Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers and at East
Sha Chau (2012-2017) - Investigation
30th MONTHLY PROGRESS REPORT FOR February
2015
1.1.1
Since early 1990s, contaminated sediment ([1])
arising
from various construction works (e.g. dredging and reclamation projects) in Hong Kong has been disposed of at a series of seabed pits
at East of Sha Chau (ESC). In late 2008,
a review indicated that the existing and planned facilities at ESC would not be
able to meet the disposal demand after 2012.
In order to meet this demand, the Hong Kong Special Administrative
Region Government (HKSARG) decided to implement a new contained aquatic
disposal (CAD) ([2])
facility at
the South of The Brothers (SB CMPs) which had been under consideration for a
number of years.
1.1.2
The environmental acceptability of the construction and operation
of the Project had been confirmed by findings of the associated Environmental
Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]). The Director of
Environmental Protection (DEP) approved this EIA report under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) in September 2005 (EIA Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA recommendation, prior to
commencement of construction works for the SB CMPs, the Civil Engineering and
Development Department (CEDD) undertook a detailed review and update of the EIA
findings for the SB site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had
been predicted to be environmentally acceptable.
1.1.4
Environmental
Permits (EPs)
(EP-312/2008/A and EP-427/2011A) were issued by the Environmental
Protection Department (EPD) to the CEDD, the Permit Holder, on 28 November 2008
for ESC CMP V and on 23 December 2011 for SB CMPs, respectively. Under the requirements of the EPs, an Environmental Monitoring and
Audit (EM&A) programme as set out in the EM&A Manuals ()
() is required to be
implemented for the CMPs.
1.1.5
The present EM&A programme under Agreement No. CE 23/2012 (EP) covers the dredging,
disposal and capping operations of the SB CMPs as well as ESC CMPs. Detailed works
schedule for both CMPs is shown in Figure 1.1. In February 2015, the
following works were being undertaken at the CMPs:
· Capping operations at ESC CMPs;
· Capping operations at SB CMP 1; and
· Disposal of contaminated mud at SB CMP 2.
Figure 1.1 Works
Schedule for ESC CMPs and SB CMPs
1.2
Reporting Period
1.2.1
This 30th
Monthly Progress Report covers the EM&A activities for the reporting month of
February 2015.
1.3
Details of Sampling and
Laboratory Testing Activities
1.3.1
The following monitoring
activities have been undertaken for ESC CMPs in February 2015:
·
Water Quality Monitoring during Capping was
undertaken for ESC CMPs on 5 February 2015.
1.3.2
The following monitoring
activities have been undertaken for SB CMPs in February 2015:
·
Water Column Profiling for CMP 2 was undertaken on 2 February 2015;
·
Pit Specific Sediment Chemistry for CMP 2 was undertaken on 3 February 2015;
·
Water Quality Monitoring during Capping was undertaken for CMP 1 on 5 February 2015;
·
Cumulative Impact Sediment Chemistry for CMP 2 was undertaken from 9 to 11 February
2015;
· Sediment
Toxicity Tests for CMP 2 was undertaken from 9
to 11
February 2015;
·
Routine Water Quality Monitoring for CMP 2 was undertaken on 12 February 2015; and
·
Demersal Trawling for CMP 2 was undertaken on 25 and 26 February 2015.
1.4.1
No outstanding sampling
remained for
February 2015. The following
laboratory analyses were still in progress during the preparation of this
monthly report and hence are not presented in this monthly report:
· Laboratory
analyses of sediment samples collected for Cumulative Impact Sediment
Chemistry of CMP 2 in
February 2015;
· Laboratory
analyses of sediment samples collected for Sediment Toxicity Tests of CMP 2 in
February 2015; and
· Identification
of Catch from Demersal Trawling of CMP 2
and subsequent chemical analysis for the biota samples in January and February
2015.
1.4.2
A summary of field activities
conducted are presented in Annex A.
1.5.1
Brief
discussion of the monitoring results of the Water Quality Monitoring during Capping of
ESC CMPs conducted
on 5 February 2015 is presented below.
1.5.2
Water Quality
Monitoring during Capping – February 2015
1.5.3
The monitoring results obtained
during February 2015
sampling in the dry season have been assessed for compliance with the Water
Quality Objectives (WQOs) through a review of the Environmental Protection
Department (EPD) routine water quality monitoring data for the dry season
period (November to
March) of 2004 – 2013 from stations in the North
Western Water Control Zone (WCZ), where ESC CMPs are located. For Salinity, the average value obtained from
the Reference stations was used for the basis as the WQO. A total of sixteen (16) monitoring stations were
sampled in February 2015 as shown in Figure
1.2. Graphical
presentation of the monitoring results is provided in Annex B.
In-situ Measurements
1.5.4
Graphical presentation of the
monitoring results is shown in Figures 1-6 of Annex B. Levels of Dissolved Oxygen (DO), pH and
Salinity at all stations in February 2015 complied with the WQO.
