Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
26th MONTHLY PROGRESS REPORT FOR OCTOBER 2014
1.1.1
Since early 1990s, contaminated sediment ([1])
arising
from various construction works (e.g. dredging and reclamation projects) in Hong Kong has been disposed of at a series of seabed pits
at East of Sha Chau
(ESC). In late 2008, a review indicated
that the existing and planned facilities at ESC would not be able to meet the
disposal demand after 2012. In order to
meet this demand, the Hong Kong Special Administrative Region Government
(HKSARG) decided to implement a new contained aquatic disposal (CAD) ([2])
facility at
the South of The Brothers (SB CMPs) which had been
under consideration for a number of years.
1.1.2
The environmental acceptability of the construction and
operation of the Project had been confirmed by findings of the associated
Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]).
The Director of Environmental Protection (DEP) approved this EIA report
under the Environmental
Impact Assessment Ordinance (Cap. 499) (EIAO) in September 2005 (EIA Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA recommendation, prior to
commencement of construction works for the SB CMPs,
the Civil Engineering and Development Department (CEDD) undertook a detailed
review and update of the EIA findings for the SB site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had
been predicted to be environmentally acceptable.
1.1.4
Environmental
Permits (EPs)
(EP-312/2008/A and EP-427/2011A) were issued by the Environmental
Protection Department (EPD) to the CEDD, the Permit Holder, on 28 November 2008
for ESC CMP V and on 23 December 2011 for SB CMPs,
respectively. Under the requirements of
the EPs, an Environmental
Monitoring and Audit (EM&A) programme as set out in the EM&A Manuals ()
()
is required
to be implemented for the CMPs.
1.1.5
The present EM&A programme under Agreement No. CE 23/2012 (EP) covers the dredging,
disposal and capping operations of the SB CMPs as well as ESC CMPs. Detailed works schedule for both CMPs is shown in Figure 1.1. In October 2014, the following
works were being undertaken at the CMPs:
·
Capping
was being undertaken at ESC CMP IVc and CMP Va;
·
Disposal of
contaminated mud was taking place at SB CMP 1; and
·
Dredging operations
were taking place at SB CMP 2.
Figure 1.1 Works Schedule for ESC CMPs and
SB CMPs
1.2
Reporting Period
1.2.1
This 26th Monthly
Progress Report covers the EM&A activities for the
reporting month of October 2014.
1.3
Details of Sampling and
Laboratory Testing Activities
1.3.1
No monitoring activity was
scheduled to be undertaken for ESC CMPs in October 2014.
1.3.2
The following monitoring
activities have been undertaken for SB CMPs in October 2014:
·
Impact Water Quality Monitoring during Dredging
Operations was undertaken for CMP 2 three
times per week on 3, 5, 7, 9, 11, 13, 15, 18, 20, 22, 24, 27, 29
and 31 October 2014;
·
Water Column Profiling for CMP 1 was undertaken on 8 October 2014;
·
Routine Water Quality Monitoring for CMP 1 was undertaken on 14 October 2014; and
·
Pit Specific Sediment Chemistry for CMP 1 was undertaken on 16 October
2014.
1.4
Details of Outstanding
Sampling and/or Analysis
1.4.1
No outstanding sampling
remained for
October 2014. The following
laboratory analyses were still in progress during the preparation of this
monthly report and hence are not presented in this monthly report:
·
Laboratory analyses of water samples collected for Routine Water Quality
Monitoring of CMP 1 in October 2014.
·
Laboratory analyses of sediment samples collected for Pit Specific Sediment
Chemistry of CMP 1 in
October 2014.
1.4.2
A summary of field activities
conducted are presented in Annex
A.
1.5.1
Brief discussion
of the monitoring results of the following activities for SB CMPs is presented in this 26th Monthly Progress Report:
·
Cumulative Impact Sediment Chemistry of CMP 1
conducted in August 2014;
·
Pit Specific Sediment Chemistry of CMP 1
conducted in September 2014;
·
Sediment Chemistry after a Major Storm for CMP 1 conducted
in September 2014;
·
Impact Water Quality Monitoring during Dredging Operations of CMP 2 conducted
in October 2014; and
·
Water Column Profiling of CMP 1 conducted on 8 October
2014.
1.5.2
Cumulative Impact
Sediment Chemistry of CMP 1 – August 2014
1.5.3
Monitoring locations for Cumulative
Impact Sediment Chemistry for CMP 1
are shown in Figure 1.2. A total of eleven (11) monitoring stations
were sampled in August 2014.
1.5.4
Analyses of results for the Cumulative Impact
Sediment Chemistry Monitoring indicated that the concentrations
of most inorganic contaminants, except Arsenic, were below the
Lower Chemical Exceedance Level
(LCEL) in August 2014 (Figures 1 and 2 of Annex B).
Concentration of Arsenic exceeded the LCEL at Capped
Pit station SB-RCA.
