Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
19TH MONTHLY PROGRESS REPORT FOR March
2014
1.1.1
Since early 1990s, contaminated
sediment ([1]) arising from
various construction works (e.g. dredging and reclamation projects) in Hong Kong has been disposed of at a series of seabed pits
at East of Sha Chau
(ESC). In late 2008, a review indicated
that the existing and planned facilities at ESC would not be able to meet the
disposal demand after 2012. In order to
meet this demand, the Hong Kong Special Administrative Region Government (HKSARG)
decided to implement a new contained aquatic disposal (CAD) ([2])
facility at the South of The Brothers (SB CMPs)
which had been under consideration for a number of years.
1.1.2
The environmental acceptability of the
construction and operation of the Project had been confirmed by findings of the
associated Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO) in September
2005 (EIA
Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA
recommendation, prior to commencement of construction works for the SB CMPs, the Civil Engineering and Development Department
(CEDD) undertook a detailed review and update of the EIA findings for the SB
site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had
been predicted to be environmentally acceptable.
1.1.4
Environmental Permits (EPs) (EP-312/2008/A and EP-427/2011A) were
issued by the Environmental Protection Department (EPD) to the CEDD, the Permit
Holder, on 28 November 2008 for East of Sha Chau (ESC) CMP V and on 23 December 2011 for SB CMPs, respectively. Under the requirements of the EPs, an
Environmental Monitoring and Audit (EM&A) programme as set out in the
EM&A Manuals ()
() is
required to be implemented for the CMPs.
1.1.5
The present
EM&A programme undertaken under Agreement No. CE 23/2012 (EP)
covers the dredging, disposal and capping operations of the SB CMPs as well as CMPs at East of Sha Chau (ESC). In March 2014, the following works were being
undertaken at the CMPs:
·
Capping
was being undertaken at ESC CMP IVc and CMP Va;
·
Disposal of
contaminated mud was taking place at SB CMP 1; and
·
Dredging
operations were taking place at SB CMP 2.
1.2
Reporting Period
1.2.1
This 19th Monthly Progress
Report covers the EM&A activities for
the reporting month of March 2014.
1.3
Details of Sampling and Laboratory Testing
Activities
1.3.1
The following
monitoring activities have been undertaken for SB CMPs
in March 2014:
·
Impact Water Quality Monitoring during Dredging
Operations was undertaken for CMP 2 three
times per week on 1, 3, 5, 7, 11, 13, 15, 17, 19, 21, 24, 26, 28 and 31 March
2014;
·
Water Column Profiling for CMP 1 was undertaken on 8 March 2014; and
·
Pit Specific Sediment Chemistry was undertaken for CMP 1 on 12 March 2014.
1.4.1
No outstanding sampling remained for March 2014.
The following laboratory analyses were still in progress during the
preparation of this monthly report and hence were not presented in this monthly
report:
·
Laboratory analyses of sediment
samples collected for Pit Specific Sediment Chemistry of CMP 1 in January, February and March 2014; and
·
Laboratory analyses of sediment
samples collected for Cumulative Impact Sediment Chemistry of CMP 1 in February 2014.
1.4.2
A summary of
field activities conducted are presented in Annex A.
1.5.1
Brief discussion of the monitoring results of the
following activities is presented in this 19th
Monthly Progress Report:
·
Pit Specific Sediment Chemistry of CMP 1 conducted in December 2013.
·
Routine Water Quality Monitoring of CMP 1 undertaken from 5 to 28 February 2014;
·
Impact Water Quality Monitoring during Dredging
Operations of CMP 2 conducted from 27 February to 31 March 2014; and
·
Water Column Profiling of CMP 1 conducted on 8 March 2014.
1.5.2
Impact Water Quality Monitoring during Dredging
Operations of CMP 2 –27 February to 31 March 2014
1.5.3
Monitoring data
collected for CMP 2 from 27 February to 31 March 2014 are presented in
this monthly report. Detailed discussion
will be presented in the corresponding Quarterly
Report.
