Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
31st MONTHLY PROGRESS REPORT FOR March
2015
1.1.1
Since early 1990s, contaminated sediment ([1]) arising from various
construction works (e.g. dredging and reclamation projects) in Hong Kong has been disposed of at a series of seabed pits
at East of Sha Chau
(ESC). In late 2008, a review indicated
that the existing and planned facilities at ESC would not be able to meet the
disposal demand after 2012. In order to
meet this demand, the Hong Kong Special Administrative Region Government
(HKSARG) decided to implement a new contained aquatic disposal (CAD) ([2]) facility at the South of The Brothers
(SB CMPs) which had been under consideration for a
number of years.
1.1.2
The environmental acceptability of the construction and
operation of the Project had been confirmed by findings of the associated
Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) in September 2005 (EIA Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA recommendation, prior to
commencement of construction works for the SB CMPs,
the Civil Engineering and Development Department (CEDD) undertook a detailed
review and update of the EIA findings for the SB site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had been
predicted to be environmentally acceptable.
1.1.4
Environmental
Permits (EPs)
(EP-312/2008/A and EP-427/2011A) were issued by the Environmental
Protection Department (EPD) to the CEDD, the Permit Holder, on 28 November 2008
for ESC CMP V and on 23 December 2011 for SB CMPs,
respectively. Under the requirements of
the EPs, an Environmental
Monitoring and Audit (EM&A) programme as set out in the EM&A Manuals ()
() is required to be
implemented for the CMPs.
1.1.5
The present EM&A programme under Agreement No. CE 23/2012 (EP) covers the dredging,
disposal and capping operations of the SB CMPs as well as ESC CMPs. Detailed works schedule for both CMPs is shown in Figure 1.1. In March 2015, the following works
were being undertaken at the CMPs:
· Capping operations at ESC CMPs;
· Capping operations at SB CMP 1; and
· Disposal of contaminated mud at SB CMP 2.
Figure 1.1 Works
Schedule for ESC CMPs and SB CMPs
1.2
Reporting Period
1.2.1
This 31st
Monthly Progress Report covers the EM&A activities for
the reporting month of March 2015.
1.3
Details of Sampling and
Laboratory Testing Activities
1.3.1
No monitoring activities have
been undertaken for ESC CMPs in March 2015.
1.3.2
The following monitoring
activities have been undertaken for SB CMPs in March
2015:
·
Pit Specific Sediment Chemistry of CMP 2 was undertaken on 4 March 2015;
and
·
Water Column Profiling of CMP 2 was undertaken on 5 March 2015.
1.4
Details of Outstanding
Sampling and/or Analysis
1.4.1
No outstanding sampling
and laboratory analysis remained for March 2015.
1.4.2
A summary of field activities
conducted are presented in Annex A.
1.5
Brief Discussion of the
Monitoring Results for SB CMPs
1.5.1
Brief
discussion of the monitoring results of the following activities for SB CMPs is presented in this 31st Monthly
Progress Report:
· Laboratory
analyses of sediment samples collected for Cumulative Impact Sediment
Chemistry of SB CMPs in February 2015;
· Pit
Specific Sediment Chemistry of CMP 2 undertaken on 4 March 2015; and
·
Water Column Profiling of CMP 2 undertaken on 5 March 2015.
1.5.2
Cumulative Impact
Sediment Chemistry of SB CMPs – February 2015
1.5.3
Monitoring locations for Cumulative
Impact Sediment Chemistry for SB CMPs
are shown in Figure 1.2. A total of eleven (11) monitoring stations
were sampled in February 2015.
1.5.4
Analyses of results for the Cumulative Impact
Sediment Chemistry Monitoring indicated that the concentrations
of most inorganic contaminants, except Arsenic, were below the
Lower Chemical Exceedance Level
(LCEL) in February 2015 (Figures 1 and 2 of Annex B). Concentration of Arsenic
exceeded the LCEL at Capped Pit station SB-RCA and SB-RCB and Mid Field station
SB-RMA.
1.5.5
Whilst the average concentration
of Arsenic in the Earth’s crust is generally ~2mg/kg, significantly higher
Arsenic concentrations (median = 14 mg/kg) have been recorded in Hong Kong’s onshore sediments ([7]). It is presumed that
the natural concentrations of Arsenic are similar in onshore and offshore
sediments ([8]),
and relatively high Arsenic levels may thus occur throughout Hong
Kong. Therefore, the LCEL exceedances of Arsenic are unlikely to be caused by the
disposal operations at CMP 2 but rather as a result of naturally occurring
deposits.
