Agreement No.
CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits at the South of The Brothers
and at East Sha Chau (2012-2017) -
Investigation
17TH MONTHLY PROGRESS REPORT FOR January
2014
1.1.1
Since early 1990s, contaminated
sediment ([1])
arising from various construction works (e.g. dredging and
reclamation projects) in Hong Kong has been disposed of at a series of seabed
pits at East of Sha Chau (ESC). In
late 2008, a review indicated that the existing and planned facilities at ESC
would not be able to meet the disposal demand after 2012. In order to meet this demand, the Hong
Kong Special Administrative Region Government (HKSARG) decided to implement a
new contained aquatic disposal (CAD) ([2])
facility at the South of The Brothers (SB CMPs) which had
been under consideration for a number of years.
1.1.2
The environmental acceptability of
the construction and operation of the Project had been confirmed by findings of
the associated Environmental Impact Assessment (EIA) study completed in 2005
under
Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO) in
September 2005 (EIA Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA
recommendation, prior to commencement of construction works for the SB CMPs,
the Civil Engineering and Development Department (CEDD) undertook a detailed
review and update of the EIA findings for the SB site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had
been predicted to be environmentally acceptable.
1.1.4
Environmental Permits (EPs) (EP-312/2008/A
and EP-427/2011A)
were issued by the Environmental Protection Department (EPD) to the CEDD, the
Permit Holder, on 28 November 2008 for East of Sha Chau (ESC) CMP V and on 23
December 2011 for SB CMPs, respectively.
Under the requirements of the EPs, an Environmental Monitoring
and Audit (EM&A) programme as set out in the EM&A Manuals ()
() is
required to be implemented for the CMPs.
1.1.5
The present
EM&A programme undertaken under Agreement No. CE 23/2012 (EP)
covers the dredging, disposal and capping operations of the SB CMPs as well as CMPs at East of Sha Chau (ESC).
In January 2014, the following works were
being undertaken at the CMPs:
¡P Capping was being
undertaken at CMP IVc and CMP Va;
¡P Disposal of contaminated
mud was taking place at SB CMP 1; and
¡P Dredging operations were
taking place at SB CMP 2.
1.2
Reporting Period
1.2.1
This Monthly Progress Report covers
the EM&A activities for the reporting month of
January 2014.
1.3
Details of Sampling and Laboratory
Testing Activities
1.3.1
No
monitoring activities have been undertaken for CMP IV and V in the reporting month of
January 2014.
1.3.2
The
following monitoring activities have been undertaken for SB CMPs in January
2014:
¡P
Impact Water Quality
Monitoring during Dredging Operations was undertaken for CMP 2 three times per week
on 2, 4, 6, 8, 10, 13, 15, 17, 20, 22, 24, and 28 January 2014;
¡P
Routine Water
Quality Monitoring was undertaken for CMP 1 on 3, 7, 9, 11, 14, 16, 18,
21, 23, 25, 27, and 29 January 2014;
¡P
Demersal Trawling for CMP 1 was
carried out on 7 and 8 January 2014;
¡P
Water Column Profiling for CMP 1 was undertaken on
9 January 2014; and
¡P
Pit Specific Sediment
Chemistry was
conducted for CMP 1 on 21 January 2014.
1.4.1
No outstanding
sampling remained for January 2014. The
following laboratory analyses were still in progress during the preparation of
this monthly report and hence were not presented in this monthly report:
¡P Laboratory analyses of sediment samples collected for Pit Specific Sediment Chemistry of CMP 1 in December 2013 and January 2014;
¡P Laboratory analyses of sediment samples collected for Cumulative Impact Sediment
Chemistry of CMP 1 in December 2013;
¡P Laboratory
analyses of water samples collected for Routine Water Quality
Monitoring for CMP 1 from 18 to 29 January 2014; and
¡P
Laboratory analyses of Suspended
Solids (SS) samples collected for Water Quality Monitoring during Dredging
Operations of CMP 2 from 10 to 28 January 2014.
1.4.2
A summary of field activities
conducted are presented in Annex
A.
1.5.1
Brief discussion of the monitoring results of the following
activities is presented in this 17th Monthly
Report:
¡P
Impact Water Quality
Monitoring during Dredging Operations of CMP 2 conducted from 11 December 2013 to 8 January 2014;
¡P
Water Column Profiling of
CMP 1 conducted in January 2014;
¡P
Routine Water Quality
Monitoring of CMP 1 undertaken
from 3 to 16 January 2014; and
¡P
Pit Specific Sediment
Chemistry of CMP 1 conducted in November 2013.
