Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
34th MONTHLY PROGRESS REPORT FOR JUne 2015
1.1.1
Since early 1990s, contaminated sediment ([1])
arising from various construction works (e.g. dredging and reclamation
projects) in Hong Kong has been disposed of at
a series of seabed pits at East of Sha Chau (ESC). In late
2008, a review indicated that the existing and planned facilities at ESC would
not be able to meet the disposal demand after 2012. In order to meet this demand, the Hong Kong
Special Administrative Region Government (HKSARG) decided to implement a new
contained aquatic disposal (CAD) ([2])
facility at the South of The Brothers (SB CMPs) which
had been under consideration for a number of years.
1.1.2
The environmental acceptability of the
construction and operation of the Project had been confirmed by findings of the
associated Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO) in September
2005 (EIA
Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA
recommendation, prior to commencement of construction works for the SB CMPs, the Civil Engineering and Development Department
(CEDD) undertook a detailed review and update of the EIA findings for the SB
site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had
been predicted to be environmentally acceptable.
1.1.4
Environmental Permits (EPs) (EP-312/2008/A and EP-427/2011A) were
issued by the Environmental Protection Department (EPD) to the CEDD, the Permit
Holder, on 28 November 2008 for ESC CMP V and on 23 December 2011 for SB CMPs, respectively. Under the requirements of the EPs, an
Environmental Monitoring and Audit (EM&A) programme as set out in the
EM&A Manuals ()
()
is required to be implemented for the CMPs.
1.1.5
The present EM&A programme under Agreement No. CE
23/2012 (EP) covers the dredging, disposal and capping operations of the
SB CMPs as well as ESC CMPs. Detailed works schedule for both CMPs is shown in Figure 1.1.
In June 2015, the following works were being undertaken at the CMPs:
· Capping operations at ESC CMPs;
· Capping operations at SB CMP 1; and
· Disposal of contaminated mud at SB CMP 2.
Figure 1.1 Works
Schedule for ESC CMPs and SB CMPs
1.2
Reporting Period
1.2.1
This 34th Monthly Progress
Report covers the EM&A activities for
the reporting month of June 2015.
1.3
Details of Sampling and Laboratory Testing
Activities
1.3.1
The following monitoring
activity has been undertaken for ESC CMPs in June 2015:
·
Water Quality Monitoring during Capping of ESC CMPs was
undertaken on 2 June 2015.
1.3.2
The following
monitoring activities have been undertaken for SB CMPs
in June 2015:
·
Pit Specific Sediment Chemistry of CMP 2 was undertaken on 8 June 2015;
·
Cumulative Impact Specific Chemistry of CMP 2 was undertaken 9 June 2015;
·
Water Quality Monitoring during Capping Operations of CMP 1 was undertaken on 10 June 2015; and
·
Water Column Profiling of CMP 2 was undertaken on 11 June 2015.
1.4
Details of Outstanding Sampling and/or
Analysis
1.4.1
No outstanding sampling remained for June 2015.
The following laboratory analyses were still in progress during the
preparation of this monthly report and hence are not presented in this monthly
report:
· Laboratory
analyses of sediment samples collected for Pit
Specific Sediment Chemistry of CMP 2 in June 2015; and
· Laboratory
analyses of sediment samples collected for Cumulative
Impact Specific Chemistry of CMP 2 in June 2015.
1.4.2
A summary of
field activities conducted are presented in Annex A.
1.5
Brief
Discussion of the Monitoring Results for ESC CMPs
1.5.1
Brief discussion of the monitoring results of Water Quality Monitoring during Capping of ESC CMPs conducted on 2 June 2015 is presented below.
1.5.2
Water Quality Monitoring during Capping – June 2015
1.5.3
The monitoring
results obtained during June 2015 sampling in the wet season have been
assessed for compliance with the Water Quality Objectives (WQOs)
through a review of the Environmental Protection Department (EPD) routine water
quality monitoring data for the wet season period (April to October) of 2004 – 2013 from
stations in the North Western Water Control Zone (WCZ), where ESC CMPs are located.
For Salinity, the average value obtained from the Reference stations was
used for the basis as the WQO. A total
of sixteen (16) monitoring stations were sampled in June 2015 as shown in Figure 1.2. Graphical presentation of the monitoring
results is provided in Annex B.
