Agreement No. CE 23/2012
(EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits at the South of The Brothers and at East
Sha Chau (2012-2017) - Investigation
14TH MONTHLY
PROGRESS REPORT FOR OCTOBER 2013
1.1.1
Since early 1990s, contaminated
sediment ([1]) arising from
various construction works (e.g. dredging and reclamation projects) in Hong Kong has been disposed of at a series of seabed pits
at East of Sha Chau (ESC). In late 2008,
a review indicated that the existing and planned facilities at ESC would not be
able to meet the disposal demand after 2012.
In order to meet this demand, the Hong Kong Special Administrative
Region Government (HKSARG) decided to implement a new contained aquatic
disposal (CAD) ([2])
facility at the South of The Brothers (SB CMPs) which had been under
consideration for a number of years.
1.1.2
The environmental acceptability of the
construction and operation of the Project had been confirmed by findings of the
associated Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE
12/2002(EP) ([3]).
The Director of Environmental Protection (DEP) approved this EIA report
under the Environmental
Impact Assessment Ordinance (Cap. 499) (EIAO) in
September 2005 (EIA Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA
recommendation, prior to commencement of construction works for the SB CMPs,
the Civil Engineering and Development Department (CEDD) undertook a detailed
review and update of the EIA findings for the SB site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had
been predicted to be environmentally acceptable.
1.1.4
Environmental Permits (EPs) (EP-312/2008/A and EP-427/2011A) were
issued by the Environmental Protection Department (EPD) to the CEDD, the Permit
Holder, on 28 November 2008 for East of Sha Chau (ESC) CMP V and on 23 December
2011 for SB CMPs, respectively. Under
the requirements of the EPs, an Environmental Monitoring and Audit
(EM&A) programme as set out in the EM&A Manuals ()
() is
required to be implemented for the CMPs.
1.1.5
The present EM&A programme undertaken
under Agreement
No. CE 23/2012 (EP) covers the dredging, disposal and capping operations
of the SB CMPs as
well as CMPs at East of Sha Chau (ESC). In October 2013, the following works were
being undertaken at the CMPs:
·
Capping
was being undertaken at CMP IVc and CMP Va;
·
Disposal of
contaminated mud was taking place at SB CMP 1; and
·
Dredging
operations were taking place at SB CMP 2.
1.2
Reporting Period
1.2.1
This Monthly Progress Report covers the EM&A
activities for the reporting month of October 2013.
1.3
Details of Sampling and Laboratory Testing Activities
1.3.1
No monitoring activities
were undertaken for CMP IV and V in the
monitoring month of October 2013.
1.3.2
The following
monitoring activities have been undertaken for SB CMPs in September 2013:
·
Pit Specific Sediment Chemistry was conducted for CMP 1 on 11 October 2013;
·
Routine Water Quality Monitoring was conducted for CMP 1 on 3, 5, 8, 11, 13, 15, 17, 19, 21, 24, 26, 29 and 31 October
2013;
·
Water Column Profiling was undertaken on 24 October 2013; and,
·
Impact Water Quality Monitoring during Dredging
Operations was undertaken for SB CMP 2 three
times per week (i.e. 2, 4, 7, 10, 12, 14, 16, 18, 21, 23, 25, 28 and 30 October
2013) in this reporting month in accordance with the EM&A Manual.
1.4.1
No outstanding sampling remained for October 2013. Laboratory analyses of Pit Specific Sediment
Chemistry of SB CMP 1 conducted in September and October 2013 and laboratory analysis of Cumulative Impact Sediment
Chemistry Monitoring of CMP V undertaken in August 2013 are yet to be completed. Laboratory analyses of Suspended Solids (SS)
for Water Quality Monitoring during Dredging Operations of CMP 2 collected on 30 October 2013 was still in progress during the
preparation of this monthly report. A
summary of field activities conducted are presented in Annex A.
1.5.1
Brief discussion of the monitoring results of Pit
Specific Sediment Chemistry Monitoring conducted in August 2013 is presented in this 14th Monthly Report. Detailed discussion will be presented in the
corresponding Quarterly Report.
1.5.2
Pit Specific Sediment Chemistry of CMP Va – August 2013
1.5.3
Monitoring locations
for Pit Specific Sediment Chemistry for CMP Va are shown in Figure 1.1. A total of
six monitoring stations were sampled in August 2013. It is observed
that the variations of metal concentrations at Active Pit Stations NPDA were much larger (i.e. greater standard deviation) when
compared to other stations (Figures 1 and 2 of Annex B).