1.5.4
Impact Water Quality Monitoring
during Dredging Operations of CMP 2 was
conducted three times per week from 27 February to 31 March 2014. On each survey day, sampling was conducted
during both mid-ebb and mid-flood tides at two Reference (Upstream) stations
upstream and five Impact (Downstream) stations downstream of the dredging
operations at CMP 2. Monitoring was
also conducted at five Sensitive Receiver Stations situated in Ma Wan, Shum Shui Kok, Tai Mo To and Tai Ho
Bay. A total of twelve stations were
monitored and locations of the sampling stations are shown in Figure 1.1.
1.5.5
Monitoring
results from 27 February to 31 March 2014 are presented in Table C1 of Annex C.
Daily dredging volume in March 2014 is reported in Annex D. Levels of Dissolved
Oxygen (DO), Turbidity and SS generally complied with the Action and Limit
Levels (see Table C2 of Annex C for details) set in the Baseline
Monitoring Report (), except for the following occasions of exceedance
shown in Table 1.1 below.
Table 1.1 Details of Exceedances
Recorded at CMP 2 in February and March 2014
Date
|
Tide
|
Parameter
|
Station
|
Type
|
15 March
2014
|
Mid-Ebb
|
SS
|
DS2
|
Action
|
|
|
SS
|
DS3
|
Action
|
17 March
2014
|
Mid-Ebb
|
SS
|
WSR45C
|
Action
|
19 March
2014
|
Mid-Ebb
|
SS
|
DS2
|
Action
|
|
|
SS
|
DS3
|
Action
|
|
|
SS
|
DS5
|
Action
|
|
|
Turbidity
|
DS5
|
Action
|
|
Mid-Flood
|
SS
|
WSR45C
|
Action
|
|
|
SS
|
WSR46
|
Action
|
|
|
Turbidity
|
WSR46
|
Action
|
21 March
2014
|
Mid-Ebb
|
SS
|
WSR45C
|
Action
|
|
Mid-Flood
|
SS
|
DS1
|
Action
|
31 March
2014
|
Mid-Ebb
|
Turbidity
|
WSR46
|
Limit
|
|
|
SS
|
DS4
|
Action
|
|
|
SS
|
DS5
|
Action
|
|
|
SS
|
WSR46
|
Action
|
|
Mid-Flood
|
SS
|
DS3
|
Action
|
|
|
SS
|
DS5
|
Action
|
|
|
SS
|
WSR45C
|
Action
|
|
|
SS
|
WSR46
|
Action
|
1.5.6
Except for the exceedances recorded during the mid-flood period on 21
March 2014, the other SS and Turbidity were recorded at stations which were
located further away from the works area when compared to Impact station DS1 at
which the levels of SS and Turbidity did not exceed the Action and Limit Levels
during the same tidal period on the same day.
As such, these recorded exceedances are not
likely to be caused by the dredging works at CMP 2.
1.5.7
SS exceedance was recorded at station DS1 only on 21 March
2014 (mid-flood). Since station DS1 was located
at the boundary of the works area, the sole exceedance
at DS1 station did not appear to indicate any unacceptable water quality
impacts outside the works area of the Project. Overall, it did not appear that the SS exceedance was caused by the dredging operations at CMP 2.
1.5.8
It should be
noted that high levels of Turbidity and SS were occasionally recorded during
baseline monitoring which are considered to be sporadic events and
characteristic of water quality in this area of Hong Kong
(baseline monitoring data are summarised in Table C3 of Annex C). Therefore, the Action and Limit Level exceedances may be caused by natural background variation
in water quality of the area.
1.5.9
Overall, the
results indicated that the dredging operations at CMP 2 did not appear to
cause any unacceptable deterioration in water quality during this reporting
period. Therefore, no further mitigation
measures, except for those recommended in the Environmental Permit (EP-427/2011/A), are considered necessary for the dredging operations.
1.5.10
Routine Water Quality Monitoring of SB CMP 1 – February 2014
1.5.11
Monitoring
results for February 2014 are shown in Tables C4-C7 of Annex C. Monthly averaged and daily monitoring results
for February 2014 are presented with graphical presentation in Figure 1-Figure 27 of Annex
B.