In-situ Measurements
1.5.4
Graphical
presentation of the monitoring results (Temperature, Dissolved Oxygen (DO), pH,
Salinity and Turbidity) is shown in Figures 1-6 of Annex B. Levels of DO, pH
and Salinity at most stations in June 2015 complied
with the WQO except Salinity at Ma Wan station. The higher Salinity
recorded at Ma Wan station is likely to be caused by its greater separation
distance from the Pearl River mouth, which is
a key source of freshwater inputs in the area, when compared to the Reference
stations. The turbidity complied with
the Action and Limit levels at all stations in June 2015 (Table C1 of Annex C).
Laboratory Measurements for Suspended Solids
(SS)
1.5.5
Concentrations of
SS complied with the WQO at most stations except
at Impact stations in June 2015 (Figure
7 of
Annex B; Table C2 of Annex C). However, the SS
complied with the Action and Limit levels at all stations in June 2015 (Table C1 of Annex C). Further statistical
analysis will be undertaken in the quarterly report to investigate whether the
capping operations at ESC CMPs is causing any
unacceptable deterioration in water quality of the area.
1.6
Brief Discussion of the Monitoring Results
for SB CMPs
1.6.1
Brief discussion of the monitoring results of the
following activities for SB CMPs is presented in this
34th Monthly Progress Report:
· Laboratory
analyses of sediment samples collected for Pit
Specific Sediment Chemistry of CMP 2 in May 2015;
· Water
Quality Monitoring during Capping Operations of CMP 1 conducted on 10 June 2015; and
·
Water Column Profiling of CMP 2 undertaken on 11 June 2015.
1.6.2
Pit Specific Sediment Chemistry of CMP 2 – May 2015
1.6.3
Monitoring
locations for Pit Specific Sediment Chemistry for CMP 2 are shown in Figure 1.3. A total of six (6) monitoring
stations were sampled in May 2015.
1.6.4
Zinc exceeded the Lower
Chemical Exceedance Level (LCEL) at Active Pit
station SB-NPBA while Nickel exceeded the Upper Chemical Exceedance
Level (UCEL) at Active Pit station SB-NPBB. In addition, Copper
and Silver exceeded the UCEL at Active Pit
stations SB-NPBA and SB-NPBB in May 2015. The concentrations
of other inorganic contaminants (Cadmium, Chromium, Mercury, Lead and Arsenic) were
lower than the LCEL at all stations. As higher Copper, Nickel, Silver and Zinc concentrations
were recorded within the Active Pit stations only which were receiving
contaminated mud during the reporting month, there is no evidence indicating
any dispersal of contaminants from the active pit.
1.6.5
For organic contaminants, the
concentrations of Total Organic Carbon (TOC) were similar at most stations
except lower values were recorded at Pit Edge
station SB-NEBB and Near Pit station SB-NNBB (Figure 10 of Annex B). Tributyltin
(TBT) concentrations were observed to be higher at Active Pit station SB-NPBA
and Near Pit station SB-NNBB (Figure 11 of Annex B).
Total dichlorodiphenyltrichloroethane (DDT), 4,4’-dichlorodiphenyldichloroethylene
(DDE), Total Polychlorinated Biphenyls (PCBs), Low and High Molecular Weight Polycyclic
Aromatic Hydrocarbons (MW PAHs) were below the limit
of reporting at most stations (except High MW PAHs at
Active Pit station SB-NPBA) in May 2015 (Figure 12 of Annex B).
1.6.6
Overall, there is no evidence
indicating any unacceptable environmental impacts to sediment quality as a
result of the contaminated mud disposal operations at CMP 2 in May 2015. Statistical analysis will be undertaken and
presented in the quarterly report to investigate whether there are any
unacceptable impacts in the area caused by the contaminated mud disposal.
1.6.7
Water Quality Monitoring during Capping Operations
of CMP 1– June 2015
1.6.8
The monitoring
results obtained during June 2015 sampling in the wet season have been assessed
for compliance with the WQOs (see Section 1.5.3 for details). A total of
fourteen (14) monitoring stations were sampled in June 2015 as shown in Figure 1.4. Graphical
presentation of the monitoring results is provided in Annex B.
In-situ
Measurements
1.6.9
Graphical
presentation of the monitoring results (Temperature, Dissolved Oxygen (DO), pH,
Salinity and Turbidity) is shown in Figures 13-18 of Annex B. Levels of pH at all
stations in June 2015 complied with the WQO.
