Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
42nd MONTHLY PROGRESS REPORT FOR february 2016
1.1.1
Since early 1990s, contaminated sediment ([1])
arising from various construction works (e.g. dredging and reclamation
projects) in Hong Kong has been disposed of at
a series of seabed pits at East of Sha Chau (ESC). In
late 2008, a review indicated that the existing and planned facilities at ESC
would not be able to meet the disposal demand after 2012. In order to meet this demand, the Hong
Kong Special Administrative Region Government (HKSARG) decided to implement a
new contained aquatic disposal (CAD) ([2])
facility at the South of The Brothers (SB CMPs) which
had been under consideration for a number of years.
1.1.2
The environmental acceptability of the construction and operation
of the Project had been confirmed by findings of the associated Environmental
Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) in September 2005 (EIA Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA recommendation, prior to
commencement of construction works for the SB CMPs,
the Civil Engineering and Development Department (CEDD) undertook a detailed
review and update of the EIA findings for the SB site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had
been predicted to be environmentally acceptable.
1.1.4
Environmental
Permits (EPs)
(EP-312/2008/A and EP-427/2011A) were issued by the Environmental
Protection Department (EPD) to the CEDD, the Permit Holder, on 28 November 2008
for ESC CMP V and on 23 December 2011 for SB CMPs,
respectively. Under the
requirements of the EPs, an Environmental
Monitoring and Audit (EM&A) programme as set out in the EM&A Manuals ()
()
is required to be implemented for the CMPs.
1.1.5
The present EM&A programme under Agreement No. CE 23/2012 (EP) covers the dredging,
disposal and capping operations of the SB CMPs as well as ESC CMPs. Detailed works schedule for both CMPs is shown in Figure 1.1. In February 2016, the following works
were being undertaken at the CMPs:
¡P Dredging operation at ESC CMP Vd;
¡P Capping operation at ESC CMP Va; and
¡P Disposal of contaminated mud at SB CMP 2.
Figure 1.1 Works
Schedule for ESC CMPs and SB CMPs
1.2
Reporting Period
1.2.1
This 42nd
Monthly Progress Report covers the EM&A activities for
the reporting month of February 2016.
1.3
Details of Sampling and
Laboratory Testing Activities
1.3.1
The following monitoring
activities have been undertaken for ESC CMPs in
February 2016:
¡P Impact Water Quality Monitoring during Capping Operations of ESC CMP Va was undertaken on 17 February 2016;and
¡P Impact Water Quality
Monitoring during Dredging Operations of ESC CMP Vd
was undertaken on 22 February 2016.
1.3.2
The following monitoring
activities have been undertaken for SB CMPs in
February 2016:
¡P
Water Column Profiling of CMP 2 was undertaken on
1 February 2016;
¡P
Cumulative Impact Sediment Chemistry of SB CMPs was undertaken on 2 and 3 February 2016;
¡P
Sediment Toxicity Test of CMP 2 was undertaken on 2
and 3 February 2016;
¡P
Pit Specific Sediment Chemistry of CMP 2 was undertaken on 4 February 2016;
¡P Impact Water Quality
Monitoring during Capping Operations of SB CMP 2 was undertaken on 11
February 2016;
¡P
Routine Water Quality Monitoring of CMP 2 was undertaken on 19 February 2016; and
¡P
Demersal Trawling for SB CMPs was
undertaken on 23 and 24 February 2016.
1.4
Details of Outstanding
Sampling and/or Analysis
1.4.1
No outstanding sampling
remained for
February 2016.
1.4.2
The following laboratory analyses
are in progress and will be presented in the corresponding quarterly report:
¡P Taxonomic identification of fishery resources
collected during Demersal Trawling for SB CMPs and
subsequent chemical analysis for the biota samples collected in January and February 2016.
¡P Laboratory analyses of sediment samples collected for Sediment Toxicity Tests of CMP 2 in
February 2016.
