Agreement
No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits at the South of The Brothers and at East
Sha Chau (2012-2017) - Investigation
13TH MONTHLY PROGRESS REPORT FOR SEPTEMBER 2013
1.1.1
Since early 1990s, contaminated
sediment ([1])
arising from various construction works (e.g. dredging and reclamation
projects) in Hong Kong has been disposed of at
a series of seabed pits at East of Sha Chau (ESC). In late 2008, a review indicated that the
existing and planned facilities at ESC would not be able to meet the disposal
demand after 2012. In order to meet this
demand, the Hong Kong Special Administrative Region Government (HKSARG) decided
to implement a new contained aquatic disposal (CAD) ([2]) facility at the
South of The Brothers (SB CMPs) which had been under consideration for a number
of years.
1.1.2
The environmental acceptability of the
construction and operation of the Project had been confirmed by findings of the
associated Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE
12/2002(EP) ([3]).
The Director of Environmental Protection (DEP) approved this EIA report
under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO)
in September 2005 (EIA Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA
recommendation, prior to commencement of construction works for the SB CMPs, the
Civil Engineering and Development Department (CEDD) undertook a detailed review
and update of the EIA findings for the SB site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had been
predicted to be environmentally acceptable.
1.1.4
Environmental Permits (EPs) (EP-312/2008/A
and EP-427/2011A)
were issued by the Environmental Protection Department (EPD) to the CEDD, the Permit
Holder, on 28 November 2008 for East of Sha Chau (ESC) CMP V and on 23 December
2011 for SB CMPs, respectively. Under
the requirements of the EPs, an Environmental Monitoring and
Audit (EM&A) programme as set out in the EM&A Manuals ()
() is
required to be implemented for the CMPs.
1.1.5
The present EM&A programme undertaken under Agreement
No. CE 23/2012 (EP) covers the dredging, disposal and capping operations of the
SB CMPs as well as CMPs at East of Sha Chau (ESC). In September 2013, the following works were
being undertaken at the CMPs:
·
Capping was being undertaken at CMP IVc;
·
Disposal of contaminated mud was taking place at SB
CMP 1; and
·
Dredging operations were taking place at SB CMP 2.
1.2.1
This Monthly Progress Report covers
the EM&A activities for the reporting month of September 2013.
1.3
Details of Sampling and Laboratory Testing Activities
1.3.1
No
monitoring activities were undertaken for CMP IV and V in the monitoring month
of September 2013.
1.3.2
The following
monitoring activities have been undertaken for SB CMPs in September 2013:
·
Pit Specific Sediment Chemistry was
conducted for SB CMP 1 on 26 September 2013
·
Water Column Profiling was scheduled to be
undertaken on 17 September 2013. However,
there was no dumping activity at CMP 1 while the monitoring team was
on-site. As such, in-situ measurements
and water sampling were not undertaken for Water Column Profiling in September
2013; and
·
Impact Water Quality Monitoring during Dredging Operations was undertaken for SB CMP 2 three times per week (i.e. 2, 4, 6, 9, 11,
13, 16, 18, 21, 25, 27, and 30 September 2013) in this reporting month in
accordance with the EM&A Manual.
1.4.1
No
outstanding sampling remained for September 2013. Laboratory analyses of Pit Specific Sediment
Chemistry of SB CMP 1 conducted in September 2013 are yet to be completed. A summary of field activities conducted are
presented in Annex A.
1.5.1
Pit Specific
Sediment Chemistry Monitoring and Cumulative Impact Sediment Chemistry
Monitoring for CMP Va are not conducted in September 2013 and the laboratory
analysis of the monitoring activities undertaken in August 2013 is yet to be
completed during the preparation of this monthly report. Hence, brief discussion of the monitoring
results is not presented in this 13th Monthly Report. Detailed discussion will be presented in the
corresponding Quarterly Report.
1.6.1
Monitoring
data collected for CMP 2 from 2 September to 30 September 2013 are presented in
this monthly report. Detailed discussion
will be presented in the corresponding Quarterly Report.