Laboratory Measurements for Suspended Solids
(SS)
1.5.5
Concentrations of SS complied with
the WQO at all stations in February 2015 (Figure 7 of Annex B).
Further statistical analysis will be undertaken in the quarterly report to
investigate whether the capping operations at ESC CMPs is causing any
unacceptable deterioration in water quality of the area.
1.6.1
Brief discussion
of the monitoring results of the following activities for SB CMPs is presented
in this 30th Monthly Progress Report:
· Pit Specific Sediment
Chemistry of CMP 2 conducted
in January and February 2015;
·
Routine Water Quality Monitoring of CMP 2 conducted in January
(laboratory measurements) and February 2015;
·
Water Column Profiling of CMP 2 conducted on 2 February
2015; and
· Water
Quality Monitoring during Capping for
CMP 1 conducted on 5 February 2015.
1.6.2
Pit Specific Sediment
Chemistry of CMP 2 – January and February 2015
1.6.3
Monitoring locations for Pit Specific
Sediment Chemistry for CMP 2 are shown in Figure 1.3. A total of six (6) monitoring stations were sampled
in January and February 2015.
1.6.4
The
concentrations of most inorganic contaminants were
lower than the Lower Chemical Exceedance Level (LCEL) except for Copper and
Silver concentrations at Active Pit station SB-NPBB in January and February
2015 (Figures 8-9 and
13-14 of
Annex B). Copper and Silver concentrations at Active Pit station SB-NPBB
exceeded the LCEL and Upper
Chemical Exceedance Level (UCEL) in both January and February 2015. As higher Copper and Silver concentrations
were recorded within the Active Pit station only which were receiving
contaminated mud during the reporting month, there is no evidence indicating
any dispersal of contaminants from the active pit.
1.6.5
For organic contaminants, the concentrations of Total
Organic Carbon (TOC) were similar amongst stations in January 2015, while
concentrations at Active Pit Station SB-NPBB were observed to be higher in
February 2015 (Figure
10 and 15 of Annex B). Tributyltin
(TBTs) concentrations were observed to be higher at Active Pit station SB-NPBB
in both January and February 2015 (Figures 11 and 16 of Annex
B). Low Molecular Weight
Polycyclic Aromatic Hydrocarbons (Low MW PAHs) and High MW PAHs were generally
below the limit of reporting at most stations except for Active Pit Station
SB-NPBB in January 2015, Near Pit Station SB-NNBA and Pit Edge Station SB-NEBB
in February 2015. Low MW PAHs and High MW
PAHs were all below the LCEL at all stations in both months. Total Dichloro-Diphenyl-Trichloroethane
(DDT), 4,4’-Dichloro-Diphenyl-Dichloroethylene (4,4’-DDE) and Total
Polychlorinated Biphenyls (PCBs) were recorded below the limit of reporting at
all stations in both January 2015 and February 2015.
1.6.6
As higher TOC and TBTs concentrations were recorded
within the Active Pit station only which was receiving contaminated mud during
the reporting month, there is no evidence indicating any dispersal of contaminants
from the active pit.
1.6.7
Overall, there is no evidence indicating any
unacceptable environmental impacts to sediment quality as a result of the
contaminated mud disposal operations at CMP 2 in January and February
2015. Statistical analysis will be
undertaken in the quarterly report to investigate whether there are any
unacceptable impacts in the area caused by the contaminated mud disposal.
1.6.8
Routine Water
Quality Monitoring of
SB CMP 2 – January and February 2015
1.6.9
The monitoring results
for the Routine Water Quality Monitoring
conducted in January and February
2015 in the dry season have been assessed for compliance with the
Water Quality Objectives (WQOs) set by EPD as discussed in Section 1.5.3. Levels of DO, Turbidity and SS were also
assessed for compliance with the Action and Limit Levels (see
Table
C1 of Annex C for details). The monitoring results are shown in Figures 6-10
of Annex B and Table
C2 of Annex C. A total of fourteen (14)
monitoring stations were sampled in January and February 2015 as shown in Figure 1.4.
In-situ Measurements
1.6.10
Analyses of in-situ measurements
for January 2015 were presented in the 29th Monthly Progress Report.
1.6.11
Analyses of
results for February 2015 indicated that the levels of pH, DO and Salinity
complied with the WQOs at all stations (Impact, Intermediate, Reference and
Water Sensitive Receiver stations) in February 2015 (Figure 23-26 of Annex B).
1.6.12
The levels of DO and Turbidity
complied with the Action and Limit Levels at all stations (Figures 24 and
27
of Annex B;
Table
C1 and C2 of Annex C).
Laboratory Measurements
1.6.13
Laboratory analysis of January
and February 2015 results indicated that concentrations of Cadmium, Mercury and
Silver were below their limit of reporting at all stations. The concentrations of Chromium and Lead in
half of the samples were below their limit for reporting in both months. Arsenic, Copper, Nickel and Zinc were
detected in samples from most stations in January and February 2015 (Figures 18-19 and 28-29 of Annex B). Results of
laboratory analysis were shown in Table C3 of Annex C. Detailed statistical analysis
will be presented in the Quarterly Report to observe any spatial and temporal
trends.
