Agreement No.
CE 23/2012 (EP)
Environmental
Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
38th MONTHLY PROGRESS REPORT FOR October 2015
1.1
Background
1.1.1
Since early 1990s, contaminated sediment
([1]) arising from various
construction works (e.g. dredging and reclamation projects) in Hong Kong has been disposed of at a series of seabed pits
at East of Sha Chau
(ESC). In late 2008, a review indicated that the existing and planned
facilities at ESC would not be able to meet the disposal demand after
2012. In order to meet this demand, the Hong Kong Special Administrative
Region Government (HKSARG) decided to implement a new contained aquatic
disposal (CAD) ([2]) facility at the South of The Brothers
(SB CMPs) which had been under consideration for a
number of years.
1.1.2
The environmental acceptability of the
construction and operation of the Project had been confirmed by findings of the
associated Environmental Impact Assessment (EIA) study completed in 2005 under
Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection (DEP) approved this EIA
report under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) in September
2005 (EIA Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA
recommendation, prior to commencement of construction works for the SB CMPs, the Civil Engineering and Development Department
(CEDD) undertook a detailed review and update of the EIA findings for the SB
site ([4]). Findings of the EIA review
undertaken in 2009/ 2010 confirmed that the construction and operation of the
SB site had been predicted to be environmentally acceptable.
1.1.4
Environmental Permits (EPs) (EP-312/2008/A and EP-427/2011A) were
issued by the Environmental Protection Department (EPD) to the CEDD, the Permit
Holder, on 28 November 2008 for ESC CMP V and on 23 December 2011 for SB CMPs, respectively. Under the requirements of the
EPs, an Environmental Monitoring and Audit
(EM&A) programme as set out in the EM&A Manuals ()
() is required
to be implemented for the CMPs.
1.1.5
The present EM&A programme under Agreement
No. CE 23/2012 (EP) covers the dredging, disposal and
capping operations of the SB CMPs as well as ESC CMPs. Detailed works schedule for both CMPs is shown in Figure 1.1. In October 2015, the following works were being
undertaken at the CMPs:
· Dredging operation
at ESC CMP Vd;
· Capping operations
at ESC CMP Va; and
· Disposal of
contaminated mud at SB CMP 2.
Figure
1.1
Works Schedule for ESC CMPs and SB CMPs
1.2
Reporting Period
1.2.1
This 38th
Monthly Progress Report covers the
EM&A activities for the reporting month of October
2015.
1.3
Details of Sampling and Laboratory Testing Activities
1.3.1
The following monitoring activities have
been undertaken for ESC CMPs in October 2015:
· Impact Water
Quality Monitoring during Dredging Operations of ESC CMPs was undertaken on 2, 5, 7, 9, 12, 14, 16, 19, 21,
23, 26, 28 and 30 October 2015.
1.3.2
The following monitoring activities have
been undertaken for SB CMPs in October 2015:
· Water Column
Profiling of CMP 2 was undertaken on 13 October 2015;
· Pit Specific
Sediment Chemistry of CMP 2 was undertaken on 15 October 2015; and
· Routine Water
Quality Monitoring of CMP 2 was undertaken on 16 October 2015.
1.4
Details of Outstanding Sampling and/or Analysis
1.4.1
No outstanding sampling remained for October
2015.
1.4.2
A summary of field activities conducted
are presented in Annex A. The following laboratory analyses were still in
progress during the preparation of this monthly report and hence are not
presented in this monthly report:
· Laboratory analyses of sediment samples collected for Pit
Specific Sediment Chemistry of SB CMP 2 in October 2015.
1.5
Brief Discussion of the Monitoring Results for ESC
CMPs
1.5.1
Brief discussion of the monitoring results of the Impact Water
Quality Monitoring during Dredging Operations of ESC CMP Vd conducted in October 2015 is presented below.
1.5.2
Impact
Water Quality Monitoring during Dredging Operations of ESC CMP Vd 2 to 31 October 2015
1.5.3
Impact Water Quality Monitoring during Dredging Operations
of ESC CMP Vd was conducted three times per week in October 2015. On
each survey day, monitoring was conducted during both mid-ebb and mid-flood
tides at two Reference (Upstream) stations and five Impact (Downstream)
stations of the dredging operations at ESC CMP Vd.
