Agreement No.
CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) -
Investigation
15TH
MONTHLY PROGRESS REPORT FOR NOVEMBER 2013
1.1.1
Since early 1990s, contaminated
sediment ([1])
arising from various construction works (e.g. dredging and
reclamation projects) in Hong Kong has been disposed of at a series of seabed
pits at East of Sha Chau (ESC). In
late 2008, a review indicated that the existing and planned facilities at ESC
would not be able to meet the disposal demand after 2012. In order to meet this demand, the Hong
Kong Special Administrative Region Government (HKSARG) decided to implement a
new contained aquatic disposal (CAD) ([2])
facility at the South of The Brothers (SB CMPs) which had
been under consideration for a number of years.
1.1.2
The environmental acceptability of
the construction and operation of the Project had been confirmed by findings of
the associated Environmental Impact Assessment (EIA) study completed in 2005
under
Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO) in
September 2005 (EIA Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA
recommendation, prior to commencement of construction works for the SB CMPs,
the Civil Engineering and Development Department (CEDD) undertook a detailed
review and update of the EIA findings for the SB site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had
been predicted to be environmentally acceptable.
1.1.4
Environmental Permits (EPs) (EP-312/2008/A
and EP-427/2011A)
were issued by the Environmental Protection Department (EPD) to the CEDD, the
Permit Holder, on 28 November 2008 for East of Sha Chau (ESC) CMP V and on 23
December 2011 for SB CMPs, respectively.
Under the requirements of the EPs, an Environmental Monitoring
and Audit (EM&A) programme as set out in the EM&A Manuals ()
() is
required to be implemented for the CMPs.
1.1.5
The present
EM&A programme undertaken under Agreement No. CE 23/2012 (EP)
covers the dredging, disposal and capping operations of the SB CMPs as well as CMPs at East of Sha Chau (ESC).
In November 2013, the following works
were being undertaken at the CMPs:
¡P
Capping was being undertaken at CMP IVc and CMP Va;
¡P
Disposal of contaminated mud was taking place at SB CMP 1; and
¡P
Dredging operations were taking place at SB CMP 2.
1.2
Reporting Period
1.2.1
This Monthly Progress Report covers
the EM&A activities for the reporting month of
November 2013.
1.3
Details of Sampling and
Laboratory Testing Activities
1.3.1
No
monitoring activities were undertaken for CMP V in the monitoring month of November
2013.
1.3.2
The
following monitoring activities have been undertaken for SB CMPs in November
2013 in accordance with the EM&A Manual:
¡P
Impact Water Quality
Monitoring during Dredging Operations was undertaken for CMP 2 three times per week
on 1, 5, 7, 9, 11, 13, 15, 18, 20, 22, 25, 27 and 29 November 2013;
¡P
Routine Water Quality
Monitoring was
conducted for CMP 1 three times per
week on 2, 5, 7, 9, 12, 14, 16, 19, 21, 23, 26, 28 and 30 November 2013;
¡P
Water Column Profiling was undertaken for CMP 1 on
7 November 2013; and,
¡P
Pit Specific Sediment
Chemistry was
conducted for CMP 1 on 12 November 2013.
1.4.1
No outstanding
sampling remained for November
2013. The following laboratory analyses were
still in progress during the preparation of this monthly report:
¡P
Laboratory
analyses of sediment samples collected for Pit
Specific Sediment Chemistry of CMP 1 in
October and November 2013;
¡P
Laboratory analyses of Suspended
Solids (SS) samples collected for Water Quality Monitoring during Dredging
Operations of CMP 2 from 18 to 29 November 2013; and
¡P
Laboratory analyses of water samples
collected for Routine Water Quality Monitoring of CMP 1 from 19
October to 30 November 2013.
1.4.2
A summary of field activities conducted are
presented in Annex A.
1.5.1
Brief discussion
of the monitoring results of Cumulative Impact Sediment
Chemistry Monitoring conducted in August 2013 is presented in this 15th Monthly Report. Detailed discussion will be presented in
the corresponding Quarterly Report.
1.5.2
Cumulative Impact
Sediment Chemistry of CMP V ¡V August 2013
1.5.3
Monitoring
locations for Cumulative Impact Sediment Chemistry for CMP V are shown in Figure 1.1. A total
of nine monitoring stations were sampled in August
2013.
1.5.4
Analyses of results for the Cumulative Impact
Sediment Chemistry Monitoring indicated that the concentrations
of all metals, except Arsenic, were below the Lower Chemical Exceedance Level (LCEL)
in August 2013 (Figures 1 and 2 of Annex B). Concentrations of Arsenic in sediments from all stations,
except for Near Field stations RNA and RNB and Ma Wan Station, exceeded the
LCEL.
1.5.5
Whilst
the average concentration of Arsenic in the Earth¡¦s crust is generally ~2mg/kg,
significantly higher Arsenic concentrations (median = 14 mg/kg) have been
recorded in Hong Kong¡¦s onshore sediments ([7]). It is presumed that the natural concentrations of Arsenic are similar in
onshore and offshore sediments ([8]), and relatively high Arsenic levels may thus occur
throughout Hong Kong. Therefore, the LECL exceedances of Arsenic are unlikely to
be caused by the disposal operations at CMP Va but rather as a result of
naturally occurring deposits. The
slight exceedances of the LCEL for the Arsenic do not necessarily indicate any
unacceptable impacts to sediment quality caused by disposal operation at CMP
Va.