1.5
Brief Discussion
of the Monitoring Results for ESC CMPs
1.5.1
Brief discussion of the monitoring
results of the following activities for ESC CMPs is
presented in this 42nd
Monthly Progress Report:
¡P
Impact Water Quality Monitoring during Dredging Operations of ESC CMP Vd in February 2016; and
¡P
Water Quality Monitoring During Capping of CMP Va
in February 2016.
1.5.2
Impact Water
Quality Monitoring during Dredging Operations of ESC CMP Vd ¡V February
2016
1.5.3
Dredging activities were carried out
on 19 - 23 February 2016 during this reporting period and monitoring
was conducted on 22 February 2016.
During the survey day, monitoring was conducted during both mid-ebb and
mid-flood tides at two Reference (Upstream) stations and five Impact
(Downstream) stations around the dredging operations at ESC CMP Vd. Monitoring
was also conducted at one Sensitive Receiver station situated in Ma Wan. A total of eight (8) stations were
monitored and locations of the sampling stations are shown in Figure 1.2.
1.5.4
Monitoring results are presented in Table B1
of Annex B. Daily dredging volume in February 2016 is reported in Annex C. Levels of Dissolved Oxygen (DO), Turbidity
and Suspended Solid (SS) complied with the Action and Limit Levels (see Table B2
of Annex B for details) set in the Baseline Monitoring Report ().
1.5.5
The results indicated that the
dredging operations at ESC CMP Vd did not appear to
cause any unacceptable deterioration in water quality during this reporting
period. Therefore, no further
action, except for those recommended in the Environmental Permit (EP-312/2008/A), are considered necessary for the dredging
operations.
1.5.6
Water Quality
Monitoring during Capping of ESC CMPs
¡V February 2016
1.5.7
The monitoring
results obtained during February 2016 sampling in the dry season have been assessed for
compliance with the Water Quality Objectives (WQOs) set by Environmental Protection Department (EPD). This consists of a
review of the EPD routine water quality monitoring data for the dry season
period (November to March) of 2005 - 2014 from stations in
the Northwestern Water Control Zone (WCZ), where the
ESC CMPs are located (). For Salinity, the averaged value
obtained from the Reference stations was used for the basis as the WQO. Levels of DO and Turbidity were
also assessed for compliance with the Action and Limit Levels (see Table
B2 of Annex B for details). A total of ten (10) monitoring stations were sampled in February
2016 as shown in Figure 1.3.
In-situ
Measurements
1.5.8
Graphical presentation of the
monitoring results (Temperature, DO, pH,
Salinity and Turbidity) is shown in Figures
1-6 of Annex D. Levels of
Salinity, DO and pH at all stations in February 2016 complied with the WQO (Table B3 of
Annex B). Level of DO and Turbidity also complied the Action and Limit levels (Table B3 of
Annex B).
Laboratory
Measurements for Suspended Solids (SS)
Concentrations of SS complied with the WQO and the
Action and Limit Levels at all stations in
February 2016 (Table B3 of Annex B; Figure 7 of Annex
D). Further
statistical analysis will be undertaken in the quarterly report to investigate
whether the capping operations at ESC CMPs is causing
any unacceptable deterioration in water quality of the area.
1.6
Brief Discussion of the
Monitoring Results for SB CMPs
1.6.1
Brief discussion of the monitoring
results of the following activities for SB CMPs is
presented in this 42nd
Monthly Progress Report:
¡P
Pit Specific Sediment Chemistry of CMP 2 in January and
February 2016;
¡P
Cumulative Impact Sediment Chemistry of CMP 2 in February 2016;
¡P
Routine Water Quality Monitoring of CMP 2 in
February 2016;
¡P
Water Column Profiling of CMP 2 in February 2016; and
¡P
Impact Water Quality Monitoring during Capping Operations of SB CMP 2 in February 2016.
