Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
45th MONTHLY PROGRESS REPORT FOR May 2016
1.1.1
Since early 1990s, contaminated sediment ([1])
arising from various construction works (e.g. dredging and reclamation
projects) in Hong Kong has been disposed of at
a series of seabed pits at East of Sha Chau (ESC). In late
2008, a review indicated that the existing and planned facilities at ESC would
not be able to meet the disposal demand after 2012. In order to meet this demand, the Hong Kong
Special Administrative Region Government (HKSARG) decided to implement a new
contained aquatic disposal (CAD) ([2])
facility at the South of The Brothers (SB CMPs) which
had been under consideration for a number of years.
1.1.2
The environmental acceptability of the
construction and operation of the Project had been confirmed by findings of the
associated Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO) in September
2005 (EIA
Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA
recommendation, prior to commencement of construction works for the SB CMPs, the Civil Engineering and Development Department
(CEDD) undertook a detailed review and update of the EIA findings for the SB
site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had
been predicted to be environmentally acceptable.
1.1.4
Environmental Permits (EPs) (EP-312/2008/A and EP-427/2011A) were
issued by the Environmental Protection Department (EPD) to the CEDD, the Permit
Holder, on 28 November 2008 for ESC CMP V and on 23 December 2011 for SB CMPs, respectively. Under the requirements of the EPs, an
Environmental Monitoring and Audit (EM&A) programme as set out in the
EM&A Manuals ()
()
is required to be implemented for the CMPs.
1.1.5
The present EM&A programme under Agreement No. CE
23/2012 (EP) covers the dredging, disposal and capping operations of the
SB CMPs as well
as ESC CMPs. Detailed works
schedule for both CMPs is shown in Figure 1.1. In May 2016, the following works were being
undertaken at the CMPs:
· Disposal of contaminated mud at ESC CMP Vd; and
· Capping operation at SB CMP 2.
Figure 1.1 Works
Schedule for ESC CMPs and SB CMPs
1.2
Reporting Period
1.2.1
This 45th Monthly Progress
Report covers the EM&A activities for
the reporting month of May 2016.
1.3
Details of
Sampling and Laboratory Testing Activities
1.3.1
The following monitoring activities have
been undertaken for ESC CMPs in May 2016:
· Water Column Profiling of
ESC CMP Vd was
undertaken on 4 May 2016;
· Routine Water Quality Monitoring of ESC CMP Vd was undertaken on 5 May 2016; and
· Pit Specific Sediment
Chemistry of ESC CMP Vd was
undertaken on 6 May 2016.
1.3.2
No monitoring activities were scheduled
to be undertaken for SB CMPs in May 2016.
1.4
Details of
Outstanding Sampling and/or Analysis
1.4.1
No outstanding sampling and analysis remained for May 2016.
1.5
Brief Discussion
of the Monitoring Results for ESC CMPs
1.5.1
Brief discussion of the monitoring results of
the following activities for ESC CMPs is presented in
this 45th Monthly Progress Report:
· Pit Specific Sediment
Chemistry of ESC CMP Vd in
May
2016;
·
Water Column Profiling of ESC CMP Vd in May 2016; and
·
Routine
Water Quality Monitoring of ESC CMP Vd
in May 2016.
1.5.2
Pit
Specific Sediment Chemistry of ESC CMP Vd
– May 2016
1.5.3
Monitoring locations for Pit Specific Sediment
Chemistry for ESC CMP Vd are shown in Figure 1.2.
A total of six (6) monitoring stations were sampled in May 2016.
1.5.4
The concentrations of all inorganic contaminants were lower than
the Lower Chemical Exceedance Level (LCEL)
at all stations (Figures 1 and 2 of Annex B).
1.5.5
For
organic contaminants, the concentrations of Total Organic Carbon (TOC) were
similar amongst most stations and it was observed to be lower at Active Pit station ESC-NPAA in May 2016 (Figure 3 of Annex B). In
May 2016, Tributyltin (TBT) concentrations were observed to be
similar among all stations, except the concentrations at Near Pit station ESC-NNAA and Pit Edge station ESC-NEAB were observed lower than the limit of
reporting (Figure 4 of Annex B).
Low and High Molecular Weight Polycyclic Aromatic Hydrocarbons (PAHs), Total Polychlorinated Biphenyls (PCBs), Total
dichlorodiphenyltrichloroethane (DDT) and 4,4’-dichlorodiphenyldichloroethylene
(DDE) concentrations were below the limit of reporting at all stations in May 2016.
1.5.6
Overall,
there is no evidence indicating any unacceptable environmental impacts to sediment
quality as a result of the contaminated mud disposal operations at ESC CMP Vd in May 2016.
Statistical analysis will be undertaken and presented in the quarterly
report to investigate whether there are any unacceptable impacts in the area
caused by the contaminated mud disposal.
1.5.7
Water Column Profiling of
ESC CMP Vd – May 2016
1.5.8
Water
Column Profiling was
undertaken on 4 May
2016. The monitoring results have been
assessed for compliance with the Water Quality Objectives (WQOs) set by Environmental Protection Department (EPD).