1.5.6
The concentration of Total Organic
Carbon (TOC) shows variation amongst stations (Figure 3
of Annex B). Tributyltin (TBTs) were recorded in
sediment samples from all stations and Ma Wan station was recorded with a
higher concentration (Figure 4 of Annex B). Concentrations of Total Polychlorinated
Biphenyls (PCBs), Low and High Molecular Weight Polycyclic
aromatic hydrocarbons (Low and High MW PAHs), total Dichloro-diphenyl-trichloroethane
(DDT) and 4,4¡¦-Dichloro-diphenyl-dichloroethylene (4,4¡¦-DDE) were
recorded below the limit of detection at all the stations.
1.5.7
Overall,
there is no evidence indicating any unacceptable environmental impacts to
sediment quality as a result of the contaminated mud disposal operations at CMP
Va during this monthly period.
1.6
Brief Discussion of the
Monitoring Results for SB CMPs
1.6.1
Brief discussion
of the monitoring results of Pit Specific Sediment
Chemistry of CMP 1 conducted in September
2013, Impact
Water Quality Monitoring during Dredging Operations of CMP 2 conducted from 30 October to 15 November 2013 and
Water
Column Profiling conducted in November 2013 is presented in this 15th
Monthly Report. Detailed discussion will be presented in
the corresponding Quarterly Report.
1.6.2
Pit Specific
Sediment Chemistry of CMP 1 ¡V September 2013
1.6.3
Monitoring
locations for Pit Specific Sediment Chemistry for CMP 1 are shown in Figure 1.2. A total
of six monitoring stations were sampled in September
2013.
1.6.4
The concentrations of all the metals except Arsenic complied with the LCEL at all stations in September
2013 (Figures 5 and 6 of Annex B).
Concentrations of Arsenic exceeded the LCEL at all stations except
Active Pit station SB-NPAB (Figures 5 and 6 of Annex B).
1.6.5
As
discussed in Section 1.5.5 above, relatively high natural levels of
Arsenic are present in Hong Kong¡¦s marine sediments and hence the slight LCEL
exceedances of Arsenic do not necessarily indicate any adverse impacts to
sediment quality caused by disposal operation at CMP 1.
1.6.6
TOC
concentration indicated variations amongst the stations in September 2013 (Figure 7 of Annex B). TBT concentrations were found to be
higher at Active Pit Station SB-NPAB and Near Pit Station SB-NNAB (Figure 8 of Annex B) in September 2013.
1.6.7
Low
and High MW PAHs concentrations were recorded below the limit of reporting at
all stations except for High MW PAHs concentration at Active Pit station
SB-NPAB in September 2013 (Figure 9 of Annex B).
1.6.8
Total
DDT, 4,4¡¦-DDE and Total PCBs were recorded below the
limit of reporting at all the stations in September 2013.
1.6.9
Active
Pit station SB-NPAB
is located within CMP 1 which was receiving contaminated mud during the
reporting period. Therefore, the
higher concentrations of contaminants (including metals and organic
contaminants) recorded at the Active Pit station only are not considered as
indicating any dispersal of contaminated mud from CMP 1. Nevertheless, detailed analysis will be
presented in the Quarterly Report to reveal any trend of increasing
sediment contaminant concentrations towards CMP 1.
1.6.10
Overall,
there is no evidence indicating any unacceptable environmental impacts to
sediment quality as a result of the contaminated mud disposal operations at CMP
1 during this monthly period.
1.6.11
Impact Water
Quality Monitoring during Dredging Operations of CMP 2 ¡V 30 October to 15 November 2013
1.6.12
Monitoring data collected for CMP 2 from 30 October to 15 November 2013 are presented in this monthly
report. Detailed discussion will be
presented in the corresponding Quarterly Report.
1.6.13
Impact Water Quality Monitoring during Dredging
Operations of CMP 2 (i.e. from 30
October to 15 November 2013) was conducted three times per week
for a total of eight (8) sampling days.
On each survey day, sampling was conducted during both mid-ebb and
mid-flood tides at two Reference (Upstream) stations upstream and five Impact
(Downstream) stations downstream of the dredging operations at CMP 2. Monitoring was also conducted at five
Sensitive Receiver Stations (Ma Wan, Shum Shui Kok, Tai Mo To and Tai Ho
Bay). A total of twelve stations
were monitored and locations of the sampling stations are shown in Figure 1.3.
1.6.14
Monitoring results from 30 October to 15 November 2013 are presented in Table C1 of Annex C. Daily dredging record of the reporting
period is presented in Annex
D. Levels of DO,
Turbidity and SS generally complied with the Action and Limit Levels (see Table C2 of Annex C
for details) set in the Baseline Monitoring Report (),
except for the following occasions of exceedances shown in Table 1.1 below.
