Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
43rd MONTHLY PROGRESS REPORT FOR March
2016
1.1.1
Since early 1990s, contaminated sediment ([1])
arising from various construction works (e.g. dredging and reclamation
projects) in Hong Kong has been disposed of at
a series of seabed pits at East of Sha Chau (ESC). In late
2008, a review indicated that the existing and planned facilities at ESC would
not be able to meet the disposal demand after 2012. In order to meet this demand, the Hong Kong
Special Administrative Region Government (HKSARG) decided to implement a new
contained aquatic disposal (CAD) ([2])
facility at the South of The Brothers (SB CMPs) which
had been under consideration for a number of years.
1.1.2
The environmental acceptability of the
construction and operation of the Project had been confirmed by findings of the
associated Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO) in September
2005 (EIA
Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA
recommendation, prior to commencement of construction works for the SB CMPs, the Civil Engineering and Development Department
(CEDD) undertook a detailed review and update of the EIA findings for the SB
site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had
been predicted to be environmentally acceptable.
1.1.4
Environmental Permits (EPs) (EP-312/2008/A and EP-427/2011A) were
issued by the Environmental Protection Department (EPD) to the CEDD, the Permit
Holder, on 28 November 2008 for ESC CMP V and on 23 December 2011 for SB CMPs, respectively. Under the requirements of the EPs, an
Environmental Monitoring and Audit (EM&A) programme as set out in the
EM&A Manuals ()
()
is required to be implemented for the CMPs.
1.1.5
The present EM&A programme under Agreement No. CE
23/2012 (EP) covers the dredging, disposal and capping operations of the
SB CMPs as well
as ESC CMPs. Detailed works
schedule for both CMPs is shown in Figure 1.1. In March 2016, the following works were being
undertaken at the CMPs:
· Disposal of contaminated mud at SB CMP 2 up to 21
March 2016;
· Capping operation at ESC CMP Va
up to 21 March 2016;
· Disposal of contaminated mud at ESC CMP Vd since 22 March 2016; and
· Capping operation at SB CMP 2 since 22 March 2016.
Figure 1.1 Works
Schedule for ESC CMPs and SB CMPs
1.2
Reporting Period
1.2.1
This 43rd Monthly Progress
Report covers the EM&A activities for
the reporting month of March 2016.
1.3
Details of
Sampling and Laboratory Testing Activities
1.3.1
The following monitoring activities have
been undertaken for ESC CMPs in March 2016:
· Water Column Profiling of
ESC CMP Vd was
undertaken on 22 March 2016; and
· Pit Specific Sediment
Chemistry of ESC CMP Vd was
undertaken on 23 March 2016.
1.3.2
The following monitoring activities have
been undertaken for SB CMPs in March 2016:
· Water Column Profiling of
CMP 2 was undertaken on 2 March 2016; and
·
Pit Specific Sediment Chemistry of CMP 2
was undertaken on 3 March 2016.
1.4
Details of
Outstanding Sampling and/or Analysis
1.4.1
No outstanding sampling remained for March 2016.
1.4.2
A summary of field activities conducted are presented in Annex A.
The following
laboratory analyses were still in progress during the preparation of this
monthly report and hence are not presented in this monthly report:
·
Laboratory analyses of sediment samples collected for Pit
Specific Sediment Chemistry of SB CMP 2 in March 2016; and
·
Laboratory analyses of sediment samples collected for Pit
Specific Sediment Chemistry of ESC CMP Vd in March 2016.
1.5
Brief Discussion
of the Monitoring Results for ESC CMPs
1.5.1
Brief discussion of the monitoring results of
the following activities for ESC CMPs is presented in
this 43rd
Monthly Progress Report:
·
Water Column Profiling of ESC CMP Vd in March 2016
1.5.2
Water Column Profiling of
ESC CMP Vd – March 2016
1.5.3
Water
Column Profiling was
undertaken at a total of two sampling stations (Upstream and Downstream
stations) on 22 March
2016. The monitoring results have been
assessed for compliance with the Water Quality Objectives (WQOs) set by Environmental Protection Department (EPD).
This consists
of a review of the EPD routine water quality monitoring data for the dry season
period (November to March) of 2005 - 2014 from stations in the Northwestern
Water Control Zone (WCZ), where the ESC CMPs are
located (). For Salinity, the averaged value obtained
from the Reference stations was used for the basis as the WQO. Levels of Dissolved Oxygen (DO) and
Turbidity were also assessed for compliance with the Action and Limit Levels (see Table B1 of Annex B for details).
In-situ Measurements
1.5.4
Analyses of results for March 2016 indicated that levels of Salinity, DO and pH generally complied with the WQOs at both Downstream and Upstream stations (Table B2 of Annex B).
In addition, DO and Turbidity at all stations
complied with the Action and Limit Levels (Table B2 of Annex B).
Laboratory Measurements for Suspended Solids (SS)
1.5.5
Analyses of results for March 2016 indicated that the SS levels complied with the WQO at Downstream stations.
Both Upstream and Downstream
stations complied with the Action and
Limit Levels (Table B2 of Annex
B).
Overall, the
monitoring results indicated that the mud disposal operation at ESC CMP Vd did not appear to cause any deterioration in water
quality during this reporting period.
1.6.1
Brief discussion of the monitoring results of
the following activities for SB CMPs is presented in
this 43rd
Monthly Progress Report:
· Water Column Profiling of
CMP 2 in 2 March 2016
1.6.2
Water
Column Profiling of CMP 2 – March 2016
1.6.3
Water
Column Profiling was
undertaken at a total of two sampling stations (Upstream and Downstream
stations) on 2 March 2016.
The monitoring results have been assessed for compliance
with the WQOs (see Section 1.5.3 for details). Levels
of DO and Turbidity were also assessed for compliance with the Action and Limit
Levels (see Table B3 of Annex B for details).
In-situ
Measurements
1.6.4
Analyses of results for March 2016 indicated that levels of Salinity, DO and pH complied with the WQOs
at both Downstream and Upstream stations (Table B4 of Annex B).
In addition, DO and Turbidity at all stations
complied with the Action and Limit Levels (Table B4 of Annex B).
Laboratory
Measurements for SS
1.6.5
Analyses of results for March 2016 indicated that the SS levels complied with the WQO at Downstream stations.
Both Upstream and Downstream
stations complied with the Action and
Limit Levels (Table B4 of Annex
B).
1.6.6
Overall, the monitoring results indicated that the mud
disposal operation at CMP 2 did not appear to cause any deterioration in water
quality during this reporting period.
1.7
Activities
Scheduled for the Next Month
1.7.1
No monitoring activities will be scheduled
in the next monthly period of April 2016 for SB CMPs.
1.7.2
The following monitoring activities will be
conducted in the next monthly period of April 2016 for ESC CMPs:
·
Routine Water Quality
Monitoring of ESC CMP Vd;
·
Pit Specific Sediment Chemistry of ESC CMP Vd; and
·
Water Column Profiling of ESC CMP Vd.
1.7.3
The sampling schedule is presented in Annex A.
1.8.1
A summary of the Study programme is presented in Annex C.