Monitoring was also conducted at one Sensitive Receiver Station situated in Ma
Wan. A total of eight (8) stations were monitored and locations of the
sampling stations are shown in Figure 1.2.
1.5.4
Monitoring results are presented in Table
B1 of Annex B. Daily dredging volume in October 2015 is reported in Annex C. It should be noted that dredging activities were not carried
out on 3, 4, 16 20 and 23 31 October 2015 during the reporting
period. Levels of Dissolved Oxygen (DO), Turbidity and Suspended Solid
(SS) generally complied with the Action and Limit Levels (see Table
B2 of Annex B for details) set in the Baseline Monitoring Report (),
except for the following occasion of exceedances
discussed in Table 1.1 below.
1.5.5
As presented in Table 1.1, the results indicated that the dredging operations at ESC
CMP Vd did not appear to cause any unacceptable
deterioration in water quality during this reporting period. Therefore,
no further action, except for those recommended in the Environmental Permit (EP-312/2008/A), are considered necessary for the dredging operations.
Table 1.1
Details of Exceedances Recorded for Impact Water
Quality Monitoring during Dredging Operations of ESC CMP Vd between 2 and 30 October 2015
Date
|
Tide
|
Parameter
|
Station
|
Type
|
Remarks
|
2 October 2015
|
Mid-Flood
|
Turbidity
|
DS2
|
Limit
|
The exceedance
was not considered as indicating any unacceptable impacts from the dredging
operations to Water Sensitive Receivers (WSRs)
outside the works area because Stations DS2 are located further away from the
works area of CMP Vd when compared to station DS1
at which the levels of Turbidity did not exceed the Action and Limit Levels
during the same tidal period.
|
26 October 2015
|
Mid-Flood
|
Turbidity
|
DS2
|
Limit
|
These exceedances were not considered as indicating any
unacceptable impacts from the dredging operations to WSRs
outside the works area because dredging activities were not carried out during the period of 3, 4, 16 20
and 23 31 October 2015.
|
28 October 2015
|
Mid-Ebb
|
Turbidity
|
DS3
|
Limit
|
28 October 2015
|
Mid-Ebb
|
Turbidity
|
DS5
|
Limit
|
30 October 2015
|
Mid-Flood
|
Turbidity
|
DS2
|
Action
|
30 October 2015
|
Mid-Flood
|
SS
|
DS1
|
Action
|
1.6
Brief
Discussion of the Monitoring Results for SB CMPs
1.6.1
Brief discussion of the monitoring
results of the following activities for SB CMPs is
presented in this 38th Monthly Progress Report:
· Pit Specific
Sediment Chemistry of CMP 2 in September 2015;
· Cumulative Impact
Sediment Chemistry of CMP 2 in August 2015;
· Routine Water
Quality Monitoring of CMP 2 in October 2015; and
· Water Column
Profiling of CMP 2 in October 2015.
1.6.2
Pit
Specific Sediment Chemistry of CMP 2 September 2015
1.6.3
Monitoring locations for Pit
Specific Sediment Chemistry for CMP 2 are shown
in Figure
1.3. A total of six (6) monitoring stations
were sampled in September 2015.
1.6.4
The concentrations of most inorganic
contaminants (Arsenic, Cadmium, Chromium, Lead, Mercury, Nickel and Zinc) were
lower than the Lower Chemical Exceedance Level (LCEL)
at all stations, except Copper and Silver (Figures 1 and 2 of Annex D). Copper exceeded the LCEL at Active Pit stations SB-NPBA and SB-NPBB
(Figure 1 of Annex D) while Silver
exceeded the Upper Chemical Exceedance Level (UCEL)
and LCEL and at Active Pit station SB-NPBA and SB-NPBB, respectively (Figure 2 of Annex D).
1.6.5
Higher
Copper and Silver concentrations were recorded within the Active Pit stations
only which were receiving contaminated mud during the reporting month. Therefore, there is no evidence indicating any
dispersal of contaminants from the active pit due to the disposal activities.