DO at most stations complied with the WQO
except at Intermediate and Ma Wan stations. As
Intermediate and Ma Wan stations are located further away from the CMP 1 and DO
at the Impact stations complied with the WQO, it is considered that the WQO exceedances of DO at these stations were possibly caused by
the natural background variation in water quality of the area, but not from the
capping operation of CMP 1. The DO and turbidity complied with the Action and Limit
levels at all stations in June 2015 (Table C3 and C4 of Annex C).
1.6.10
Levels of Salinity
exceeded the WQO at most stations except at Tai Ho Bay stations. The
lower Salinities recorded at Tai Ho Bay and Reference stations are likely due
to the close proximity of the nearby streams and Pearl
River mouth, which release large amount of freshwater runoff in
the area during flooding. The Salinities
at other stations were above the WQO as they were located further away from the
Tai Ho Bay and Reference stations which experienced less freshwater runoff from
the nearby streams.
Laboratory Measurements
1.6.11
Concentrations
of SS complied with the WQO (11.6 mg/L for wet season) at most stations in June 2015 except at Tai Ho Bay station 1
(Figure 19 of Annex B). However, SS at
all stations complied with the Action and Limit Levels in June 2015 (Table C3 and C4 of Annex C).
1.6.12
For nutrients,
concentrations of Ammonia (NH3) were relatively similar
amongst most stations except a slightly lower value was recorded at
Reference and Tai Ho Bay stations (Figures 20 of Annex B). Concentrations of Biochemical Oxygen Demand
(BOD5) were similar at most stations except higher values were recorded at Tai Ho Bay stations in June 2015. Total Inorganic Nitrogen (TIN) at all
stations exceeded the WQO of 0.5 mg/L in June 2015 (Figure 22 of Annex B). It should
be noted that the
North Western WCZ has historically experienced higher levels of TIN and the exceedances
of TIN WQO at all stations are unlikely to be caused by the capping operation
at CMP 1.
1.6.13
Since lower BOD5 was recorded for both Impact and Reference stations,
the higher concentration at Tai Ho Bay stations is likely due to
the natural fluctuation of BOD5 in the environment. Therefore, there is no evidence indicating
any degradation of water quality due to the capping activities at CMP 1.
1.6.14
Statistical
analysis will be undertaken and presented in the quarterly report to
investigate whether the capping operations at CMP 1 is causing any unacceptable
impacts in water quality of the area.
1.6.15
Water Column Profiling of CMP 2 – June 2015
1.6.16
Water Column Profiling was undertaken at a total of two sampling stations (Upstream
and Downstream stations) on 11 June 2015. The water quality monitoring results have been
assessed for compliance with the WQOs as discussed in Section 1.5.3. The
monitoring results were also compared with
the Action and Limit Levels set in Baseline Monitoring Report (see Table C3 of Annex C for details).
In-situ Measurements
1.6.17
Analyses of
results for June 2015 indicated that levels of Temperature, Salinity, DO and pH
complied with the WQOs at both Downstream and
Upstream stations (Table C5 of Annex C). DO and Turbidity at all
stations complied with the Action and Limit Levels (Tables C3 and C5 of Annex C).
Laboratory Measurements for SS
1.6.18
Analyses of
results for June 2015 indicated that the Suspended
Solid (SS) levels at both Upstream and Downstream stations complied with the
WQO. Both Upstream and Downstream
stations also complied with the Action and Limit Levels (Tables C3 and C5 of Annex C).
1.6.19
Overall, the
monitoring results indicated that the mud disposal operation at CMP 2 did not
appear to cause any deterioration in water quality during this reporting
period.
1.7
Activities Scheduled for the Next Month
1.7.1
The following
monitoring activities will be conducted in the next monthly period of July 2015
for SB CMPs:
·
Pit Specific Sediment Chemistry of CMP 2;
·
Demersal Trawling for CMP 2;
·
Water Column Profiling of CMP 2; and
·
Routine Water Quality Monitoring of CMP 2.
1.7.2
No monitoring activity is scheduled
to be conducted in the next monthly period of July 2015 for ESC CMPs.
1.7.3
The sampling
schedule is presented in Annex A.
1.8.1
A summary of the Study
programme is presented in Annex D.