sampling and/or Analysis
1.4.1
No outstanding sampling remained for August 2016.
1.4.2
A
summary of field activities conducted are presented in Annex A. The following analyses are in progress and will be
presented in the corresponding quarterly report:
·
Species identification of the biota samples collected from Demersal Trawling for ESC CMPs in July and August 2016;
·
Laboratory analyses of sediment samples collected for Benthic Recolonisation Studies of ESC CMPs and SB CMP 1 in August 2016; and
·
Laboratory analyses for Sediment Toxicity Test of ESC CMPs in August 2016.
1.4.3
The
following laboratory analyses are in progress during the preparation of this
monthly report and will be presented in the next monthly report once the data
are available:
·
Laboratory analyses of sediment samples collected for Pit
Specific Sediment Chemistry of ESC CMP Vd in August 2016; and
·
Laboratory analyses of sediment samples collected for Cumulative
Impact Sediment Chemistry of ESC CMP Vd in August 2016.
1.5
Brief
Discussion of the Monitoring Results for ESC CMPs
1.5.1
Brief discussion of the
monitoring results of the following activities for ESC CMPs
is presented in this 48th Monthly Progress Report:
· Routine Water Quality
Monitoring of ESC CMPs
in August 2016;
·
Water Column Profiling of ESC CMP Vd in August 2016; and
· Sediment Chemistry
after a Major Storm of ESC CMPs in August 2016.
1.5.2
Routine Water Quality Monitoring of ESC CMPs – August 2016
1.5.3
Routine Water Quality
Monitoring of
ESC CMPs was
undertaken on 8 August 2016. The monitoring results
have been assessed for compliance with the Water Quality Objectives (WQOs) set by Environmental
Protection Department (EPD). This
consists of a review of the EPD routine water quality monitoring data for the
wet season period (April to October) of 2005 - 2014 from
stations in the Northwestern Water Control Zone
(WCZ), where the ESC CMPs are located (). For Salinity, the averaged value obtained
from the Reference stations was used for the basis as the WQO. Levels of Dissolved Oxygen (DO) and Turbidity were
also assessed for compliance with the Action and Limit Levels (see Table B1 of Annex B for details).
The monitoring results are shown
in Tables B2 and B3 of Annex B and Figures 1 - 10
of Annex C. A total of sixteen
(16) monitoring stations were sampled in August 2016 as shown in Figure 1.2.
In-situ Measurements
1.5.4
Graphical
presentation of the monitoring results (Temperature, DO, pH, Salinity and
Turbidity) is shown in Figures 1 - 6 of Annex C. Analyses of results for August
2016
indicated that the levels of pH and DO complied with the WQOs at all stations (Impact, Intermediate, Reference and
Ma Wan stations) in August 2016 (Table B2 of Annex
B; Figures 1 and 3 of Annex C).
Levels of Salinity at most stations complied with the WQOs, except for Ma Wan station (Table B2 of Annex B; Figure
5 of Annex C).
The higher Salinities recorded at Ma Wan station are likely to be caused
by the larger separation distance to Pearl River mouth, which release a large
amount of freshwater runoff in the area during flooding, when compared to the
Reference stations.
1.5.5
The levels of DO and Turbidity complied with the Action and
Limit Levels at all stations (Table
B2 of Annex B; Figures 3 and 6 of Annex C).
1.5.6
Overall, in-situ measurement results of
the Routine Water Quality
Monitoring indicated
that the disposal operation at ESC CMP Vd did not
appear to cause any unacceptable impacts in water quality in August
2016.
Laboratory Measurements
1.5.7
Laboratory analysis of August 2016 results indicated that
concentrations of Cadmium, Lead, Silver and Mercury were below their limit of
reporting at all stations. Arsenic,
Chromium, Nickel, Copper and Zinc were detected in August 2016 samples and the
concentrations of these metals and metalloid were similar amongst stations (Table B3 of Annex
B; Figure 7 of Annex
C).
1.5.8
For nutrients, concentrations of Total Inorganic Nitrogen
(TIN) at all stations in August 2016 exceeded the WQO (0.5 mg/L) (Table B3 of Annex
B; Figure 8 of Annex
C). It should be noted that due to the effect of
Pearl River, the North Western WCZ has historically experienced higher levels
of TIN ([8]).
Since TIN concentrations were recorded to be similar amongst all
stations, the exceedances of TIN WQO at all stations
are unlikely to be caused by the disposal operation at ESC CMP Vd. Concentrations
of Ammonia Nitrogen (NH3-N) were relatively similar amongst all stations (Table B3 of Annex
B; Figure 8 of Annex
C). Levels of 5-day Biochemical Oxygen Demand
(BOD5) appear to be higher at Ma Wan station in August 2016 (Table B3 of Annex
B; Figure 9 of Annex
C).
1.5.9
Analyses
of results for August 2016 indicated
that the SS levels complied with
the WQO
(11.1 mg/L for wet season) and the
Action and Limit Levels at all stations (Table B3 of Annex
B; Figure 10 of Annex
C).
1.5.10
Overall, results of the Routine Water Quality Monitoring indicated that the
disposal operation at ESC CMP Vd did not appear to
cause any unacceptable deterioration in water quality in August
2016. Detailed statistical analysis will be
presented in the Quarterly Report to investigate any spatial and temporal
trends of potential concern.