1.6.6
For organic contaminants, the concentrations of Total Organic
Carbon (TOC) were similar at all stations, except lower concentrations were
recorded in Pit Edge station SB-NEBB and Active Pit station SB-NPBB (Figure 3 of Annex D). Tributyltin (TBT)
concentrations were observed to be higher at Active Pit stations SB-NPBA and
SB-NPBB (Figure 4 of Annex D). Low and High Molecular Weight Polycyclic
Aromatic Hydrocarbons (PAHs), Total Polychlorinated
Biphenyls (PCBs), 4,4-dichlorodiphenyldichloroethylene (DDE) and Total
dichlorodiphenyltrichloroethane (DDT) concentrations were below the limit of
reporting at most stations, except High MW PAHs at
Active Pit stations SB-NPBB (Figure 5 of Annex D).
1.6.7
Overall,
there is no evidence indicating any unacceptable environmental impacts to
sediment quality as a result of the contaminated mud disposal operations at CMP
2 in September 2015. Statistical analysis will be undertaken and
presented in the quarterly report to investigate whether there are any
unacceptable impacts in the area caused by the contaminated mud disposal.
1.6.8
Cumulative
Impact Sediment Chemistry of SB CMPs August 2015
1.6.9
Monitoring locations for Cumulative
Impact Sediment Chemistry for
SB CMPs are shown
in Figure
1.4. A total of eleven (11) monitoring
stations were sampled in August 2015.
1.6.10
Analyses of results for the Cumulative
Impact Sediment Chemistry Monitoring indicated
that the concentrations of all inorganic contaminants were generally below the LCEL in August 2015,
except Arsenic at Tai Ho Bay Station 2 (THB2) (Figures 6 and 7 of Annex D). It should be noted that the average concentration of Arsenic in the Earths crust is generally
~2mg/kg, significantly higher Arsenic concentrations (median = 14 mg/kg) have
been recorded in Hong Kongs onshore sediments
([8]). It is presumed that the natural concentrations of Arsenic are
similar in onshore and offshore sediments ([9]),
and relatively high Arsenic levels may thus occur throughout Hong
Kong. Therefore, the
LCEL exceedances of Arsenic are unlikely to be caused
by the disposal operations at CMP 2 but rather as a result of naturally occurring deposits.
1.6.11
For organic contaminants, concentrations of TOC at Near-field stations
SB-RNA and SB-RNB and Mid-field stations SB-RMA and SB-RMB were recorded to be
lower than other stations (Figure 8 of Annex D). Concentrations of TBTs
were recorded to be higher at Ma Wan station (Figure 9 of Annex D). Total
DDT, 4,4-DDE, Total PCBs as
well as Low and High Molecular Weight PAHs were recorded below the limit of
reporting at all stations.
1.6.12
Overall,
there is no evidence indicating any unacceptable environmental impacts to
sediment quality as a result of the contaminated mud disposal operations at CMP
2 in August 2015. Statistical analysis will be undertaken and presented
in the quarterly report to investigate whether there are any unacceptable
impacts in the area caused by the contaminated mud disposal.
1.6.13
Routine
Water Quality Monitoring of SB CMP 2 October 2015
1.6.14
The monitoring results for the Routine Water Quality Monitoring conducted
in October 2015 in the wet season have been assessed for compliance with the Water Quality Objectives (WQOs)
set by Environmental Protection Department (EPD). This consists of a
review of the EPD routine water quality monitoring data for the wet season
period (April to October) of 2004 - 2013 from stations in the Northwestern Water Control Zone (WCZ), where the CMPs are located ().
For Salinity, the averaged value obtained from the Reference stations was used
for the basis as the WQO. Levels of
DO and Turbidity were also assessed for compliance with the Action and Limit
Levels (see Table B3 of Annex B for
details). The monitoring results are shown in Figures
10-19 of Annex D and Tables B4 and B5 of Annex B. A total of
fourteen (14) monitoring stations were sampled in October 2015 as shown in Figure 1.5.