1.5.4
Cadmium, Chromium, Lead, Zinc, Mercury and Nickel complied with the Lower Chemical Exceedance Level (LCEL)
at all stations in August 2013 (Figures 1 and 2 of Annex B). Concentrations of Arsenic exceeded the LCEL
at Active Pit station NPDB, Pit Edge stations NEDA and NEDB and Near Pit station NNDA (Figures
1 of Annex B). Concentrations
of Copper and Silver exceeded LCEL at Active Pit station NPDA (Figures 1 and 2 of Annex B).
1.5.5
Whilst the
average concentration of Arsenic in the Earth’s crust is generally ~2mg/kg,
significantly higher Arsenic concentrations (median = 14 mg/kg) have been
recorded in Hong Kong’s onshore sediments ([7]). It is presumed that the
natural concentrations of Arsenic are similar in onshore and offshore sediments
([8]), and relatively high Arsenic levels may thus occur
throughout Hong Kong. Therefore, the exceedances of the LCEL for
Arsenic are unlikely to be caused by the disposal operations at CMP Va but
rather as a result of naturally occurring deposits.
1.5.6
In addition,
the Active Pit station NPDA is located within CMP Va which was receiving
contaminated mud during the reporting period.
As such, the exceedances of LCEL for Copper and Silver which were
recorded at the Active station NPDA only are not considered as indicating any
dispersal of contaminated mud from CMP Va.
1.5.7
Total Organic
Carbon (TOC) concentration was similar amongst all stations in August 2013 (Figure
3 of Annex B). Tributyltin (TBT)
concentration was found to be higher at Active Pit station NPDA (Figure
4 of Annex B) in August 2013.
1.5.8
Low Molecular
Weigh Polycyclic Aromatics Hydrocarbons (Low MW PAHs) concentrations at Active
station NPDA were recorded above the limit of reporting in August 2013. High Molecular Weight Polycyclic Aromatics
Hydrocarbons (High MW PAHs) concentrations at Active Pit stations NPDA and NPDB and
Pit-edge station NEPA were also detected above the limit of reporting in August
2013 (Figure 5 of Annex
B).
However, these detected concentrations of Low and High MW PAHs were
below LCELs.
1.5.9
Total
Dichloro-diphenyl-trichloroethane (DDT), 4,4’-Dichloro-diphenyl-dichloroethylene
(4,4’-DDE) and Total Polychlorinated Biphenyls (PCBs) were recorded below the
limit of reporting at all the stations in August 2013.
1.5.10
As explained in Section
1.5.6, Active Pit
stations NPDA and NPDB are located
within CMP Va which was receiving contaminated mud during the reporting
period. Therefore, the higher concentrations
of contaminants (including metals and organic contaminants) recorded at the two
stations only are not considered as indicating any dispersal of contaminated
mud from CMP Va. Nevertheless, detailed
analysis will be presented in the Quarterly Report to reveal any trend of increasing sediment contaminant
concentrations towards CMP Va.
1.5.11
Overall, there is
no evidence indicating any unacceptable environmental impacts to sediment
quality as a result of the contaminated mud disposal operations at CMP Va during
this monthly period.
1.6
Brief Discussion of the Monitoring Results for SB CMPs
1.6.1
Impact Water Quality Monitoring during Dredging Operations of CMP 2 – 2 to 28 October 2013
1.6.2
Monitoring data collected for CMP 2
from 2 to 28 October 2013 are presented in this monthly report.
Detailed discussion will be presented in the corresponding Quarterly
Report.
1.6.3
Impact Water Quality Monitoring during Dredging
Operations of CMP 2 (i.e. from 2 October
to 28 October 2013) was conducted three times per week for
a total of nine (9) sampling days. On
each survey day, sampling was conducted during both mid-ebb and mid-flood tides
at two Reference (Upstream) stations upstream and five Impact (Downstream)
stations downstream of the dredging operations at CMP 2. Monitoring was also conducted at five
Sensitive Receiver Stations (Ma Wan, Shum Shui Kok, Tai Mo To and Tai Ho
Bay). A total of twelve stations were
monitored and locations of the sampling stations are shown in Figure 1.2.
1.6.4
Monitoring results from 2 to 28October are presented in Table C1 of Annex C. Levels of DO, Turbidity and SS
generally complied with the Action and Limit Levels (see Table C2 of Annex C for details) set in the Baseline Monitoring Report (), except for the following occasions of exceedances shown in Table 1.1 below.