1.6.2
Pit Specific Sediment Chemistry of CMP 2 ¡V January
and February 2016
1.6.3
Monitoring locations for Pit Specific Sediment Chemistry for CMP 2 are shown in Figure 1.4. A total of six (6) monitoring stations
were sampled in January and February 2016.
1.6.4
The concentrations of most
inorganic contaminants (Arsenic, Cadmium, Chromium, Lead,
Mercury, Nickel and
Zinc) were lower than the Lower Chemical Exceedance
Level (LCEL) at all stations, except
Silver and Copper (Figures 8, 9, 13 and 14 of Annex D). In January 2016, Silver
and Copper exceeded
the LCEL at both Active Pit stations SB-NPBA and SB-NPBB (Figure 9 of Annex D). In February 2016, Silver
and Copper exceeded
the LCEL at Active Pit station SB-NPBB (Figure 14 of Annex D).
1.6.5
For organic contaminants, the concentrations of Total
Organic Carbon (TOC) were similar amongst most stations and it was observed to
be lower at Pit Edge station SB-NPBB in January and February 2016 (Figures 10 and 15 of Annex D). Tributyltin (TBT) concentrations were observed to be higher at
Active Pit stations SB-NPBA (Figures 11 and 16 of Annex D). 4,4¡¦-dichlorodiphenyldichloroethylene
(DDE) concentrations were observed to be higher at Active Pit SB-NPBB in
January and February 2016 (Figures 12 and 17 of Annex D). Total
dichlorodiphenyltrichloroethane (DDT) concentrations were observed to be higher
at Pit Edge station SB-NEBA and Active Pit station SB-NPBB in February 2016
whilst concentrations of DDT were below limit of reporting at all stations in
January 2016 (Figure 12 of Annex D). Low and High Molecular Weight Polycyclic
Aromatic Hydrocarbons (PAHs), Total Polychlorinated
Biphenyls (PCBs) and concentrations were below the limit of reporting at all
stations.
1.6.6
Overall, there is no evidence indicating any
unacceptable environmental impacts to sediment quality as a result of the
contaminated mud disposal operations at CMP 2 in January
and February 2016. Statistical analysis will be undertaken
and presented in the quarterly report to investigate whether there are any
unacceptable impacts in the area caused by the contaminated mud disposal.
1.6.7
Cumulative
Impact Sediment Chemistry of SB CMPs ¡V February 2016
1.6.8
Monitoring locations for Cumulative Impact Sediment Chemistry for SB CMPs are shown in Figure 1.5. A total of eleven (11) monitoring
stations were sampled in February 2016.
1.6.9
Analyses of results for the Cumulative Impact Sediment Chemistry Monitoring indicated that the concentrations
of all inorganic contaminants, except Arsenic
concentrations in Far-field station SB-RFB, were below the LCEL in February 2016 (Figures 18 and 19 of Annex D).
1.6.10
Whilst the average concentration
of Arsenic in the Earth¡¦s crust is generally ~2mg/kg, significantly higher
Arsenic concentrations (median = 14 mg/kg) have been recorded in Hong Kong¡¦s onshore sediments ([9]). It is presumed
that the natural concentrations of Arsenic are similar in onshore and offshore
sediments ([10]), and relatively high Arsenic levels may thus occur
throughout Hong Kong. Therefore, the LECL exceedances
of Arsenic are unlikely to be caused by the disposal operations at CMP 2 but
rather as a result of naturally occurring deposits.
1.6.11
For organic contaminants, concentrations of
TOC at Near-field station SB-RNA was
recorded to be lower than other stations (Figure 20 of
Annex D). Concentrations of TBTs
were recorded to be higher at Ma Wan station (Figure
21 of Annex D). Total
DDT, 4,4¡¦-DDE, Total PCBs as well as Low and High Molecular
Weight PAHs were recorded below the limit of reporting at all stations.