1.5.5
Whilst the average concentration
of Arsenic in the Earth’s crust is generally ~2mg/kg, significantly higher
Arsenic concentrations (median = 14 mg/kg) have been recorded in Hong Kong’s onshore sediments ([7]). It is presumed that
the natural concentrations of Arsenic are similar in onshore and offshore
sediments ([8]),
and relatively high Arsenic levels may thus occur throughout Hong
Kong. Therefore, the LCEL exceedances of Arsenic are unlikely to be caused by the
disposal operations at CMP 1 but rather as a result of naturally occurring
deposits.
1.5.6
For organic contaminants, concentration of Total Organic
Carbon (TOC) at Tai Ho Bay Station 2 (THB2) was recorded to be higher than
other stations (Figure 3 of Annex B). Concentrations
of Tributyltin (TBTs) were
recorded to be higher at Near-field station SB-RNB and Mid-field station SB-RMB
(Figure 4 of Annex B). Total Dichloro-Diphenyl-Trichloroethane (DDT), 4,4’-Dichloro-Diphenyl-Dichloroethylene
(4,4’-DDE),
Total Polychlorinated Biphenyls (PCBs) as well as Low and High Molecular
Weight Polycyclic Aromatic Hydrocarbons (MW PAHs)
were recorded below the limit of reporting at all stations.
1.5.7
Overall, there is no evidence indicating any
unacceptable environmental impacts to sediment quality as a result of the
contaminated mud disposal operations at CMP 1 in August 2014.
1.5.8
Pit Specific
Sediment Chemistry of CMP 1 – September 2014
1.5.9
Monitoring locations for Pit Specific
Sediment Chemistry for CMP 1 are shown in Figure 1.3. A total of six (6) monitoring stations were
sampled in September
2014.
1.5.10
The
concentrations of all inorganic contaminants were
lower than the LCEL at all stations in September 2014 (Figures 5 and 6 of Annex B).
1.5.11
For organic contaminants, the concentrations of TOC
and TBTs were observed to be higher at Active Pit
station SB-NPAB (Figures
7 and 8 of Annex B). Low MW PAHs, High
MW PAHs, Total DDT, 4,4’-DDE and Total PCBs were
recorded below the limit of reporting at all stations in September 2014.
1.5.12
As higher TOC and TBTs concentrations
were recorded within the Active Pit station only which were
receiving contaminated mud during the reporting month, there is no evidence
indicating any dispersal of contaminants from the active pit.
1.5.13
Overall, there is no evidence indicating any
unacceptable environmental impacts to sediment quality as a result of the
contaminated mud disposal operations at CMP 1 in September 2014.
1.5.14
Sediment Chemistry
after a Major Storm of CMP 1 – September 2014
1.5.15
Sampling for Sediment Chemistry after a Major Storm
Event was conducted at eleven (11) monitoring stations (Figure 1.2) on 19
September 2014 after the visit of Typhoon Kalmaegi, which
led to the issue of Gale or Storm Wind Signal No.8 on 16 September 2014. The track of Doksuri
is shown in Figure 1.4.
Figure
1.4 Track of Typhoon Kalmaegi from 12 to 17
September 2014 (Source: Hong Kong Observatory)
1.5.16
Analyses of results for the Sediment Chemistry
after a Major Storm indicated that the concentrations of most inorganic
contaminants, except Arsenic, were below the LCEL
(Figures 9 and
10 of Annex B). Concentration of Arsenic
exceeded the LCEL at Capped Pit stations SB-RCA and SB-RCB. As discussed in Section 1.5.5,
the slight exceedances of the LCEL for Arsenic are
unlikely to be caused by the disposal operations at CMP 1 but rather as a
result of naturally occurring deposits.
1.5.17
Overall, there appeared to be no
evidence showing the failure of CMPs in retaining
disposed mud or causing contamination of sediments after the major storm event
in September 2014.
1.5.18
Impact Water
Quality Monitoring during Dredging Operations of CMP 2 – October 2014
1.5.19
Impact Water Quality Monitoring during Dredging
Operations of CMP 2 was conducted three times per week
from 1 to 31 October 2014 during the reporting period. On each survey day, monitoring was conducted during
both mid-ebb and mid-flood tides at two Reference (Upstream) stations and five
Impact (Downstream) stations of the dredging operations at CMP 2. Monitoring was also conducted at five
Sensitive Receiver Stations situated in Ma Wan, Shum Shui
Kok, Tai Mo To and Tai Ho Bay. A total of twelve (12) stations were
monitored and locations of the sampling stations are shown in Figure 1.5.
1.5.20
Monitoring results are presented in Table C1
of Annex C. Daily dredging volume in October 2014 is
reported in Annex D. Levels of Dissolved Oxygen (DO), Turbidity
and Suspended Solids (SS) generally complied with the Action and Limit Levels
(see Table
C2 of Annex C for
details) set in the Baseline Monitoring Report (),
except for the following occasion of exceedances discussed
in Table
1.1
below.
1.5.21
As presented in Table 1.1,
the results indicated that the dredging operations at CMP 2 did not appear
to cause any unacceptable deterioration in water quality during this reporting
period. Therefore, no further mitigation
measures, except for those recommended in the Environmental Permit (EP-427/2011/A),
are considered necessary for the dredging operations.