Table 1.1 Details of exceedances recorded at SB
CMP 2 in October 2013
Date
|
Tide
|
Parameter
|
Station
|
Type
|
4
October 2013
|
Mid-Ebb
|
Turbidity
|
WSR46
|
Limit
|
|
|
SS
|
WSR46
|
Action
|
|
Mid-Flood
|
Turbidity
|
DS3
|
Action
|
|
|
SS
|
DS2
|
Action
|
|
|
SS
|
DS3
|
Action
|
7
October 2013
|
Mid-Ebb
|
Turbidity
|
DS1
|
Limit
|
|
|
Turbidity
|
DS2
|
Action
|
|
|
Turbidity
|
DS3
|
Limit
|
|
|
Turbidity
|
DS4
|
Limit
|
|
|
Turbidity
|
DS5
|
Limit
|
|
|
SS
|
DS1
|
Limit
|
|
|
SS
|
DS3
|
Action
|
|
|
SS
|
DS4
|
Action
|
|
|
SS
|
DS5
|
Action
|
|
Mid-Flood
|
Turbidity
|
DS1
|
Limit
|
|
|
SS
|
DS1
|
Limit
|
|
|
SS
|
WSR46
|
Action
|
10
October 2013
|
Mid-Ebb
|
Turbidity
|
DS1
|
Action
|
|
Mid-Flood
|
Turbidity
|
DS1
|
Limit
|
|
|
Turbidity
|
DS2
|
Action
|
|
|
SS
|
DS1
|
Limit
|
18
October 2013
|
Mid-Ebb
|
SS
|
DS1
|
Action
|
|
Mid-Flood
|
Turbidity
|
WSR46
|
Action
|
|
|
SS
|
WSR45C
|
Action
|
|
|
SS
|
WSR46
|
Action
|
21
October 2013
|
Mid-Flood
|
SS
|
DS1
|
Action
|
23
October 2013
|
Mid-Flood
|
Turbidity
|
DS1
|
Limit
|
|
|
SS
|
DS1
|
Action
|
|
|
SS
|
DS4
|
DS4
|
25
October 2013
|
Mid-Flood
|
Turbidity
|
DS1
|
Limit
|
|
|
SS
|
DS1
|
Limit
|
|
|
SS
|
DS2
|
Action
|
|
|
SS
|
DS3
|
Action
|
28
October 2013
|
Mid-Flood
|
Turbidity
|
DS1
|
Limit
|
|
|
SS
|
DS1
|
Limit
|
|
|
SS
|
DS3
|
Action
|
1.6.5
It should be noted that the
exceedances on 4 (mid-ebb and mid-flood tides) and 18 October 2013 (mid-flood
tide) were recorded at stations which are located further away from the works area
when compared to station DS1 at which the levels of SS, Turbidity and DO did
not exceed the Action and Limit Levels during the same tidal period on the same
day. As such, these recorded exceedances
are not likely to be caused by the dredging works at CMP 2.
1.6.6
Linear Regression was conducted to determine any significant spatial trend of Turbidity and SS levels recorded at stations DS1 to DS5 on 7 October
2013. Results of the statistical analysis did not indicate any significant spatial
trend of increasing Turbidity and SS levels with proximity to the dredging
operations (i.e. r2 value < 0.6).
The statistical analysis was also
performed for SS levels at stations DS1 to DS5 recorded on 25 October 2013
(mid-flood). Although a significant spatial trend was observed, the exceedances of
Action and Limit Levels were only recorded within a limited range at Impact
stations DS1, DS2 and DS3 which are within ~1 km distance downstream from the
dredging operation and exceedances were not recorded at any WSR stations. In addition, the spatial trend was only recorded
on one tide within only one monitoring day.
As such, there did not appear to be any evidence of unacceptable water
quality impact as a result of the dredging operations at the CMP.
1.6.7
Exceedances at DS1 and other
stations were also detected on 10, 18 (mid-ebb), 21 (mid-flood), 23
(mid-flood), 25 (mid-flood) and 28 October 2013 (mid-flood). However, these exceedances did not indicate
any trend of increasing SS or Turbidity levels toward the dredging operations. Instead, high levels of Turbidity and SS and
low levels of DO were occasionally recorded during baseline monitoring which
are considered to be sporadic events and characteristic of water quality in
this area of Hong Kong. Therefore, the Action and Limit Level
exceedances may be caused by natural background variation in water quality of
the area.
1.6.8
Overall, the results indicated that
the dredging operations at CMP 2 did not appear to cause any unacceptable
deterioration in water quality during this reporting period. Therefore, no further mitigation measures,
except for those recommended in the Environmental Permit (EP-427/2011/A), are considered necessary for the dredging operations.