1.5.12
The monitoring
results for the Routine
Water Quality Monitoring conducted for
February 2014 in the dry season have been assessed for compliance with the
Water Quality Objectives (WQOs) set by EPD. This
consists of a review of the EPD routine water quality monitoring data for the
dry season period (November to March) of 2003-2012 from stations in the Northwestern Water Control Zone, where the CMPs are located.
For Salinity, the averaged value obtained from the Reference stations
was used for the basis as the WQO. Levels of DO, Turbidity and SS were also assessed for
compliance with the Action and Limit Levels (see Table C2 of Annex C for details).
1.5.13
Locations of
monitoring stations are presented in Figure 1.2 and Figure 1.3.
In-situ
Measurements
1.5.14
Analyses of results indicated that for all the stations
(Impact, Intermediate, Reference and Water Sensitive Receiver stations), both daily
and monthly average levels of pH, DO and Salinity complied with the WQOs in February 2014 (Figure
1, 2, 4, 12, 15, and 16 of Annex
B).
1.5.15
In February
2014, daily and monthly average levels of DO and Turbidity at all the stations complied
with the Action and Limit Levels (Tables C4 and C6 of Annex C).
Laboratory
Measurements
1.5.16
Analyses of
February 2014 results indicated that concentrations of Mercury and Silver were
below their limit of reporting at all the stations. Concentrations
of Cadmium and Chromium were mostly below their limit of reporting except for a
few occasions. The daily concentrations
of Arsenic, Copper, Lead, Nickel and Zinc indicated variations over time at all the stations throughout February
2014. Daily recorded levels of 5-day Biochemical
Oxygen Demand (BOD5), Ammoniacal-Nitrogen
(NH3-N) and Total Inorganic Nitrogen (TIN) were observed to fluctuate
over time throughout February 2014 (Figure 24-26 of Annex B). Compliance
with TIN WQO (0.50 mg/L) was observed at all the stations in the
monitoring period.
1.5.17
In February 2014, monthly averaged concentrations of Copper and Zinc
were slightly higher at Ma Wan station (Figure 6 of Annex
B).
Monthly
average concentrations of the other metals were similar amongst stations (Figure 7 of Annex B). Monthly average levels of BOD5, NH3-N
and TIN were
similar amongst stations (Figures 8 and 9 of Annex B). The monthly
average concentration of TIN did not show any exceedance
of the WQO in February 2014 (Figure 9 of Annex B).
1.5.18
Daily levels
of SS complied with
the Action and Limit Levels set in the EM&A Manual and
occasionally exceeded SS WQO (14.4 mg/L for dry season) in February 2014 (Figure 27 of Annex B). The monthly average level of SS compiled with the WQO at all
stations (Figure 10 of Annex B). These occasional exceedances recorded for daily SS levels are thus not likely to be
caused by mud disposal works, but sporadic
events and characteristic of water quality in this area of Hong
Kong.
1.5.19
Overall,
results of the Routine Water Quality Monitoring indicated that the disposal operation at CMP 1 did
not appear to cause any unacceptable deterioration in water quality in February
2014.
Recommendations
1.5.20
From the
results of the Routine Water Quality Monitoring conducted in October 2013, November 2013, January
2014 and February 2014 for CMP 1, there did not appear to be any unacceptable deterioration in
water quality in all of the sampling events which were conducted three times a
week during the monitoring period. In
accordance with the EM&A Manual, it is recommended to adjust the sampling
frequency to eight (8) times per year which is the same as the frequency of Routine Water Quality Monitoring for CMP V. It is
anticipated that this adjusted sampling frequency is adequate for tracking the
potential change in contaminant concentrations in seawater which may take a
long time to appear while at the same time address the potential seasonal
difference in seawater quality.
1.5.21
Water Column Profiling of CMP 1 – March 2014
1.5.22
Water Column Profiling was undertaken at a total of two sampling stations (Upstream
and Downstream stations) on 8 March 2014.