This consists
of a review of the EPD routine water quality monitoring data for the wet season
period (April to October) of 2005 - 2014 from stations in the Northwestern
Water Control Zone (WCZ), where the ESC CMPs are
located (). For Salinity, the averaged value obtained
from the Reference stations was used for the basis as the WQO. Levels of Dissolved Oxygen (DO) and
Turbidity were also assessed for compliance with the Action and Limit Levels (see Table C1 of Annex C for details).
In-situ Measurements
1.5.9
Analyses of results for May 2016 indicated that levels of Salinity, DO and pH complied with the WQOs at both Downstream and Upstream stations (Table C2 of Annex C).
In addition, DO and Turbidity at all stations complied
with the Action and Limit Levels (Table
C2 of Annex C).
Laboratory Measurements for Suspended Solids (SS)
1.5.10
Analyses of results for May 2016 indicated that the SS
levels were higher than the WQO at Downstream station. However, both Upstream and Downstream
stations complied with the Action and Limit Levels (Table C2 of Annex C).
Overall, the
monitoring results indicated that the mud disposal operation at ESC CMP Vd did not appear to cause any deterioration in water
quality during this reporting period.
1.5.11
Routine
Water Quality Monitoring of ESC CMP Vd
– May
2016
1.5.12
Routine
Water Quality Monitoring was undertaken on 5 May 2016. The
monitoring results have been assessed for compliance with the WQOs (see Section
1.5.8 for details). Levels of DO and
Turbidity were also assessed for compliance with the Action and Limit Levels
(see Table C1 of Annex C for details). The monitoring results are shown in Tables C3 and C4 of Annex C and Figures
5 - 14 of Annex B.
A total of sixteen (16) monitoring stations were sampled in May 2016 as shown in Figure 1.3.
In-situ Measurements
1.5.13
Graphical presentation of the monitoring results
(Temperature, DO, pH, Salinity and Turbidity) is shown in Figures 5 - 10 of Annex B. Analyses
of results for May 2016 indicated that
the levels of pH, Salinity and DO complied
with the WQOs at all stations (Impact, Intermediate,
Reference and Ma Wan stations) in May 2016 (Table C3 of Annex C; Figures 5, 6, 7 and 9 of Annex B).
1.5.14
The levels of DO and Turbidity complied
with the Action and Limit Levels at all stations (Table C3 of Annex C; Figures 6, 7 and 10 of Annex B).
1.5.15
Overall, in-situ measurement results
of the Routine
Water Quality Monitoring indicated that the disposal operation at ESC
CMP Vd did not appear to cause any unacceptable impacts in water quality in May 2016.
Laboratory Measurements
1.5.16
Laboratory analysis of May 2016 results indicated that concentrations
of Cadmium, Chromium, Silver, Nickel and
Mercury were below their limit of reporting at all stations. Arsenic, Lead, Copper and Zinc were detected in May 2016 samples and the concentrations were
similar amongst stations (Table C4 of Annex C; Figure 11 of Annex B).
1.5.17
For nutrients, concentrations of Total
Inorganic Nitrogen (TIN) at all stations in May 2016 exceeded the WQO (0.5 mg/L) (Table C4 of Annex C; Figure 12 of Annex B). It should be noted that due to effect of
Pearl River, the North Western WCZ has historically experienced higher levels
of TIN ([8]). Since TIN concentrations were recorded to be
similar amongst all stations, the exceedances of TIN
WQO at all stations are unlikely to be caused by the disposal operation at ESC
CMP Vd. Concentrations
of Ammonia Nitrogen (NH3-N) were relatively similar amongst all stations (Table C4 of Annex C; Figure 12 of Annex B). Levels of 5-day Biochemical Oxygen Demand
(BOD5) appear to be higher at Reference and Ma Wan stations in May 2016 (Table C4 of Annex C; Figure 13 of Annex B).
1.5.18
Concentrations of SS were higher than the
WQO (11.1 mg/L for wet season) at Impact
and Intermediate stations. However,
concentrations of SS complied with the Action and Limit Levels at all stations
in May 2016 (Table C4 of Annex C; Figure 14 of Annex B).
1.5.19
Overall, results of the Routine Water Quality
Monitoring indicated that the disposal operation at ESC CMP Vd did not appear to cause any unacceptable deterioration
in water quality in May 2016. Detailed statistical analysis will be
presented in the Quarterly Report to investigate any spatial and temporal
trends of potential concern.
1.6
Activities
Scheduled for the Next Month
1.6.1
The following monitoring activities will be
conducted in the next monthly period of June 2016 for SB CMPs:
·
Water Quality Monitoring During Capping of CMP 2.
1.6.2
The following monitoring activities will be
conducted in the next monthly period of June 2016 for ESC CMPs:
·
Water Column Profiling of ESC CMP Vd;
·
Pit Specific Sediment Chemistry of ESC CMP Vd; and
·
Cumulative Impact Sediment Chemistry of ESC CMP Vd.
1.6.3
The sampling schedule is presented in Annex
A.
1.7.1
A summary of the Study programme is presented in Annex
D.