1.5.2
Impact Water
Quality Monitoring during Dredging Operations of CMP 2 ¡V 11 December 2013 to 8
January 2014
1.5.3
Monitoring data collected for CMP 2 from 11 December 2013 to 8 January 2014
are presented in this monthly report.
Detailed discussion will be presented in the corresponding Quarterly Report.
1.5.4
Impact Water Quality Monitoring during Dredging
Operations of CMP 2 was conducted three times per week from 11 December
2013 to 8 January 2014. On each
survey day, sampling was conducted during both mid-ebb and mid-flood tides at
two Reference (Upstream) stations upstream and five Impact (Downstream)
stations downstream of the dredging operations at CMP 2. Monitoring was also conducted at five
Sensitive Receiver Stations situated in Ma Wan, Shum Shui Kok, Tai Mo To and
Tai Ho Bay. A total of twelve
stations were monitored and locations of the sampling stations are shown in Figure 1.1.
1.5.5
Monitoring results from 11 December
2013 to 8 January 2014 are presented in Table C1 of Annex C. Daily dredging volume in December 2013 is
reported in Annex D. Levels of Dissolved Oxygen (DO),
Turbidity and SS generally complied with the Action and Limit Levels (see Table C2 of Annex C
for details) set in the Baseline Monitoring Report (),
except for the following occasions of exceedances shown in Table 1.1 below.
Table 1.1 Details of Exceedances
Recorded at CMP 2 in December 2013/
January 2014
Date
|
Tide
|
Parameter
|
Station
|
Type
|
11 December 2013
|
Mid-Flood
|
Turbidity
|
DS1
|
Limit
|
|
|
SS
|
DS1
|
Limit
|
16 December 2013
|
Mid-Flood
|
SS
|
DS1
|
Action
|
20 December 2013
|
Mid-Flood
|
Turbidity
|
DS4
|
Action
|
|
|
SS
|
DS4
|
Action
|
23 December 2013
|
Mid-Flood
|
SS
|
DS2
|
Action
|
27 December 2013
|
Mid-Flood
|
SS
|
DS1
|
Action
|
4 January 2014
|
Mid-Flood
|
SS
|
DS1
|
Action
|
|
|
SS
|
DS2
|
Action
|
|
|
SS
|
WSR45C
|
Action
|
6 January 2014
|
Mid-Flood
|
Turbidity
|
DS2
|
Action
|
|
|
SS
|
DS2
|
Action
|
1.5.6
Regarding the exceedances
observed, most of them were recorded at one station
only during the sampling event. The
exceedances on 4 January 2014 were recorded at three monitoring stations,
however, these exceedances did not show any trend of
increasing SS or Turbidity levels toward the dredging operations
. As such, it is considered
that these exceedances were not indicating any
unacceptable water quality impacts as a result of the dredging operations at the CMP 2.
1.5.7
In addition to the above, high
levels of Turbidity and SS were occasionally recorded during baseline
monitoring which are considered to be sporadic events and characteristic of
water quality in this area of Hong Kong.
Therefore, the Action and Limit Level exceedances may be caused by
natural background variation in water quality of the area.
1.5.8
Overall, the results indicated that
the dredging operations at CMP 2 did not appear to cause any unacceptable
deterioration in water quality during this reporting period. Therefore, no further mitigation
measures, except for those recommended in the Environmental Permit (EP-427/2011/A),
are considered necessary for the dredging operations.
1.5.9
Water Column Profiling of CMP 1 ¡V January 2014
1.5.10
Water Column Profiling was undertaken
at a total of two sampling stations (Upstream and Downstream stations) on 9
January 2014. The water quality monitoring results have been
assessed for compliance with the Water Quality Objectives (WQOs) set by EPD. This
consists of a review of the EPD routine water quality monitoring data for the
dry season period (November to March) of 2003-2012 from stations in the
Northwestern Water Control Zone, where the CMPs are located. For Salinity, the average value obtained
from the Upstream station was used for the basis as
the WQO. The monitoring results
were also compared with the Action
and Limit Levels set in the EM&A Manual (). Graphical presentations of the
monitoring results are provided in Annex
B.
In-situ Measurements
1.5.11
Analyses of results for 9 January
2014 indicated that levels of Salinity, pH and DO complied with the WQOs at
both Upstream and Downstream stations (Figures 1-3 of Annex B). DO and Turbidity complied with the
Action and Limit Levels set in the EM&A Manual.
Laboratory Measurements for Suspended Solids (SS)
1.5.12
Analyses of data obtained on 9
January 2014 indicated that the SS levels at Downstream and Upstream stations
complied with the WQO (Figure 4 of Annex B). In addition, SS levels at all the
stations complied with the Action and Limit Levels set in the EM&A Manual.