1.5.11
Water Column Profiling of ESC CMP Vd – August 2016
1.5.12
Water Column Profiling was undertaken at a total of two sampling stations
(Upstream and Downstream stations) on 15 August 2016. The monitoring results have been assessed for
compliance with the WQOs (see Section 1.5.3 for details). Levels of DO and
Turbidity were also assessed for compliance with the Action and Limit Levels
(see Table B1 of Annex B for details).
In-situ Measurements
1.5.13
Analyses
of results for August 2016 indicated that levels of Salinity and pH
complied with the WQOs at both Downstream and
Upstream stations (Table B4 of Annex B). Levels of DO at Upstream station was lower than the WQO (4
mg/L for wet season). However, DO
and Turbidity at all stations complied with the Action and Limit Levels (Table B4 of Annex B).
Laboratory Measurements for Suspended Solids (SS)
1.5.14
Analyses
of results for August 2016 indicated that the SS levels were higher than the
WQO at Downstream station. However, both
Upstream and Downstream stations complied with the Action and Limit Levels (Table B4 of Annex B).
1.5.15
Overall,
the monitoring results indicated that the mud disposal operation at ESC CMP Vd did not appear to cause any deterioration in water
quality during this reporting period.
1.5.16
Sediment Chemistry after a Major Storm of ESC CMPs
– August 2016
1.5.17
Sampling for Sediment
Chemistry after a Major Storm Event was conducted at nine (9) monitoring
stations (Figure
1.3) on 5 August 2016 after the
visit of Typhoon Nida, which led to the issue of Gale
or Storm Wind Signal No.8 on 1 August 2016.
The track of Nida is shown in Figure
1.4.
Figure
1.4 Track of Typhoon Nida from 29 July to 3 August 2016 (Source: Hong Kong
Observatory)
1.5.18
Analyses
of results for the Sediment Chemistry after a Major Storm indicated that the concentrations of all inorganic
contaminants were below the LCEL (Figures 11 and 12 of Annex B).
1.5.19
Overall,
there appeared to be no evidence showing the failure of CMPs
in retaining disposed mud or causing contamination of sediments after the major
storm event in August 2016.
1.6.1
Brief discussion of the
monitoring results of the following activities for SB CMPs
is presented in this 48th
Monthly Progress Report:
·
Water Quality Monitoring during Capping Operations of SB CMPs
in August 2016.
1.6.2
Water Quality Monitoring during Capping of SB CMPs – August 2016
1.6.3
The
monitoring results obtained during
August 2016 sampling in the wet
season have been assessed for compliance with the WQOs
(see Section
1.5.3 for details). Levels of DO and
Turbidity were also assessed for compliance with the Action and Limit Levels (see Table B5 of Annex B for details). A total of twenty (20) monitoring stations were sampled in August 2016
as shown in Figure 1.5. Graphical presentation of the monitoring
results is provided in Annex C.
In-situ Measurements
1.6.4
Graphical
presentation of the monitoring results (Temperature, DO, pH, Salinity and
Turbidity) is shown in Figures 13 - 18 of Annex C. Levels of pH
at all stations in August 2016 complied with the WQO (Table
B6 of Annex B; Figure 13 of Annex C). The levels of
Turbidity at all stations complied with the Action and Limit levels in August 2016 (Table B6 of Annex B; Figure 14 of Annex C). DO at all
stations also complied with the WQO and the Action and Limit levels in August
2016 (Table B6 of Annex B; Figure 16 of Annex C).
1.6.5
Levels
of Salinity at most stations complied
with the WQO except at Tai Ho Bay 2 station (Table B6 of Annex B; Figure 18 of Annex C). The lower Salinities recorded
at Tai Ho Bay 2 are likely due to the close proximity of the nearby streams,
which release large amount of freshwater runoff in the area during flooding.
Laboratory Measurement
1.6.6
Concentrations of SS were recorded higher than the WQO (11.1
mg/L for wet season) at Reference, Intermediate, Ma Wan and Tai Mo To stations in
August 2016
(Table B6
of Annex
B; Figure 19 of Annex C). However,
levels of SS at all stations
complied with the Action and Limit Levels (Table B4 of Annex B).
1.6.7
For nutrients, concentrations of NH3 were relatively
similar
amongst all stations (Table B6 of Annex
B; Figure 20 of Annex C). TIN at all stations exceeded the WQO of 0.5
mg/L (Table B6
of Annex
B; Figure 21 of Annex C). As discussed in Section 1.5.8, the North Western WCZ has
historically experienced higher levels of TIN and such exceedances of TIN WQO at all stations are unlikely to be
caused by the disposal operation at CMP 2. Levels of BOD5
appeared to be higher at Tai Ho Bay 1 station in August 2016 (Table B6 of Annex B; Figure
22 of Annex C).
1.6.8
Overall, the monitoring results indicated that the capping operation at CMP 2 did not appear
to cause any unacceptable deterioration in water quality in August
2016. Statistical analysis will be
undertaken and presented in the quarterly report to investigate whether the
capping operations at CMP 2 is causing any unacceptable impacts in water quality of the
area.
1.7
Activities
Scheduled for the Next Month
1.7.1
The following monitoring activities will be conducted in the next
monthly period of September 2016 for ESC CMPs:
·
Water Column Profiling of ESC CMP Vd; and
·
Pit Specific Sediment Chemistry of ESC CMP Vd.
1.7.2
No monitoring activities will be scheduled in the next monthly
period of September 2016 for SB CMPs.
1.7.3
The
sampling schedule is presented in Annex A.
1.8.1
A
summary of the Study programme is presented in Annex D.