1.5.6
For organic contaminants, concentration of Total Organic
Carbon (TOC) at Tai Ho Bay Station 2 (THB2) was recorded to be higher than
other stations (Figure 3 of Annex B). Concentrations of Tributyltin
(TBTs) were recorded to be higher at Near-field
station SB-RNB and Ma Wan station (Figure 4 of Annex B).
Total Dichloro-Diphenyl-Trichloroethane
(DDT), 4,4’-Dichloro-Diphenyl-Dichloroethylene
(4,4’-DDE),
Total Polychlorinated Biphenyls (PCBs) as well as Low and High Molecular
Weight Polycyclic Aromatic Hydrocarbons (MW PAHs)
were recorded below the limit of reporting at all stations.
1.5.7
Overall, there is no evidence indicating any
unacceptable environmental impacts to sediment quality as a result of the
contaminated mud disposal operations at CMP 2 in February 2015.
1.5.8
Pit Specific
Sediment Chemistry of CMP 2 – March 2015
1.5.9
Monitoring locations for Pit Specific
Sediment Chemistry for CMP 2 are shown in Figure 1.3. A total of six (6) monitoring stations were
sampled in March 2015.
1.5.10
The
concentrations of all inorganic contaminants were
lower than the LCEL in March 2015 (Figures 5-6 of
Annex B).
1.5.11
For organic contaminants, the concentrations of TOC
were similar amongst stations in March 2015 (Figure 7 of Annex B). TBTs concentrations
were observed to be slightly higher at Pit Edge station SB-NEBB in March 2015 (Figures 8 of Annex B). Total DDT, 4,4’-DDE, Total PCBs, Low and High MW PAHs
were below the limit of reporting at all stations in March 2015.
1.5.12
Overall, there is no evidence indicating any
unacceptable environmental impacts to sediment quality as a result of the
contaminated mud disposal operations at CMP 2 in March 2015. Statistical analysis will be undertaken in
the quarterly report to investigate whether there are any unacceptable impacts
in the area caused by the contaminated mud disposal.
1.5.13
Water Column
Profiling of CMP 2 – March
2015
1.5.14
Water Column Profiling was
undertaken at a total of two sampling stations (Upstream and Downstream
stations) on 5 March 2015. The
water quality monitoring results have been assessed for compliance with the
Water Quality Objectives (WQOs) through
a review of the Environmental Protection Department (EPD) routine water quality
monitoring data for the dry season period (November to March)
of 2004
– 2013 from stations in the North Western Water Control Zone (WCZ), where SB
CMP 2 is located. For Salinity, the
average value obtained from the Reference stations was used for the basis as
the WQO. The
monitoring results were also compared with the Action and
Limit Levels
set in Baseline Monitoring Report (see Table C1 of Annex C for details).
In-situ Measurements
1.5.15
Analyses of results for March 2015
indicated that levels of Salinity, Dissolved Oxygen (DO) and pH complied with
the WQOs at both Downstream and Upstream stations (Table C2 of Annex C). DO and Turbidity at all stations complied
with the Action and Limit Levels (Table C1 and C2 of
Annex C).
Laboratory Measurements for SS
1.5.16
Analyses of results for February
2015 indicated that the Suspended
Solid (SS) levels at both Upstream and Downstream stations complied with the
WQO and the Action and Limit Levels (Tables C1 and C2 of Annex C).
1.5.17
Overall, the monitoring results
indicated that the mud disposal operation at CMP 2 did not appear to cause any
deterioration in water quality during this reporting period.
1.6
Activities Scheduled for the
Next Month
1.6.1
The following monitoring activities
will be conducted in the next monthly period of April 2015 for SB CMPs:
·
Pit Specific Sediment Chemistry of CMP 2;
·
Water Column Profiling of CMP 2;
and
·
Routine Water Quality Monitoring of CMP 2.
1.6.2
No monitoring activity is scheduled to be conducted in
the next monthly period of April 2015 for ESC CMPs.
1.6.3
The sampling schedule is presented
in Annex A.
1.7.1
A summary of the Study programme is
presented in Annex D.