1.6.12
Overall, there is no evidence indicating any
unacceptable environmental impacts to sediment quality as a result of the
contaminated mud disposal operations at CMP 2 in February 2016. Statistical analysis will be
undertaken and presented in the quarterly report to investigate whether there
are any unacceptable impacts in the area caused by the contaminated mud
disposal.
1.6.13
Routine Water
Quality Monitoring of
SB CMP 2 ¡V February 2016
1.6.14
Routine Water Quality Monitoring
was undertaken at a total of two sampling stations (Upstream and Downstream
stations) on 19 February
2016. The
monitoring results
have been assessed for compliance with the WQOs (see Section 1.5.7 for details). Levels of DO and Turbidity were also
assessed for compliance with the Action and Limit Levels (see Table B4 of Annex B for
details). The monitoring results
are shown in Tables
B5 and B6 of Annex B and Figures 22 - 31 of Annex D. A total of twenty (20) monitoring
stations were sampled in February 2016 as shown in Figure 1.6.
In-situ Measurements
1.6.15
Graphical presentation of the monitoring
results (Temperature, DO, pH, Salinity and Turbidity) is shown in Figures 22 - 27
of
Annex D. Analyses
of results for February 2016
indicated that the levels of pH, DO and Salinity complied
with the WQOs at all stations (Impact, Intermediate,
Reference and Water Sensitive Receiver stations) in February 2016 (Table B5 of Annex B; Figures 22 - 24, 26 of Annex D).
1.6.16
The levels of DO and Turbidity
complied with the Action and Limit Levels at all stations (Table B5 of Annex B; Figures 24 and 27 of Annex D).
1.6.17
Overall, in-situ
measurement results of the Routine Water Quality Monitoring indicated
that the disposal operation at CMP 2 did not appear to cause any unacceptable impacts in
water quality in February 2016.
Laboratory Measurements
1.6.18
Laboratory analysis of February
2016 results indicated that concentrations of Cadmium, Chromium, Nickel, Lead,
Silver and Mercury were below their limit of reporting at all stations. Arsenic, Copper and Zinc were detected
in February 2016 samples and the concentrations were similar amongst stations (Table B6
of Annex B;
Figure
28 of Annex
D).
1.6.19
For nutrients, concentrations of Total
Inorganic Nitrogen (TIN) at Tai Ho Bay 2 station in February 2016 exceeded the
WQO (0.5 mg/L) (Table B6 of Annex
B; Figure 29 of Annex D). It should be noted that due to effect of
Pearl River, the North Western WCZ has historically experienced higher levels
of TIN ([11]). Since TIN concentrations were recorded
to be similar amongst all stations, the exceedances of
TIN WQO at all stations are unlikely to be caused by the disposal operation at
CMP 2. Ammonia Nitrogen (NH3-N)
concentration was relatively similar amongst all stations (Table B6
of Annex B;
Figure
29 of Annex
D). Levels
of 5-day Biochemical Oxygen Demand (BOD5) appear to be higher at Tai
Ho Bay 1 and Shum Shui Kok
stations in February 2016 (Table B6 of Annex B;
Figure
30 of Annex
D).
1.6.20
Concentrations of SS complied
with the WQO (13.5 mg/L for dry season) and the Action and Limit Levels at all
stations in February 2016 (Table B6 of Annex B;
Figure
32 of Annex
D).
1.6.21
Overall, results of the Routine Water
Quality Monitoring indicated that the disposal operation at CMP 2 did not
appear to cause any unacceptable deterioration in water quality in February 2016. Detailed statistical analysis will be
presented in the Quarterly Report to investigate any spatial and temporal
trends of potential concern.
1.6.22
Water Column Profiling
of CMP 2 ¡V February 2016
1.6.23
Water Column Profiling was
undertaken at a total of two sampling stations (Upstream and Downstream
stations) on 1 February 2016. The monitoring results
have been assessed for compliance with the WQOs (see Section 1.5.7 for details). Levels
of DO and Turbidity were also assessed for compliance with the Action and Limit
Levels (see Table B4 of Annex
B for details).