1.6.2
Impact Water Quality Monitoring during Dredging
Operations of CMP 2 – 2 September to 30 September 2013
1.6.3
Impact Water
Quality Monitoring during Dredging Operations of CMP 2 (i.e. from 2 September
to 30 September 2013) was conducted three times per week for a total of nine
(9) sampling days. On each survey day,
sampling was conducted during both mid-ebb and mid-flood tides at two Reference
(Upstream) stations upstream and five Impact (Downstream) stations downstream
of the dredging operations at CMP 2.
Monitoring was also conducted at five Sensitive Receiver Stations (Ma
Wan, Shum Shui Kok, Tai Mo To and Tai Ho Bay).
A total of twelve stations were monitored and locations of the sampling
stations are shown in Figure
1.1.
1.6.4
Monitoring
results from 2 September to 30 September are presented in Table B1 of Annex B. Sampling at THB2 was cancelled during mid-ebb
tide on 4 September 2013 due to adverse weather. Sampling at THB2 was also cancelled during
both mid-ebb and mid-flood tides on 21 September 2013 since severe Typhoon
Usagi was approaching. Levels of DO,
Turbidity and SS generally complied with the Action and Limit Levels (see Table B2 of Annex B for
details) set in the Baseline Monitoring Report ([7]),
except for the following occasions of exceedances shown in Table 1.1 below.
Table 1.1 Details of exceedances recorded at SB
CMP 2 in September 2013
Date
|
Tide
|
Parameter
|
Station
|
Type
|
2 September 2013
|
Mid-Ebb
|
Bottom DO
|
WSR45C
|
Action
|
4 September 2013
|
Mid-Flood
|
Turbidity
|
WSR46
|
Limit
|
6 September 2013
|
Mid-Ebb
|
Turbidity
|
WSR46
|
Limit
|
|
Mid-Ebb
|
SS
|
WSR46
|
Action
|
|
Mid-Flood
|
Turbidity
|
DS1
|
Limit
|
|
Mid-Flood
|
SS
|
DS1
|
Limit
|
|
Mid-Flood
|
SS
|
WSR46
|
Action
|
18 September 2013
|
Mid-Ebb
|
Turbidity
|
WSR46
|
Action
|
|
Mid-Flood
|
SS
|
WSR45C
|
Action
|
21 September 2013
|
Mid-Flood
|
Turbidity
|
WSR46
|
Limit
|
|
Mid-Flood
|
SS
|
WSR46
|
Action
|
25 September 2013
|
Mid-Ebb
|
Turbidity
|
DS2
|
Limit
|
|
Mid-Ebb
|
SS
|
DS2
|
Limit
|
27 September 2013
|
Mid-Flood
|
SS
|
DS2
|
Action
|
1.6.5
It
should be noted that all exceedances except those on 6 September 2013 were
recorded at stations which are located further away from the works area when compared
to station DS1 at which the levels of SS, Turbidity and DO (Surface and
Mid-depth) did not exceed the Action and Limit Levels during the same tidal
period on the same day. As such, these
recorded exceedances are not likely to be caused by the dredging works at CMP
2.
1.6.6
On
6 September 2013, though exceedances of Action and Limit Levels were recorded
at stations WSR46 and DS1, there did not appear to be any trend of increasing
SS or Turbidity levels toward the dredging operations. Instead, high levels of Turbidity and SS and
low levels of DO were occasionally recorded during baseline monitoring which
are considered to be sporadic events and characteristic of water quality in
this area of Hong Kong. Therefore, the Action and Limit Level
exceedances may be caused by natural background variation in water quality of
the area.
1.6.7
Overall,
the results indicated that the dredging operations at CMP 2 did not appear
to cause any unacceptable deterioration in water quality during this reporting
period. Therefore, no further mitigation
measures, except for those recommended in the Environmental Permit (EP-427/2011/A),
are considered necessary for the dredging operations.
1.7.1
Pit Specific
Sediment Chemistry, Routine Water Quality Monitoring and Water Column Profiling
for CMP 1 as well as Impact Water Quality Monitoring during Dredging Operations
for CMP 2 will be conducted in the next monthly period of October 2013.
1.7.2
No
monitoring activities will be conducted for CMP IV and CMP V in the next
monthly period of October 2013.
1.7.3
The
sampling schedule is presented in Annex A.
1.8.1
A
summary of the Study programme is presented in Annex C.