Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
36th MONTHLY PROGRESS REPORT FOR August
2015
1.1.1
Since early 1990s, contaminated sediment ([1]) arising from various construction works
(e.g. dredging and reclamation projects) in Hong Kong
has been disposed of at a series of seabed pits at East of Sha
Chau (ESC). In
late 2008, a review indicated that the existing and planned facilities at ESC
would not be able to meet the disposal demand after 2012. In order to meet this demand, the Hong Kong
Special Administrative Region Government (HKSARG) decided to implement a new
contained aquatic disposal (CAD) ([2]) facility at the South of The Brothers
(SB CMPs) which had been under consideration for a
number of years.
1.1.2
The environmental acceptability of the construction and
operation of the Project had been confirmed by findings of the associated
Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]).
The Director of Environmental Protection (DEP) approved this EIA report
under the Environmental
Impact Assessment Ordinance (Cap. 499) (EIAO) in September 2005 (EIA Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA recommendation, prior to
commencement of construction works for the SB CMPs,
the Civil Engineering and Development Department (CEDD) undertook a detailed
review and update of the EIA findings for the SB site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had been
predicted to be environmentally acceptable.
1.1.4
Environmental
Permits (EPs)
(EP-312/2008/A and EP-427/2011A) were issued by the Environmental
Protection Department (EPD) to the CEDD, the Permit Holder, on 28 November 2008
for ESC CMP V and on 23 December 2011 for SB CMPs,
respectively. Under the requirements of
the EPs, an Environmental
Monitoring and Audit (EM&A) programme as set out in the EM&A Manuals ()
()
is required to be implemented for the CMPs.
1.1.5
The present EM&A programme under Agreement No. CE 23/2012 (EP) covers the dredging,
disposal and capping operations of the SB CMPs
as well as ESC CMPs. Detailed works schedule for both CMPs is shown in Figure 1.1. In August 2015, the following works were
being undertaken at the CMPs:
· Capping operations at ESC CMPs;
· Capping operations at SB CMP 1; and
· Disposal of contaminated mud at SB CMP 2.
Figure 1.1 Works
Schedule for ESC CMPs and SB CMPs
1.2
Reporting
Period
1.2.1
This 36th Monthly Progress Report covers the EM&A activities for the reporting month of August 2015.
1.3
Details
of Sampling and Laboratory Testing Activities
1.3.1
The following monitoring activities have been undertaken for
ESC CMPs in August 2015:
·
Benthic Recolonisation Studies of ESC CMPs
was undertaken on 12 August 2015; and
1.3.2
Water Quality
Monitoring During Capping of ESC CMPs
was undertaken on 18 August 2015. The following monitoring activities have been
undertaken for SB CMPs in August 2015:
·
Water Column Profiling of CMP 2 was undertaken on 10 August 2015;
·
Routine Water Quality Monitoring of CMP 2 was
undertaken on 13 August 2015;
·
Pit Specific Sediment Chemistry of CMP 2 was undertaken on 17 August 2015;
·
Demersal Trawling for CMPs was undertaken on 19 and 20 August
2015;
·
Cumulative Impact Sediment Chemistry of CMP 2 was undertaken on 19 and 21 August 2015;
·
Sediment Toxicity Test of CMP 2 was undertaken on 19 and 21 August 2015;
·
Water Quality Monitoring During
Capping of CMP 1 was undertaken on 24 August 2015;
andBenthic Recolonisation
Studies of CMP 1 was undertaken on 26 August 2015.
1.4
Details
of Outstanding Sampling and/or Analysis
1.4.1
No outstanding sampling remained for August 2015.
1.4.2
A
summary of field activities conducted are presented in Annex A. The following laboratory analyses were still in
progress during the preparation of this monthly report and hence are not
presented in this monthly report:
·
Laboratory
analyses of sediment samples collected for Cumulative Impact Sediment Chemistry of SB CMP 2 in August 2015; and
·
Laboratory
analyses of sediment samples collected for Pit Specific Sediment Chemistry of SB CMP 2 in August 2015.
1.4.3
The
following laboratory analyses are in progress and will be presented in the
corresponding quarterly report:
·
Laboratory analyses of sediment samples collected for Benthic Recolonisation Studies of ESC CMPs and SB CMP 1 in August 2015;
·
Taxonomic
identification of fishery resources collected during Demersal Trawling for SB CMPs in July and August
2015; and
·
Laboratory analyses for Sediment Toxicity Test of SB CMP 2 in August
2015.
1.5
Brief
Discussion of the Monitoring Results for ESC CMPs
1.5.1
Brief discussion of the
monitoring results of the Water Quality Monitoring
during Capping of ESC CMPs conducted in August 2015 is presented below. Graphical
presentation of the monitoring results is provided in Annex B.