In-situ Measurements
1.6.24
Analyses of results for February 2016 indicated that levels of Salinity, DO and pH complied
with the WQOs at both Downstream and Upstream
stations (Table B7 of Annex B).
In
addition, DO and Turbidity at all stations complied with the Action
and Limit Levels (Table B7 of
Annex B).
Laboratory Measurements for
SS
1.6.25
Analyses of results for February
2016 indicated that the SS levels exceeded the WQO at both Upstream and
Downstream stations. However, both
Upstream and Downstream stations complied with the Action and Limit Levels (Table B7
of Annex B).
1.6.26
Overall, the monitoring results
indicated that the mud disposal operation at CMP 2 did not appear to cause any
deterioration in water quality during this reporting period.
1.6.27
Water Quality
Monitoring during Capping of SB CMP 1 ¡V February 2016
1.6.28
The monitoring results obtained
during
February 2016 sampling in the dry season have been assessed for compliance
with the WQOs (see Section 1.5.7 for
details). Levels
of DO and Turbidity were also assessed for compliance with the Action and Limit
Levels (see Table B4 of Annex
B for details). A total of fourteen
(14)
monitoring stations were sampled in February 2016 as shown in Figure 1.7. Graphical presentation of the monitoring
results is provided in Annex
D.
In-situ Measurements
1.6.29
Graphical presentation of the
monitoring results (Temperature, DO, pH, Salinity and Turbidity) is shown in Figures 32-37 of Annex D. Levels of pH and Salinity at all stations
in February 2016
complied with the WQO (Table B8 of Annex B;
Figures
32 and 37 of Annex D). The levels of
Turbidity at all stations complied with the Action and Limit levels in February 2016.
(Table
B8 of Annex
B; Figure 33 of Annex
D). DO at all
stations also complied with the WQO and the Action and Limit levels in February
2016
(Table B8 of Annex B; Figure 35
of Annex D).
Laboratory Measurement
1.6.30
Concentrations of SS were
recorded higher than the WQO (13.5
mg/L for dry season) at Reference, Intermediate, Ma
Wan, Sham Shui Kok and Tai
Mo To stations in February 2016 (Table B8
of Annex B;
Figure
39 of Annex
B).
However, SS at all stations
complied with the Action and Limit Levels in February 2016 (Table B8 of Annex B).
1.6.31
For nutrients, concentrations of NH3
were relatively similar
amongst all stations
(Table
B8 of Annex
B; Figure 39 of
Annex D). TIN at Reference, Impact, Sham Shui Kok, Tai Mo To and Tai Ho
Bay 1 stations exceeded the WQO of 0.5 mg/L in February 2016 (Table B8
of Annex B;
Figure
41 of Annex D). As discussed in Section 1.6.19,
the North Western WCZ has
historically experienced higher levels of TIN and the exceedances of TIN WQO at these stations are unlikely to be
caused by the capping operation at CMP 1.
1.6.32
Concentrations of BOD5
were similar at all stations in February 2016 (Table B8
of Annex B;
Figure
41 of Annex D).
1.6.33
Statistical
analysis will be undertaken and presented in the quarterly report to investigate
whether the capping operations at CMP 1 is causing any unacceptable impacts in
water quality of the area.
1.7
Activities Scheduled for the
Next Month
1.7.1
The
following monitoring activities will be conducted in the next
monthly period of March
2016 for SB CMPs:
¡P
Pit Specific Sediment Chemistry of CMP 2;
and
¡P
Water Column Profiling of CMP 2.
1.7.2
The
following monitoring activities will be conducted in the next
monthly period of March
2016 for ESC CMPs:
¡P
Pit Specific Sediment Chemistry of ESC CMP Vd; and
¡P Water
Column Profiling of ESC CMP Vd.
1.7.3
The sampling schedule is presented in Annex A.
1.8.1
A summary of the Study programme is
presented in Annex E.