1.5.13
Overall, in-situ
measurement and laboratory analyses results indicated that the mud disposal
operation at CMP 1 did not appear to cause any deterioration in water quality
during this reporting period.
1.5.14
Routine Water Quality Monitoring of SB CMP 1 ¡V January 2014
1.5.15
The monitoring
results for the Routine Water Quality Monitoring conducted on 3, 7, 9, 11, 14 and 16 January 2014 in the dry
season have been assessed for compliance with the WQOs set by EPD. This
consists of a review of the EPD routine water quality monitoring data for the
dry season period (November to March) of 2003-2012 from stations in the
Northwestern Water Control Zone, where the CMPs are located. For Salinity, the averaged value
obtained from the Reference stations was used for the basis as the WQO.
1.5.16
Daily in-situ monitoring and daily
laboratory results are shown in Tables C3 and C4 of Annex C. Monthly
averaged in-situ measurement and laboratory analyses results for January
2014 will be presented with graphical presentation in the next monthly report
when all the laboratory analyses are completed. Locations of monitoring stations were
presented in Figure 1.2 and 1.3.
In-situ Measurements
1.5.17
Analyses of results indicated that for all the stations
(Impact, Intermediate, Reference and Water Sensitive Receiver stations), daily
levels of pH, DO and Salinity complied with the WQOs (Table
C3 of Annex C).
1.5.18
Levels of
Temperature, Salinity and pH showed similar magnitude from 3 to 16 January 2014 (Figure 5, 6 and 10 of Annex B) at all the stations. Levels of DO were detected to fluctuate over time from 3 to 16 January 2014 and also showed
relative variations amongst the stations (Figure 9 of Annex B).
1.5.19
Daily
levels of Turbidity from 3 to 16 January 2014 all complied with the Action and
Limit Levels set in the EM&A Manual (Tables C3 of Annex C), except Turbidity levels at Intermediate Station and
Ma Wan Station on 3 January 2014.
Fluctuation of Turbidity levels over time from 3 to 16 January 2014 was also recorded (Figure 7 of Annex B). Levels
of Turbidity also showed relative variations amongst the stations.
Laboratory Measurements
1.5.20
Laboratory
analyses results
of metals and nutrients are presented in Table
C4 of Annex C.
Graphical presentations of monitoring results on individual monitoring
days are presented in Figure 11-23 of Annex B.
1.5.21
Analyses
of 3 to 16 January 2014 results indicated that concentrations of Silver,
Cadmium and Mercury were below their limit of reporting at all
the stations (Figure 11, 13 and 17 of Annex B).
Recorded concentrations of Arsenic, Chromium, Copper, Lead, Nickel and
Zinc indicated variations over time at all the stations from 3 to 16 January 2014 without
any trend of increasing contaminant concentrations towards the pit (Figure 12, 14, 15, 16, 18 and
19 of Annex B).
1.5.22
Daily
recorded levels of TIN, BOD5 and NH3-N were observed to fluctuate
over time through 3 to 16 January
2014 (Figure 20-22 of Annex B). Compliance with TIN WQO (0.50 mg/L)
was recorded at all the stations in the monitoring period except the
measurement at Water Sensitive Receiver station THB1 on 9 January 2014. The only exceedance of TIN WQO at Water Sensitive Receiver
station THB1 on one day did
not provide any evidence of unacceptable water quality impacts due to the mud
disposal activities.
1.5.23
Daily
levels of SS from 3
to 16 January 2014 all complied with the Action and Limit Levels set in the EM&A Manual (Tables C4 of Annex C). Exceedances of SS WQO (14.4 mg/L for dry season) were
recorded (Figure 23
of Annex
B) from 3 to 16 January 2014. The exceedances of WQO were recorded at
Reference stations, Impact stations and other Water Sensitive Receiver stations
on the same monitoring day (3 January 2014). The reference stations are located
upstream from the mud pits and considered unlikely to be affected by mud
disposal works. In addition, the SS
levels at Impact stations were recorded lower than those at Reference or
Intermediate stations. Given the information above, it is considered that the
exceedances of SS WQO are
unlikely to be caused by mud disposal operations. Instead,
high levels of SS were occasionally recorded during baseline monitoring which
are considered to be sporadic events and characteristic of water quality in
this area of Hong Kong.
1.5.24
The exceedances
of SS WQO on 7,
11, 14, and 16 January 2014 were also recorded at stations which
are located further away from the works area when compared to Impact stations
at which the levels of SS did not exceed WQO on the same day. Hence,
these exceedances of WQO are not considered to be caused by mud disposal
works.
