Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) -
Investigation
32nd MONTHLY PROGRESS REPORT FOR April 2015
1.1.1
Since early 1990s, contaminated sediment ([1])
arising
from various construction works (e.g. dredging and reclamation projects) in Hong Kong has been disposed of at a series of seabed pits
at East of Sha Chau (ESC). In late
2008, a review indicated that the existing and planned facilities at ESC would
not be able to meet the disposal demand after 2012. In order to meet this demand, the Hong
Kong Special Administrative Region Government (HKSARG) decided to implement a
new contained aquatic disposal (CAD) ([2])
facility at
the South of The Brothers (SB CMPs) which had been under consideration for a
number of years.
1.1.2
The environmental acceptability of the construction and
operation of the Project had been confirmed by findings of the associated
Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) in September 2005 (EIA Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA recommendation, prior to
commencement of construction works for the SB CMPs, the Civil Engineering and
Development Department (CEDD) undertook a detailed review and update of the EIA
findings for the SB site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had
been predicted to be environmentally acceptable.
1.1.4
Environmental
Permits (EPs)
(EP-312/2008/A and EP-427/2011A) were issued by the Environmental
Protection Department (EPD) to the CEDD, the Permit Holder, on 28 November 2008
for ESC CMP V and on 23 December 2011 for SB CMPs, respectively. Under the requirements of the EPs, an Environmental Monitoring and
Audit (EM&A) programme as set out in the EM&A Manuals ()
() is required to be
implemented for the CMPs.
1.1.5
The present EM&A programme under Agreement No. CE 23/2012 (EP) covers the dredging,
disposal and capping operations of the SB CMPs as well as ESC CMPs. Detailed works schedule for both CMPs is
shown in Figure 1.1. In April 2015, the following works were
being undertaken at the CMPs:
¡P Capping operations at ESC CMPs;
¡P Capping operations at SB CMP 1; and
¡P Disposal of
contaminated mud at SB CMP 2.
Figure 1.1 Works
Schedule for ESC CMPs and SB CMPs
1.2
Reporting Period
1.2.1
This 32nd
Monthly Progress Report covers the EM&A activities for the reporting month of
April 2015.
1.3
Details of Sampling and
Laboratory Testing Activities
1.3.1
No monitoring activities have
been undertaken for ESC CMPs in April 2015.
1.3.2
The following monitoring
activities have been undertaken for SB CMPs in April 2015:
¡P Routine
Water Quality Monitoring of CMP 2
was undertaken on 14 April 2015;
¡P Pit
Specific Sediment Chemistry of CMP 2 was undertaken on 15 April
2015; and
¡P Water
Column Profiling of CMP 2 was undertaken on 17 April 2015.
1.4
Details of Outstanding
Sampling and/or Analysis
1.4.1
No outstanding sampling
remained for April 2015. The
following laboratory analyses were still in progress during the preparation of
this monthly report and hence are not presented in this monthly report:
¡P Laboratory
analyses of Routine Water Quality Monitoring of CMP 2 in
April 2015; and
¡P Laboratory
analyses of sediment samples collected for Pit
Specific Sediment Chemistry of CMP 2 in April 2015.
1.4.2
A summary of field activities conducted are presented in Annex A.
1.5
Brief Discussion of the
Monitoring Results for SB CMPs
1.5.1
Brief discussion
of the monitoring results of the following activities for SB CMPs is presented
in this 32nd Monthly Progress Report:
¡P
In-situ measurements of Routine Water
Quality Monitoring of CMP 2 undertaken on 14 April 2015; and
¡P
Water Column Profiling of CMP 2 undertaken on 17 April 2015.
1.5.2
Routine Water
Quality Monitoring of
SB CMP 2 ¡V April 2015
1.5.3
The monitoring results
for the Routine Water Quality Monitoring
conducted in April
2015 in
the wet season have been assessed for compliance with the Water Quality
Objectives (WQOs) set by EPD. This
consists of a review of the EPD routine water quality monitoring data for the
wet season period (April to October) of 2004 - 2013 from stations in the Northwestern
Water Control Zone, where the CMPs are located. For Salinity, the averaged value
obtained from the Reference stations was used for the basis as the WQO. Levels
of Dissolved Oxygen (DO) and Turbidity were also assessed for compliance with
the Action and Limit Levels (see Table C1
of Annex C for
details). The monitoring results
are shown in Figures 1-5 of Annex
B and Table C2 of Annex C. A total
of fourteen (14) monitoring stations were sampled in April 2015
as shown in Figure 1.2.
In-situ
Measurements
1.5.4
Analyses of
results for April 2015 indicated that the levels of pH, DO and Salinity
complied with the WQOs at all stations (Impact, Intermediate, Reference and
Water Sensitive Receiver stations) in April 2015 (Figures 1-5 of Annex B).
1.5.5
The levels of DO and Turbidity
complied with the Action and Limit Levels at all stations (Figures 3 and 5 of Annex
B;
Table
C1 of Annex C).
1.5.6
Overall, in-situ
measurement results of the Routine Water Quality Monitoring indicated
that the disposal operation at CMP 2 did not appear to cause any unacceptable impacts
in water quality in April 2015.
1.5.7
Water Column
Profiling of CMP 2 ¡V April
2015
1.5.8
Water Column Profiling was
undertaken at a total of two sampling stations (Upstream and Downstream
stations) on 17 April 2015. The
water quality monitoring results have been assessed for compliance with the
WQOs as discussed in Section 1.5.3. The
monitoring results were also compared with the Action and
Limit Levels
set in Baseline Monitoring Report (see Table C1
of Annex C for
details).
In-situ Measurements
1.5.9
Analyses of results for April 2015
indicated that levels of Salinity, DO and pH complied with the WQOs at both
Downstream and Upstream stations (Table C3 of Annex C). DO and Turbidity at all stations
complied with the Action and Limit Levels (Table C1 and
C3 of
Annex C).
Laboratory Measurements for
SS
1.5.10
Analyses of results for April 2015
indicated that the Suspended Solid (SS) levels at Upstream station exceeded the
WQO while Downstream station complied with the WQO. It is considered that the exceedance of
SS at Upstream station was possibly caused by natural background variation of
water quality in the area. However,
both Upstream and Downstream stations complied with the Action and Limit Levels (Tables C1 and C3 of Annex C).
1.5.11
Overall, the monitoring results
indicated that the mud disposal operation at CMP 2 did not appear to cause any
deterioration in water quality during this reporting period.
1.6
Activities Scheduled for the
Next Month
1.6.1
The following monitoring activities
will be conducted in the next monthly period of May 2015 for SB CMPs:
¡P Pit Specific
Sediment Chemistry of CMP 2;
¡P Water
Column Profiling of CMP 2; and
¡P Routine
Water Quality Monitoring of CMP 2.
1.6.2
No monitoring activity is scheduled
to be conducted in the next monthly period of May 2015 for ESC CMPs.
1.6.3
The sampling schedule is presented
in Annex A.
1.7.1
A summary of the Study programme is
presented in Annex D.