Table 1.1 Details
of Exceedances Recorded at CMP 2 between 1 and 31 October 2014
Date
|
Tide
|
Parameter
|
Station
|
Type
|
Remarks
|
7 October 2014
|
Mid-Flood
|
Turbidity
|
DS2
|
Action
|
These exceedances were not considered as indicating any
unacceptable impacts from the dredging operations to Water Sensitive
Receivers (WSRs) outside the works area due to the
following reason:
· Stations DS2, DS3,
WSR45C and WSR46 are located further away from the works area of CMP 2 when
compared to station DS1 at which the levels of Turbidity and SS did not exceed
the Action and Limit Levels during the same tidal period.
|
9 October 2014
|
Mid-Flood
|
SS
|
DS3
|
Action
|
9 October 2014
|
Mid-Flood
|
Turbidity
|
WSR45C
|
Limit
|
9 October 2014
|
Mid-Flood
|
Turbidity
|
WSR46
|
Action
|
11 October 2014
|
Mid-Flood
|
SS
|
DS2
|
Action
|
20 October 2014
|
Mid-Flood
|
SS
|
DS2
|
Action
|
20 October 2014
|
Mid-Flood
|
SS
|
DS3
|
Action
|
27 October 2014
|
Mid-Ebb
|
SS
|
DS2
|
Action
|
27 October 2014
|
Mid-Flood
|
SS
|
DS2
|
Action
|
29 October 2014
|
Mid-Flood
|
SS
|
DS2
|
Action
|
|
22 October 2014
|
Mid-Flood
|
Turbidity
|
DS1
|
Limit
|
These exceedances
were not considered as indicating any unacceptable impacts from the dredging
operations to WSRs outside the works area due to
the following reason:
· Action / Limit Level Exceedances of Turbidity and SS were recorded at Stations
DS1 and DS2 which are located in the vicinity of the works area during one tidal period
only, and exceedances were not recorded at stations
WSR45C and WSR46 which are the nearest WSRs. It is thus considered that the exceedances were not indicating any unacceptable impacts
from the dredging operations to the nearby WSRs.
|
22 October 2014
|
Mid-Flood
|
Turbidity
|
DS2
|
Limit
|
22 October 2014
|
Mid-Flood
|
SS
|
DS1
|
Action
|
22 October 2014
|
Mid-Flood
|
SS
|
DS2
|
Action
|
|
|
|
|
|
|
|
|
|
|
9 October 2014
|
Mid-Ebb
|
SS
|
DS1
|
Action
|
These exceedances
were not considered as indicating any unacceptable impacts from the dredging
operations to WSRs outside the works area due to
the following reason:
·
Station DS1 is
located close to the works area whilst stations DS4 and DS5 are located
further away from the works area of CMP 2 when compared to stations DS2-3 at
which the levels of Turbidity and SS did not exceed the Action and Limit
Levels during the same tidal period.
These exceedances were thus not considered
as indicating any unacceptable impacts from the dredging operations to WSR
outside the works area.
|
9 October 2014
|
Mid-Ebb
|
Turbidity
|
DS4
|
Action
|
9 October 2014
|
Mid-Ebb
|
Turbidity
|
DS5
|
Action
|
9 October 2014
|
Mid-Ebb
|
SS
|
DS4
|
Action
|
9 October 2014
|
Mid-Ebb
|
SS
|
DS5
|
Action
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.5.22
Water Column
Profiling of CMP 1 –
October 2014
1.5.23
Water Column Profiling was
undertaken at a total of two sampling stations (Upstream and Downstream
stations) on 8 October 2014. The
water quality monitoring results have been assessed for compliance with the
Water Quality Objectives (WQOs) through a review of
the Environmental Protection Department (EPD) routine water quality monitoring data
for the wet season period (April to October) of 2003-2012 from stations in the
North Western Water Control Zone (WCZ), where CMP is located. The monitoring results were
also compared with the Action and Limit Levels set in
Baseline
Monitoring Report (see Table C2 of Annex C for details).
In-situ Measurements
1.5.24
Analyses of results for October 2014
indicated that levels of Salinity, turbidity, DO and pH
complied with the WQOs at both Downstream and Upstream
stations (Table C3 of Annex C).
Laboratory
Measurements for SS
1.5.25
Analyses of results for September
2014 indicated
that the SS levels at Upstream station
complied with the WQO. The Downstream
station exceeded the WQO. SS levels at
all stations complied with the Action
and Limit Levels (Table C3 of Annex C).
1.5.26
Overall, the monitoring results
indicated that the mud disposal operation at CMP 1 did not appear to cause any
deterioration in water quality during this reporting period.
1.6
Activities Scheduled for the
Next Month
1.6.1
The following monitoring activities
will be conducted in the next monthly period of November 2014 for SB CMPs:
· Pit Specific
Sediment Chemistry of CMP 1;
· Impact
Monitoring during Dredging Operations of CMP 2;
· Routine
Water Quality Monitoring of CMP 1; and
· Water
Column Profiling of CMP 1.
1.6.2
No monitoring activity is scheduled to be undertaken
in the next monthly period of November 2014 for ESC CMPs.
1.6.3
The sampling schedule is presented
in Annex A.
1.7.1
A summary of the Study programme is
presented in Annex E.