Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at
24th MONTHLY PROGRESS REPORT FOR August
2014
·
Capping
was being undertaken at ESC CMP IVc and CMP Va; ·
Disposal of
contaminated mud was taking place at SB CMP 1; and ·
Dredging
operations were taking place at SB CMP 2. |
Figure 1.1 Works Schedule for ESC CMPs and SB CMPs
·
Water Quality Monitoring during Capping was
undertaken for ESC CMPs on 9 August 2014; and ·
Benthic Recolonisation
Studies was
undertaken for ESC CMPs on 14 August 2014. |
·
Impact Water Quality Monitoring during Dredging
Operations was undertaken for CMP 2 three
times per week on 1, 4, 6, 8, 11, 13, 15, 18, 20, 22, 26, 28 and 30 August
2014; ·
Pit Specific Sediment Chemistry for CMP 1 was undertaken on 5 August 2014; ·
Routine Water Quality Monitoring for CMP 1 was undertaken on 7 August 2014; ·
Sediment Toxicity Tests for CMP 1 was undertaken on 12 and 13 August
2014; ·
Water Column Profiling for CMP 1 was undertaken on 14 August 2014; ·
Cumulative Impact Sediment Chemistry for CMP 1 was undertaken from 19 to 21 August
2014; and ·
Demersal Trawling
for CMP 1 was undertaken on 20 and 21 August 2014. |
·
Laboratory analyses of sediment samples collected
for Benthic Recolonisation Studies of ESC CMPs in August 2014;
·
Laboratory analyses of sediment samples collected
for Cumulative Impact Sediment Chemistry of CMP 1 in August 2014;
·
Laboratory analyses of sediment samples collected
for Sediment Toxicity Tests of CMP 1
in August 2014; and
·
Identification
of Catch from Demersal Trawling of CMP 1 and subsequent
chemical analysis for the biota samples in July and August 2014.
|
·
Pit Specific Sediment Chemistry of CMP 1 conducted in July and
August 2014;
·
Impact Water Quality Monitoring during Dredging Operations of CMP 2 conducted
in August 2014;
·
Routine Water Quality Monitoring of CMP 1 conducted on 7 August
2014; and
·
Water Column Profiling of
CMP 1 conducted on 14 August 2014.
|
Table 1.1 Details
of Exceedances Recorded at CMP 2 between 1 and 30 August 2014
Date |
Tide |
Parameter |
Station |
Type |
Remarks |
6 August 2014 |
Mid-Flood |
Bottom DO |
WSR45C |
Action |
These exceedances were not considered as indicating any
unacceptable impacts from the dredging operations to WSRs
outside the works area due to the following reasons: · Stations
DS5, WSR45C and WSR46 are located further away from the works area of CMP 2
when compared to station DS1 at which the levels of DOB did not exceed the
Action and Limit Levels during the same tidal period. · The lower
DO levels recorded at stations DS5, WSR45C and WSR46 during this reporting
period were possibly caused by the presence of thermocline
within the water column, as indicated by the relatively larger drop in water
temperature from the surface to the bottom water depths (see Annex E for the raw data). The thermocline
would prevent mixing of surface layer water of higher DO with water
underneath (ie at mid and bottom depths) and thus
reducing DO levels at mid and bottom depths. |
8 August 2014 |
Mid-Flood |
Bottom DO |
WSR45C |
Action |
|
18 August 2014 |
Mid-Ebb |
Bottom DO |
WSR45C |
Action |
|
18 August 2014 |
Mid-Flood |
Bottom DO |
WSR45C |
Action |
|
20 August 2014 |
Mid-Ebb |
Bottom DO |
DS5 |
Action |
|
20 August 2014 |
Mid-Ebb |
Bottom DO |
WSR45C |
Action |
|
20 August 2014 |
Mid-Ebb |
Bottom DO |
WSR46 |
Action |
|
20 August 2014 |
Mid-Flood |
Bottom DO |
WSR45C |
Action |
|
22 August 2014 |
Mid-Ebb |
Bottom DO |
DS5 |
Action |
|
22 August 2014 |
Mid-Ebb |
Bottom DO |
WSR45C |
Action |
|
22 August 2014 |
Mid-Flood |
Bottom DO |
WSR45C |
Action |
|
11 August 2014 |
Mid-Ebb |
Surf and Mid DO |
DS4 |
Action |
These exceedances were not considered as indicating any
unacceptable impacts from the dredging operations to WSRs
outside the works area due to the following reason: · Stations
DS3, DS4, DS5, WSR45C and WSR46 are located further away from the works area
of CMP 2 when compared to station DS1 at which the levels of surface and
mid-depth DO, Turbidity and SS did not exceed the Action and Limit Levels
during the same tidal period. |
11 August 2014 |
Mid-Ebb |
Surf and Mid DO |
DS5 |
Action |
|
11 August 2014 |
Mid-Ebb |
Surf and Mid DO |
WSR45C |
Action |
|
11 August 2014 |
Mid-Flood |
Turbidity |
DS3 |
Action |
|
11 August 2014 |
Mid-Flood |
Turbidity |
DS5 |
Action |
|
13 August 2014 |
Mid-Ebb |
Surf and Mid DO |
DS3 |
Action |
|
13 August 2014 |
Mid-Ebb |
Surf and Mid DO |
DS4 |
Action |
|
13 August 2014 |
Mid-Ebb |
Surf and Mid DO |
DS5 |
Action |
|
13 August 2014 |
Mid-Ebb |
Surf and Mid DO |
WSR45C |
Action |
|
13 August 2014 |
Mid-Ebb |
Surf and Mid DO |
WSR46 |
Action |
|
13 August 2014 |
Mid-Flood |
SS |
WSR45C |
Action |
|
20 August 2014 |
Mid-Flood |
Surf and Mid DO |
WSR45C |
Action |
|
28 August 2014 |
Mid-Ebb |
SS |
DS5 |
Action |
In-situ
Measurements
Laboratory
Measurements
In-situ
Measurements
Laboratory
Measurements for SS
·
Impact Water Quality Monitoring during Dredging
Operations of CMP 2; ·
Pit Specific Sediment Chemistry of CMP 1;
and ·
Water Column
Profiling of CMP 1. |
([1])
According to the Management
Framework of Dredged/ Excavated Sediment of ETWB TC(W) No. 34/2002,
contaminated sediment in general shall mean those sediment requiring Type 2 –
Confined Marine Disposal as determined according to this TC(W).
([2]) CAD options may involve use of excavated
borrow pits, or may involve purpose-built excavated
pits. CAD sites are those which involve
filling a seabed pit with contaminated mud and capping it with uncontaminated
material such that the original seabed level is restored and the contaminated
material is isolated from the surrounding marine environment.7
([3])
Detailed Site Selection Study for a
Proposed Contaminated Mud Disposal Facility within the Airport East/ East of
Sha Chau Area (Agreement No. CE 12/2002(EP))
([4])
Under the CEDD study Contaminated Sediment Disposal Facility to
the South of The Brothers (Agreement No. FM 2/2009)
([5]) ERM (2012) Environmental Monitoring and Audit
(EM&A) Manual. Final First Review. Environmental Monitoring and Audit for
Contaminated Mud Pits to the South of the Brothers and at
([6])
ERM (2010) Environmental Monitoring and Audit
(EM&A) Manual. Final Second Review. Environmental Monitoring and Audit for
Contaminated Mud Pit at Sha Chau (2009-2013) – Investigation. Agreement No. CE 4/2009(EP). Submitted to EPD in
November 2010.