1.5.25
Overall, in-situ
measurement and laboratory analyses results
indicated that the disposal operation at CMP 1 did not appear to cause any
unacceptable deterioration in water quality during monitoring period of 3 to 16
January 2014.
1.5.26
Pit Specific
Sediment Chemistry of CMP 1 ¡V November 2013
1.5.27
Monitoring
locations for Pit Specific Sediment Chemistry for CMP 1 are shown in Figure 1.4. A total
of six monitoring stations were sampled in November
2013.
1.5.28
The concentrations of all the metals except Arsenic,
Copper, Lead, Silver and Zinc complied
with the Lower Chemical Exceedance Level (LCEL) at
most stations in November 2013 (Figures 24 and 25 of Annex B).
Concentrations of Arsenic exceeded the LCEL at all stations except
Active Pit station SB-NPAB. Levels
of Copper, Lead, Silver and Zinc exceeded the LCEL at Active Pit station
SB-NPAB only.
1.5.29
Whilst
the average concentration of Arsenic in the Earth¡¦s crust is generally ~2mg/kg,
significantly higher Arsenic concentrations (median = 14 mg/kg) have been
recorded in Hong Kong¡¦s onshore sediments ([9]). It is presumed that the natural concentrations of Arsenic are similar in
onshore and offshore sediments ([10]), and relatively high Arsenic levels may thus occur
throughout Hong Kong. Therefore, the LECL exceedances of Arsenic are unlikely to
be caused by the disposal operations at CMP 1 but rather as a result of
naturally occurring deposits.
1.5.1
The concentration of Total Organic
Carbon (TOC) concentration
showed variations amongst the stations in November 2013 (Figure 26 of Annex B). Tributyltin
(TBTs) concentrations
were found to be higher at Active
Pit station SB-NPAB (Figure 27 of Annex B) in November 2013.
1.5.2
Low
Molecular Weight Polycyclic Aromatic Hydrocarbons (MW PAHs) concentrations were
recorded below the limit of reporting at all stations except Active Pit station SB-NPAB in November 2013 (Figure 28 of Annex B). The concentrations of Low MW PAHs at Active Pit station SB-NPAB are recorded below LCEL. High MW PAHs concentrations were
recorded below the limit of reporting at all stations except Active Pit stations SB-NPAA and SB-NPAB in November 2013 (Figure 28 of Annex B). High MW PAHs
concentrations at Active Pit station SB-NPAB
exceeded LCEL in November 2013.
1.5.3
Total Dichloro-Diphenyl-Trichloroethane (DDT),
4,4¡¦-Dichloro-Diphenyl-Dichloroethylene
(4,4¡¦-DDE) and Total Polychlorinated Biphenyls (PCBs) were recorded below the
limit of reporting at all the stations except Active Pit station SB-NPAB in October 2013.
Total PCBs concentrations at Active
Pit station SB-NPAB exceeded LCEL in November 2013.
1.5.4
Active
Pit stations SB-NPAA and SB-NPAB are located within CMP 1 which was receiving contaminated mud during
the reporting period. Therefore,
the higher concentrations of contaminants (including metals and organic
contaminants) recorded at the Active Pit stations only are not considered as
indicating any dispersal of contaminated mud from CMP 1. Nevertheless, detailed analyses will be
presented in the Quarterly Report to reveal any trend of increasing
sediment contaminant concentrations towards CMP 1.
1.5.5
Overall,
there is no evidence indicating any unacceptable environmental impacts to
sediment quality as a result of the contaminated mud disposal operations at CMP
1 during this monthly period.
1.6
Activities Scheduled for the
Next Month
1.6.1
The following monitoring activities
will be conducted in the next monthly period of February 2014 for SB CMPs:
¡P
Impact Water Quality
Monitoring during Dredging Operations of CMP 2;
¡P
Pit Specific Sediment
Chemistry of CMP 1;
¡P
Cumulative Impact Sediment
Chemistry of CMP 1;
¡P
Sediment Toxicity Test of CMP 1;
¡P
Tissue/ Whole Body Sampling
of CMP 1;
¡P
Demersal Trawling
of CMP 1;
¡P
Routine Water
Quality Monitoring of CMP 1; and
¡P
Water Column Profiling of CMP 1.
1.6.2
Water Quality Monitoring during Capping
of
CMP V will be conducted in the next monthly period of February
2014.
1.6.3
The sampling schedule is presented
in Annex A.
1.7.1
A summary of the Study programme is
presented in Annex E.