In-situ Measurements
1.6.15
Graphical presentation of the monitoring
results (Temperature, DO, pH, Salinity and Turbidity) is shown in Figures
10-15 of Annex D. Analyses of results for October 2015 indicated that the
levels of pH, DO and Salinity complied with the WQOs at
all stations (Impact, Intermediate, Reference and Water Sensitive Receiver
stations) in October 2015 (Figures 10 12, 14 of Annex D).
1.6.16
The levels of DO and Turbidity complied with the Action and Limit Levels
at all stations (Table B4 of
Annex B; Figures 12 and 15 of Annex D).
1.6.17
Overall, in-situ measurement results of the Routine
Water Quality Monitoring indicated that
the disposal operation at CMP 2 did not appear to cause any unacceptable
impacts in water quality in October 2015.
Laboratory
Measurements
1.6.18
Laboratory
analysis of October 2015 results indicated that concentrations of Arsenic,
Cadmium, Chromium, Lead, Silver and Mercury were below their limit of reporting
at all stations. Copper, Nickel and Zinc were detected in October 2015
samples and the concentrations were similar amongst stations (Figure 16 of Annex D). Results of laboratory analysis were shown in
Table B5 of Annex B.
1.6.19
For nutrients, concentrations of Total Inorganic
Nitrogen (TIN) at all stations in October 2015 exceeded the WQO (0.5 mg/L) (Figure 17 of Annex D). It should be noted that the North Western WCZ has
historically experienced higher levels of TIN and the exceedances of TIN WQO at these stations are unlikely to be
caused by the disposal operation at CMP 2. Ammonia Nitrogen (NH3-N)
concentration was relatively similar amongst all stations (Figure 17 of Annex D). Levels of 5-day Biochemical Oxygen Demand (BOD5)
appear to be higher at Shum Shui Kok
and Tai Mo To stations in October 2015 (Figure 18 of Annex D).
1.6.20
Concentrations
of SS exceeded the WQO (11.6 mg/L for wet season) at most stations,
except Impact, Tai Mo to and Tai Ho Bay 2 stations in October 2015.
However, concentrations of SS complied with the
Action and Limit Levels at all stations in October
2015 (Figure 19 of Annex D; Table B5 of
Annex B).
1.6.21
Overall, results of the Routine
Water Quality Monitoring indicated that
the disposal operation at CMP 2 did not appear to cause any unacceptable
deterioration in water quality in October 2015. Detailed statistical
analysis will be presented in the Quarterly Report to investigate any spatial
and temporal trends of potential concern.
1.6.22
Water
Column Profiling of CMP 2 October 2015
1.6.23
Water Column Profiling was undertaken at a total of two sampling stations (Upstream and
Downstream stations) on 13 October 2015. The monitoring results have been assessed for compliance with the WQOs (see Section
1.6.14 for details).
In-situ Measurements
1.6.24
Analyses of results for October 2015
indicated that levels of Salinity, DO and pH complied with the WQOs at both Downstream and Upstream stations (Table
B6 of Annex B). In addition, DO and Turbidity at all stations complied with
the Action and Limit Levels (Tables B3 and B6 of Annex B).
Laboratory
Measurements for SS
1.6.25
Analyses of results for October 2015
indicated that the SS levels only complied with the WQO at Downstream
stations. However, both Upstream and Downstream stations complied with
the Action and Limit Levels (Tables B3 and B6 of Annex B).
Overall, the
monitoring results indicated that the mud disposal operation at CMP 2 did not
appear to cause any deterioration in water quality during this reporting
period.
1.7
Activities Scheduled for the Next Month
1.7.1
The following monitoring activities will
be conducted in the next monthly period of November 2015 for SB CMPs:
· Pit Specific
Sediment Chemistry of CMP 2;
· Routine Water
Quality Monitoring of CMP 2; and
· Water Column
Profiling of CMP 2.
1.7.2
The following monitoring activities will be conducted in the next monthly period of November
2015 for ESC CMPs:
· Impact Monitoring
during Dredging Operations of ESC CMP Vd.
1.7.3
The sampling schedule is presented in
Annex A.
1.8
Study
Programme
1.8.1
A summary of the Study programme is
presented in Annex
E.