Table 1.1 Details of exceedances
recorded at SB CMP 2 in October / November 2013
Date
|
Tide
|
Parameter
|
Station
|
Type
|
30 October 2013
|
Mid-Flood
|
Turbidity
|
DS5
|
Limit
|
|
|
SS
|
DS5
|
Action
|
1 November 2013
|
Mid-Ebb
|
Turbidity
|
DS1
|
Action
|
|
|
SS
|
DS1
|
Action
|
|
Mid-Flood
|
SS
|
DS1
|
Action
|
|
|
SS
|
DS3
|
Action
|
5 November 2013
|
Mid-Flood
|
SS
|
DS3
|
Action
|
|
|
SS
|
DS4
|
Action
|
7 November 2013
|
Mid-Flood
|
Turbidity
|
DS1
|
Limit
|
|
|
SS
|
DS1
|
Limit
|
|
|
SS
|
DS2
|
Action
|
|
|
SS
|
DS3
|
Action
|
|
|
SS
|
DS4
|
Action
|
|
|
SS
|
WSR45C
|
Action
|
11 November 2013
|
Mid-Flood
|
SS
|
DS4
|
Action
|
13 November 2013
|
Mid-Flood
|
SS
|
DS3
|
Action
|
|
|
SS
|
DS5
|
Action
|
15 November 2013
|
Mid-Flood
|
SS
|
WSR46
|
Action
|
1.6.15
It should be noted that the exceedances on 30 October 2013 and 5, 11, 13 and 15
November 2013 (mid-flood tide) were recorded at stations which are located
further away from the works area when compared to station DS1 at which the
levels of SS and Turbidity did not exceed the Action and Limit Levels during
the same tidal period on the same day.
As such, these recorded exceedances are not
likely to be caused by the dredging works at CMP 2.
1.6.16
Linear Regression was conducted to determine any significant
spatial trend of SS levels recorded at stations DS1 to DS4 during the mid-flood tide on
7 November 2013. The results of the statistical analysis did
not indicate any significant spatial trend of increasing SS levels with
proximity to the dredging operations (i.e. r2 value < 0.6). As such, there did not appear to be any
evidence of unacceptable water quality impact as a result of the dredging
operations at the CMP 2 although exceedances were
recorded during the mid-flood tide on 7 November 2013.
1.6.17
Exceedances
at DS1 and other stations were also detected on 1 November (mid-ebb and
mid-flood). However, these
exceedances did not indicate any trend of increasing SS or Turbidity levels
toward the dredging operations.
Instead, high levels of Turbidity and SS and low levels of DO were
occasionally recorded during baseline monitoring which are considered to be
sporadic events and characteristic of water quality in this area of Hong
Kong. Therefore, the Action and
Limit Level exceedances may be caused by natural background variation in water
quality of the area.
1.6.18
Overall, the results indicated that
the dredging operations at CMP 2 did not appear to cause any unacceptable
deterioration in water quality during this reporting period. Therefore, no further mitigation
measures, except for those recommended in the Environmental Permit (EP-427/2011/A),
are considered necessary for the dredging operations.
1.6.19
Water Column Profiling for CMP 1 ¡V November 2013
In-situ Measurements
1.6.20
Water Column Profiling was
undertaken at a total of two sampling stations (Upstream and Downstream
stations) in November 2013. The water quality monitoring results for November 2013
have been assessed for compliance with the Water Quality Objectives (WQOs) set
by Environmental Protection Department (EPD). This
consists of a review of the EPD routine water quality monitoring data for the
dry season period (November to March) of 2003-2012 from stations in the
Northwestern Water Control Zone, where the CMPs are located. For Salinity, the average value obtained
from the Upstream station was used for the basis as
the WQO. Graphical presentation of the monitoring results is provided in Annex B.
1.6.21
Analyses of results for November
2013 indicated that levels of Salinity, pH and DO complied with the WQOs at
both Upstream and Downstream stations (Figures 10-12 of Annex B). DO and Turbidity complied with the
Action and Limit Levels set in the EM&A Manual ().
Laboratory
Measurements for Suspended Solids (SS)
1.6.22
Analyses of data obtained in
November 2013 indicated that the SS levels at Downstream and Upstream stations complied the WQO (Figure 13 of Annex B). In addition, SS levels at all stations
complied with the Action and Limit Levels set in the EM&A Manual.
1.6.23
Overall, the results indicated that
the mud disposal operation at CMP 1 did not appear to cause any deterioration
in water quality during this reporting period.
1.7
Activities Scheduled for the
Next Month
1.7.1
Pit Specific Sediment Chemistry,
Cumulative
Impact Sediment Chemistry, and Water Column Profiling for
CMP 1 as well as Impact Water Quality Monitoring during Dredging Operations for
CMP 2 will be conducted in the next monthly period of December 2013.
1.7.2
Water Quality Monitoring during Capping
for CMP IVc and CMP V and Benthic Recolonisation Studies for CMP IV
will be conducted in the next monthly period of December 2013.
1.7.3
The sampling schedule is presented
in Annex A.
1.8.1
A summary of the Study programme is
presented in Annex E.