1.6.9
Routine Water Quality Monitoring for SB CMP 1 – October 2013
1.6.10
The results
for the Routine Water Quality Monitoring conducted on 3, 5, 8, 11, 13 and 15
October 2013 in the wet season have been assessed for compliance with the Water
Quality Objectives (WQOs) set by Environmental
Protection Department (EPD). This consists of
a review of the EPD routine water quality monitoring data for the wet season
period (April to October) of 2002-2011 from stations in the Northwestern Water
Control Zone, where the CMPs are located.
For Salinity, the average value obtained from the Upstream Station was
used for the basis as the WQO. In-situ monitoring and laboratory results
are shown in Tables C3 and C4 of Annex C, with
graphical presentation provided in Annex B. Locations of
monitoring stations were presented in Figure 1.3 and 1.4.
In-situ
Measurements
1.6.11
Analysis of
results for 3, 5,
8, 11, 13 and 15 October 2013
indicated that for all the stations (Impact, Intermediate, Reference and Ma
Wan), levels of pH, DO and Salinity complied with the WQOs (Annex B). All in-situ water quality measurements showed
relatively minor variations amongst Impact, Intermediate and Reference stations
(Annex B).
1.6.12
Levels of
Turbidity within the reporting month generally complied with the Action and
Limit Levels set in the EM&A Manual ()
(Figures
10, 20, 30, 40, 50 and 60 of Annex B). Variation
of Turbidity amongst all the stations was observed throughout the monitoring
period.
Laboratory
Measurements
1.6.13
Data interpretation on monthly average concentrations of metals and nutrients will
be presented when monitoring data are made available upon completion of laboratory
analysis. Graphical presentations of
monitoring results on individual monitoring days from 3 to 15 October 2013 are
presented in Annex B.
1.6.14
Exceedances of
Suspended Solids (SS) WQO (12.2 mg/L for wet season) were occasionally recorded
(Figure 15,
25, 35, 45, 55 and 65 of Annex B). The exceedances of
WQO were recorded at Reference stations, Impact stations and other Water
Sensitive Receiver stations on the same monitoring day (3, 5, 8, and 15 October
2013). The reference stations are
located with a sufficient distance from the mud pits and considered unlikely to
be affected disposal works. In addition,
the SS levels at Impact stations were recorded lower than those at Reference or
Intermediate stations. Hence, it is
considered that the exceedances of WQO are unlikely to be caused by mud
disposal operations. In addition, high levels of SS were occasionally recorded during baseline
monitoring which are considered to be sporadic events and characteristic of
water quality in this area of Hong Kong. Concentrations
of SS complied with the Action and Limit Levels at all stations during the
reporting month.
1.6.15
Overall, the
results indicated that the disposal operation at CMP 1 did not appear to cause
any unacceptable deterioration in water quality during this reporting period.
1.6.16
Water Column Profiling for CMP 1 – October 2013
In-situ
Measurements
1.6.17
Water Column Profiling was
undertaken at a total of two sampling stations (Upstream and Downstream
stations) in October 2013. The water quality monitoring results for October 2013
have been assessed for compliance with the Water Quality Objectives (WQOs) set
by Environmental Protection Department (EPD). This consists of a review of the EPD routine water quality monitoring
data for the wet season period (April to October) of 2002-2011 from stations in
the Northwestern Water Control Zone, where the CMPs are located. For Salinity, the average value obtained from
the Upstream station was used for the basis as the WQO. Graphical presentation of the monitoring
results is provided in Annex
B.
1.6.18
Analyses of results for October
2013 indicated that levels of Salinity, pH and DO complied with the WQOs at
both Upstream and Downstream stations (Figures 66-68 of Annex B). DO and Turbidity complied
with the Action and Limit Levels set in the EM&A Manual ().
Laboratory
Measurements for Suspended Solids (SS)
1.6.19
Analyses of data obtained in October
2013 indicated that the SS levels at Downstream and Upstream stations exceeded
the WQO (Figure 69 of Annex
B) but the SS levels at Downstream stations are
significantly smaller than those at Upstream stations indicating by statistical
analysis. In addition, SS levels at all
stations complied with the Action and Limit Levels set in the EM&A
Manual.
1.6.20
Overall, the results indicated that
the mud disposal operation at CMP 1 did not appear to cause any deterioration
in water quality during this reporting period.
1.7
Activities Scheduled for the Next Month
1.7.1
Pit Specific Sediment Chemistry, Routine Water Quality Monitoring and Water Column Profiling for CMP 1
as well as Impact Water Quality Monitoring during Dredging Operations for CMP 2 will be conducted in the next monthly period of November 2013.
1.7.2
No monitoring activities will be
conducted for CMP IV and CMP V in the next monthly period of November 2013.
1.7.3
The sampling schedule is presented
in Annex A.
1.8.1
A summary of the Study programme is
presented in Annex D.