Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at
25th MONTHLY PROGRESS REPORT FOR september 2014
·
Capping
was being undertaken at ESC CMP IVc and CMP Va;
·
Disposal of
contaminated mud was taking place at SB CMP 1; and
·
Dredging
operations were taking place at SB CMP 2.
Figure 1.1 Works Schedule for ESC CMPs and SB CMPs
·
Impact
Water Quality Monitoring during Dredging Operations was undertaken for CMP 2
three times per week on 1, 3, 5, 8, 11, 13, 15, 18, 20, 22, 24, 26 and 29 September
2014;
·
Pit
Specific Sediment Chemistry for CMP 1 was undertaken on 18 September 2014; and
·
Water
Column Profiling for CMP 1 was undertaken on 12 September 2014.
·
Laboratory
analyses of sediment samples collected for Pit Specific Sediment Chemistry of
CMP1 in September 2014.
Table 1.1 Details
of Exceedances Recorded at CMP 2 between 1 and 30 September 2014
Date |
Tide |
Parameter |
Station |
Type |
Remarks |
1 September
2014 |
Mid-Flood |
Turbidity |
DS2 |
Action |
These exceedances were not
considered as indicating any unacceptable impacts from the dredging
operations to WSRs outside the works area due to
the following reason: · Stations DS2, DS4, DS5,
WSR45C and WSR46 are located further away from the works area of CMP 2 when
compared to station DS1 at which the levels of bottom DO, surface and mid-depth DO, Turbidity and SS did not exceed the Action and Limit
Levels during the same tidal period. |
5 September
2014 |
Mid-Ebb |
Surf and
Mid DO |
DS4 |
Action |
|
5 September
2014 |
Mid-Ebb |
Surf and
Mid DO |
DS5 |
Action |
|
5 September
2014 |
Mid-Ebb |
Surf and
Mid DO |
WSR45C |
Action |
|
5 September
2014 |
Mid-Flood |
Bottom DO |
WSR45C |
Action |
|
5 September
2014 |
Mid-Flood |
Surf and
Mid DO |
WSR45C |
Limit |
|
11
September 2014 |
Mid-Ebb |
Surf and
Mid DO |
DS4 |
Action |
|
11 September
2014 |
Mid-Ebb |
Surf and
Mid DO |
DS5 |
Action |
|
11
September 2014 |
Mid-Ebb |
Surf and
Mid DO |
WSR45C |
Action |
|
11
September 2014 |
Mid-Ebb |
Turbidity |
DS4 |
Action |
|
11
September 2014 |
Mid-Ebb |
Turbidity |
DS5 |
Action |
|
11 September 2014 |
Mid Flood |
SS |
WSR46 |
Action |
|
13 September
2014 |
Mid-Flood |
Surf and
Mid DO |
WSR45C |
Action |
|
13
September 2014 |
Mid-Flood |
Surf and
Mid DO |
WSR46 |
Action |
|
22
September 2014 |
Mid-Flood |
SS |
DS4 |
Action |
|
22 September 2014 |
Mid-Flood |
SS |
WSR45C |
Action |
|
3 September
2014 |
Mid-Flood |
Turbidity |
DS1 |
Action |
These exceedances were not considered as
indicating any unacceptable impacts from the dredging operations to WSRs outside the works area due to the following reason: · Action Level Exceedance of Turbidity and SS was recorded at Station
DS1 which is located at the boundary of the works area during one tidal period
only, and given that the dredging rate was well within the limit as specified
under the EP, it is considered that the exceedance
was not indicating any unacceptable impacts from the dredging operations to
the nearby WSRs. |
3 September
2014 |
Mid-Flood |
SS |
DS1 |
Action |
|
22
September 2014 |
Mid-Ebb |
SS |
DS1 |
Action |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
24
September 2014 |
Mid-Flood |
SS |
DS1 |
Action |
These exceedances were not considered as
indicating any unacceptable impacts from the dredging operations to WSRs outside the works area due to the following reason: ·
Reference station US2 has high SS level similar to the
levels recorded at stations DS1 and DS3 during the same tidal period. The
Action Level Exceedances of SS at stations DS1 and
DS3 are considered to be isolated sporadic event which may be caused by
natural background variation in water quality characteristics of the
monitoring area. |
24
September 2014 |
Mid-Flood |
SS |
DS3 |
Action |
|
|
|
|
|
|
In-situ Measurements
·
Pit Specific Sediment Chemistry of CMP 1;
·
Impact Monitoring during Dredging Operations of CMP
2;
·
Routine Water Quality Monitoring of CMP 1; and
·
Water Column Profiling of CMP 1.
([1])
According to the Management
Framework of Dredged/ Excavated Sediment of ETWB TC(W) No. 34/2002,
contaminated sediment in general shall mean those sediment requiring Type 2 –
Confined Marine Disposal as determined according to this TC(W).
([2]) CAD options may involve use of excavated
borrow pits, or may involve purpose-built excavated
pits. CAD sites are those which involve
filling a seabed pit with contaminated mud and capping it with uncontaminated
material such that the original seabed level is restored and the contaminated
material is isolated from the surrounding marine environment.7
([3])
Detailed Site Selection Study for a
Proposed Contaminated Mud Disposal Facility within the Airport East/ East of
Sha Chau Area (Agreement No. CE 12/2002(EP))
([4])
Under the CEDD study Contaminated Sediment Disposal Facility to
the South of The Brothers (Agreement No. FM 2/2009)
([5]) ERM (2012) Environmental Monitoring and Audit
(EM&A) Manual. Final First Review. Environmental Monitoring and Audit for
Contaminated Mud Pits to the South of the Brothers and at