The water quality monitoring
results have been assessed for compliance with the WQOs
(Table C8 of Annex C). The
monitoring results were also compared with
the Action and Limit Levels set in Baseline Monitoring Report.
In-situ
Measurements
1.5.23
Analyses of
results for March 2014 indicated that levels of Salinity, pH and DO complied
with the WQOs at both Upstream and Downstream
stations (Table C8 of Annex C). DO and Turbidity complied with the Action and
Limit Levels.
Laboratory
Measurements for Suspended Solids (SS)
1.5.24
Analyses of data
obtained on 8 March 2014 indicated that the SS levels at Downstream and
Upstream stations complied with the WQO (Table
C8 of Annex C). In addition, SS
levels at all the stations complied with the Action and Limit Levels.
1.5.25
Overall, the
monitoring results indicated that the mud disposal operation at CMP 1 did not
appear to cause any deterioration in water quality during this reporting period.
1.5.26
Pit Specific Sediment Chemistry of CMP 1 – December 2013
1.5.27
Monitoring
locations for Pit Specific Sediment Chemistry for CMP 1 are shown in Figure 1.4. A total of
six (6) monitoring stations were sampled in December 2013.
1.5.28
The concentrations of all the metals except Arsenic were lower than the Lower Chemical Exceedance Level (LCEL) at all stations in December 2013 (Figures 28 and 29 of Annex B). Concentrations of Arsenic exceeded the LCEL
at all stations except Active Pit station SB-NPAB and Near Pit station SB-NNAB.
1.5.29
Whilst the
average concentration of Arsenic in the Earth’s crust is generally ~2mg/kg, significantly
higher Arsenic concentrations (median = 14 mg/kg) have been recorded in Hong Kong’s onshore sediments ([8]). It is presumed that the natural concentrations of
Arsenic are similar in onshore and offshore sediments ([9]), and relatively high Arsenic levels may thus occur
throughout Hong Kong. Therefore,
the LECL exceedances of Arsenic are unlikely to be
caused by the disposal operations at CMP 1 but rather as a result of naturally
occurring deposits.
1.5.30
For organic contaminants, the
concentration of Total Organic Carbon (TOC) concentration was similar amongst
stations in December 2013 (Figure 30 of Annex B). Concentrations
of Tributyltin (TBTs) were observed
to be higher at Active Pit station SB-NPAA and SB-NPAB in December 2013 (Figure
31 of Annex B). Low and High Molecular Weight Polycyclic Aromatic
Hydrocarbons (Low and High MW PAHs) concentrations
were recorded below the limit of reporting at all stations except Active Pit station
SB-NPAB (Figure 32 of Annex B).
Total Dichloro-Diphenyl-Trichloroethane
(DDT), 4,4’-Dichloro-Diphenyl-Dichloroethylene
(4,4’-DDE) and Total Polychlorinated Biphenyls (PCBs) were recorded below the
limit of reporting at all the stations in December 2013.
1.5.31
Active Pit stations SB-NPAA and SB-NPAB are located within CMP 1 which was receiving contaminated mud during
the reporting period. Therefore, the
higher concentrations of contaminants (including metals and organic
contaminants) recorded at the Active Pit stations only are not considered as
indicating any dispersal of contaminated mud from CMP 1. Nevertheless, detailed analyses will be
presented in the Quarterly Report to reveal any
trend of increasing sediment contaminant concentrations towards CMP 1.
1.5.32
Overall, there is no evidence
indicating any unacceptable environmental impacts to sediment quality as a
result of the contaminated mud disposal operations at CMP 1 during this monthly
period.
1.6
Activities Scheduled for the Next Month
1.6.1
The following
monitoring activities will be conducted in the next monthly period of April 2014
for SB CMPs:
·
Impact Water Quality Monitoring during Dredging
Operations of CMP 2;
·
Pit Specific Sediment Chemistry of CMP 1;
·
Routine Water
Quality Monitoring of CMP 1; and
·
Water Column Profiling of CMP 1.
1.6.2
The sampling
schedule is presented in Annex A.
1.7.1
A summary of the Study
programme is presented in Annex E.