1.5.2
Water Quality Monitoring during Capping of ESC CMPs – August 2015
1.5.3
The
monitoring results obtained during August
2015 sampling in the wet season have
been assessed for compliance with the Water Quality Objectives (WQOs) set by Environmental Protection Department (EPD). This consists of a review of the EPD routine water
quality monitoring data for the wet season period (April to October) of 2004 - 2013 from
stations in the Northwestern Water Control Zone
(WCZ), where the CMPs are located (). For Salinity, the averaged value obtained
from the Reference stations was used for the basis as the WQO. Levels of Dissolved Oxygen (DO) and Turbidity were
also assessed for compliance with the Action and Limit Levels (see Table C1 of Annex C for details). A
total of ten (10) monitoring stations were sampled in August 2015 as
shown in Figure 1.2.
In-situ Measurements
1.5.4
Graphical
presentation of the monitoring results (Temperature, DO, pH, Salinity and Turbidity) is shown in Figures 1-6 of Annex B. Levels of Dissolved Oxygen (DO) and pH at all
stations in August 2015 complied with the WQO and
the Action and Limit levels (Table C1 of
Annex
C). Level of Salinity
at most station also complied with WQO, except for Ma Wan station. The
higher Salinities recorded at Ma Wan station are likely to be caused by the
larger separation distance to Pearl River mouth, which release a large amount
of freshwater runoff in the area during flooding, when compared to the
Reference stations.
Laboratory
Measurements for Suspended Solids (SS)
Concentrations of SS complied with the WQO at all stations in August 2015, except for the Reference
stations (Figure 7 of Annex B; Table C2 of Annex C). However, concentrations of SS at all stations
complied with the Action and Limit Levels. Further statistical analysis will
be undertaken in the quarterly report to investigate whether the capping
operations at ESC CMPs is causing any unacceptable
deterioration in water quality of the area.
1.6.1
Brief discussion of the
monitoring results of the following activities for SB CMPs
is presented in this 36th Monthly Progress Report:
·
Water Quality Monitoring During Capping of CMP 1 in August 2015;
·
Water Column Profiling of CMP 2 in
August 2015; and
·
Routine Water Quality Monitoring of CMP 2 in August 2015.
1.6.2
Water Quality Monitoring during Capping of SB CMP 1 – August 2015
1.6.3
The
monitoring results obtained during August
2015 sampling in the wet season have
been assessed for compliance with the WQOs (see Section 1.5.3 for details). Levels of DO and Turbidity were also assessed for
compliance with the Action and Limit Levels (see Table C3 of Annex C for details). A
total of fourteen (14) monitoring stations were sampled in August 2015 as
shown in Figure 1.3. Graphical presentation of the monitoring
results is provided in Annex B.
In-situ Measurements
1.6.4
Graphical
presentation of the monitoring results (Temperature, DO, pH, Salinity and
Turbidity) is shown in Figures 8-13 of Annex B. Levels of pH at all
stations in August 2015 complied with the WQO. DO at most stations complied
with the WQO and the Action and Limit levels except at Sham Shui Kok station in August 2015 (Table C3 of Annex C). The exceedance of WQO and the Action and Limit levels at Sham Shui Kok station was unlikely to
be caused by the capping operation at SB as the levels of DO complied with the
WQO and the Action and Limit levels at all other stations, including Impact stations
which are located closer to CMP 1. In
addition, the levels of Turbidity complied with the Action and Limit levels
at all stations in August 2015 (Table C3 and C4 of Annex C).
1.6.5
Levels
of Salinity at most stations complied
with the WQO except at Intermediate, Sham Shui Kok, Tai Ho
Bay 2 and Ma Wan stations. The lower Salinities
recorded at Tai Ho Bay 2 and Reference stations are likely
due to the close proximity of the nearby streams, which release large amount of
freshwater runoff in the area during flooding.
The Salinities at other stations were higher
or above
the WQO as they were located further away from the Tai Ho Bay and Reference
stations which experienced less freshwater runoff from the nearby streams.
Laboratory Measurements
1.6.6
Concentrations of SS complied with the WQO (11.6
mg/L for wet season) at Intermediate, Ma Wan, Tai Ho Bay
2 and Tai Mo To stations, but not at Reference, Impact, Tai Ho Bay 1
and Sham Shui Kok stations
in August 2015
(Figure 14 of Annex B).
However, SS at all stations complied with the Action
and Limit Levels in August 2015 (Table C3 and C4 of
Annex C).
1.6.7
For nutrients, concentrations of Ammonia (NH3)
were relatively similar amongst most
stations except
a slightly lower value was recorded at Tai Ho Bay 2 station (Figures 15
of Annex B). Total Inorganic
Nitrogen (TIN) at Impact, Reference, Tai Ho Bay 1 and Tai Mo To stations exceeded the
WQO of 0.5 mg/L in August 2015 (Figure
16 of Annex B). It should be noted
that the North Western WCZ has historically experienced higher
levels of TIN and the exceedances
of TIN WQO at these stations are unlikely to be caused by the capping operation
at CMP 1.
1.6.8
Concentrations of Biochemical Oxygen Demand (BOD5)
were similar at most stations except higher values
were recorded at Reference stations in August 2015 (Figures 17
of Annex B).
1.6.9
Statistical analysis will be
undertaken and presented in the quarterly report to investigate whether the
capping operations at CMP 1 is causing any unacceptable impacts in water quality of the
area.