1.6.14
For nutrients, concentrations of Total Inorganic
Nitrogen (TIN) at Tai Ho Bay 2 in January 2015 and most stations (except
Intermediate and Ma Wan Stations)
in February 2015 exceeded
the WQO (0.5mg/L) (Figure 20 and 30 of Annex B). It is important to note that due to the effect of the
Pearl River, the North Western WCZ has historically experienced higher levels
of TIN () . Therefore, the exceedances of TIN WQO at all
stations are unlikely to be caused by the disposal operation at CMP 2. Ammonia Nitrogen (NH3-N) concentration was
relatively similar amongst all stations (Figure 20 and 30 of Annex B). Level of 5-day
Biochemical Oxygen Demand (BOD5) appear to be higher at Tai Ho Bay
station 1 in January 2015 and at Shum Shui Kok and Tai Mo To stations in
February 2015 (Figure
21 and 31
of Annex B).
1.6.15
Concentrations of SS exceeded the WQO (13.7 mg/L for
dry season) at Tai Ho Bay station 1 in January 2015 while complied with the
WQO at all stations in February 2015.
SS at all stations complied with the Action and
Limit Levels in January and February
2015 (Figure
22
and 32 of Annex B; Table C2 of Annex C).
1.6.16
Overall, results of the Routine Water
Quality Monitoring indicated that the disposal operation at CMP 2 did not
appear to cause any unacceptable deterioration in water quality in January and
February 2015.
1.6.17
Water Column
Profiling of CMP 2 –
February 2015
1.6.18
Water Column Profiling was undertaken
at a total of two sampling stations (Upstream and Downstream stations) on 2
February 2015. The
water quality monitoring results have been assessed for compliance with the
WQOs as discussed in Section 1.5.3. The monitoring results were
also compared with the Action and Limit Levels set in
Baseline
Monitoring Report (see Table C1 of Annex C
for details).
In-situ Measurements
1.6.19
Analyses of results for February 2015
indicated that levels of Salinity, DO and pH complied with the WQOs at both
Downstream and Upstream stations (Table C4 of Annex C). DO and Turbidity at all stations complied
with the Action and Limit Levels (Table C1 and C4 of
Annex C).
Laboratory Measurements for SS
1.6.20
Analyses of results for February
2015 indicated that the SS levels
at both Upstream and Downstream stations complied with the WQO. SS levels at all stations also complied with the
Action and Limit Levels (Tables C1 and C3 of Annex C).
1.6.21
Overall, the monitoring results indicated
that the mud disposal operation at CMP 2 did not appear to cause any
deterioration in water quality during this reporting period.
1.6.22
Water Quality
Monitoring during Capping Operations of CMP 1– February 2015
1.6.23
The monitoring results obtained during
February 2015 sampling in the dry season have been assessed for compliance with
the WQOs (see Section 1.5.3 for details). A total of fourteen (14) monitoring stations
were sampled in February 2015 as shown in Figure 1.4. Graphical presentation of
the monitoring results is provided in Annex
B.
In-situ Measurements
1.6.24
Graphical presentation of the
monitoring results is shown in Figures 33-38 of Annex B.
Levels of DO, pH and Salinity at all stations in February 2015 complied
with the WQO.
Laboratory Measurements
1.6.25
Concentrations of SS complied
with the WQO at all stations in February 2015 (Figure 39 of
Annex B).
1.6.26
For nutrients, concentrations of
Ammonia (NH3) were
similar amongst all stations (Figures 40 of
Annex B). Concentrations of Biochemical Oxygen Demand
(BOD5)
were similar at Impact, Intermediate and Reference stations, but slightly
higher than other stations in February 2015.
Total Inorganic Nitrogen (TIN) at all stations exceeded the WQO of 0.5
mg/L in February 2015 (Figure 42 of Annex B). As discussed in Section 1.6.14, the North Western WCZ has
historically experienced higher levels of TIN and the
exceedances of TIN WQO at all stations are unlikely to be caused by the capping
operation at CMP 1.
1.6.27
Since higher BOD5 was recorded for both
Impact and Reference stations, the higher concentration is likely due to the
natural fluctuation of BOD5 in the environment. Therefore, there is no evidence indicating
any degradation for water quality due to the capping activities at CMP 1.
1.6.28
Statistical
analysis will be undertaken in the quarterly report to investigate whether the
capping operations at CMP 1 is causing any unacceptable impacts in
water quality of the area.
1.7
Activities Scheduled for the
Next Month
1.7.1
The following monitoring activities
will be conducted in the next monthly period of March 2015 for SB CMPs:
·
Pit Specific Sediment Chemistry of CMP 2;
and
·
Water Column Profiling of CMP 2.
1.7.2
No monitoring activities will be conducted in the next
monthly period of March 2015 for ESC CMPs.
1.7.3
The sampling schedule is presented
in Annex A.
1.8.1
A summary of the Study programme is
presented in Annex D