1.6.10
Routine Water Quality Monitoring of SB CMP
2 – August 2015
1.6.11
The monitoring results for the Routine Water Quality
Monitoring conducted in August 2015 in the wet season have
been assessed for compliance with the WQOs (see Section 1.5.3 for details). Levels of Dissolved Oxygen (DO) and Turbidity were
also assessed for compliance with the Action and Limit Levels (see Table C3 of Annex C for details). The
monitoring results are shown in Figures 18-28 of Annex B and Tables C5 and C6 of Annex C. A total of twenty (20)
monitoring stations were sampled in August 2015 as shown in Figure 1.4.
In-situ Measurements
1.6.12
Graphical
presentation of the monitoring results (Temperature, DO, pH, Salinity and
Turbidity) is shown in Figures 18-23 of Annex B. Analyses of results for August 2015 indicated that the
levels of pH and DO complied with the WQOs at
all stations (Impact, Intermediate, Reference and Water Sensitive Receiver
stations) in August 2015 (Figures 18 – 20 of Annex B).
1.6.13
The levels of Salinity at Impact, Intermediate and Water
Sensitive Receiver stations exceeded the WQO range in August 2015 (Figure 22 of Annex B). The lower Salinities recorded at these
stations, which lead to exceedance of the WQO, is
likely to be caused by the freshwater discharged from the Pearl River Delta
during the summer months which tend to form a surface layer of low salinity
water at these stations with shallower depth when compared with the Reference
stations.
1.6.14
The levels of DO and Turbidity complied with the Action and
Limit Levels at all stations (Figures
19 and 22 of Annex B; Table C5
of Annex C).
1.6.15
Overall, in-situ measurement results of
the Routine Water Quality
Monitoring indicated
that the disposal operation at CMP 2 did not appear to cause any unacceptable impacts in water quality in August
2015.
Laboratory Measurements
1.6.16
Laboratory analysis of August 2015 results indicated
that concentrations of Cadmium, Chromium, Silver and Mercury were below their limit of reporting at all stations. Arsenic, Copper, Lead, Nickel and Zinc were
detected in August 2015 samples and the concentrations were similar amongst
stations (Figures 24-25 of Annex
B). Results of
laboratory analysis were shown in Table C6 of Annex
C.
1.6.17
For nutrients,
concentrations of TIN at all stations in August 2015 exceeded the WQO (0.5mg/L) (Figure 26 of
Annex B). As discussed in Section
1.6.7, the North Western WCZ has historically experienced higher
levels of TIN and the exceedances
of TIN WQO at all stations in August 2015 were unlikely to be caused by the disposal operation
at CMP 2. Ammonia Nitrogen (NH3-N)
concentration was relatively similar amongst all stations (Figure
26 of Annex
B). Levels of
5-day Biochemical Oxygen Demand (BOD5) appear to be higher at Tai Ho
Bay 1 and Shum Shui Kok stations in August 2015 (Figure
27 of Annex
B).
1.6.18
Concentrations of SS complied the WQO (11.6 mg/L for
wet season) at all stations, except Reference stations in August 2015. Concentrations of SS complied with the Action and Limit Levels at all stations in August 2015 (Figure 28 of Annex B;
Table C6 of Annex C).
1.6.19
Overall, results of the Routine Water Quality Monitoring indicated that the
disposal operation at CMP 2 did not appear to cause any unacceptable
deterioration in water quality in August 2015. Detailed statistical analysis will be presented
in the Quarterly Report to investigate any spatial and temporal trends of
potential concern.
1.6.20
Water Column Profiling of CMP 2 – August 2015
1.6.21
Water Column Profiling was undertaken at a total of two sampling stations
(Upstream and Downstream stations) on 10
August 2015. The water quality monitoring results have been
assessed for compliance with the WQOs as discussed in Section
1.5.3. The
monitoring results were also compared with the Action and Limit Levels set in Baseline Monitoring Report (see
Table C3 of Annex C for details).
In-situ Measurements
1.6.22
Analyses
of results for August 2015 indicated that levels of Salinity, DO and pH complied with the WQOs at both
Downstream and Upstream stations (Table C7 of Annex C). In addition, DO
and Turbidity at all stations complied with the Action and Limit Levels (Tables C3 and C7 of Annex C).
Laboratory Measurements for SS
1.6.23
Analyses
of results for August 2015 indicated
that the SS levels at both Upstream and
Downstream stations complied with the WQO.
Both Upstream and Downstream stations also complied with the Action and Limit Levels (Tables
C3 and C7 of Annex C).
Overall, the
monitoring results indicated that the mud disposal operation at CMP 2 did not
appear to cause any deterioration in water quality during this reporting
period.
1.7
Activities
Scheduled for the Next Month
1.7.1
The
following monitoring activities will be conducted in the next monthly period of
September 2015 for SB CMPs:
·
Pit Specific Sediment Chemistry of CMP 2; and
·
Water Column Profiling of CMP 2.
1.7.2
The following monitoring activities will be conducted in the next
monthly period of September 2015 for ESC CMPs:
·
Impact Monitoring during
Dredging Operations of ESC CMPs.
1.7.3
The
sampling schedule is presented in Annex A.
1.8.1
A
summary of the Study programme is presented in Annex D.