Agreement No. CE 4/2009 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pit at Sha Chau (2009-2013) - Investigation

 

28th MONTHLY PROGRESS REPORT FOR CONTAMINATED MUD PITS AT SHA CHAU October 2011

 

1.1                                      Background

Since 1992, the East of Sha Chau area has been the site of a series of dredged contaminated mud pits (CMPs) designed to provide confined marine disposal capacity for contaminated mud arising from the HKSAR’s dredging and reclamation projects.  CMP IVc is presently in operation for backfilling by contaminated mud and is anticipated to reach its capacity in 2011.  A series of four newly constructed seabed pits at the East of Sha Chau area, CMP Va-d, will be provided for the disposal of contaminated mud after CMP IVc is full.  Dredging operations were completed for the construction of CMP Va-b and are now taking place to construct CMP Vc.  The environmental monitoring and audit (EM&A) programme for the CMPs at the East of Sha Chau area presently covers disposal and capping operations at CMP IV and dredging operations at CMP Vc.

1.2                                      Reporting Period

This Monthly Progress Report covers the monitoring period of October 2011.

1.3                                      Details of Sampling and Laboratory Testing Activities

After the Typhoon Nesat visited Hong Kong which led to the issue of Typical Cyclone Warning Signal No. 8 on 29 September 2011, sediment sampling was undertaken for the Post-storm Monitoring of CMP IVc on 4 October 2011.

For CMP V, sampling for Impact Water Quality Monitoring during Dredging Operations was conducted on 18 October 2011.  A summary of field activities are presented in Annex A.

A summary of monitoring data submitted by the Contractor in this reporting month is presented in Table 1.1. 

Table 1.1         Summary of monitoring data submitted by the Contractor during the reporting month

Key Task

Monitoring Component

Results Received from the Contractor

CMP IV

 

 

Demersal Trawling

Marine Biota

11, 12 August 2011 sampling: 20 October 2011

CMP V

 

 

Impact Monitoring during Dredging Operations

Water Quality

September 2011 sampling: 20 October 2011

 

 

 

1.4                                      Details of Outstanding Sampling and / or Analysis

No outstanding sampling and laboratory analysis remained from October 2011. 

1.5                                      Brief Discussion of the Monitoring Results

Results of Impact Water Quality Monitoring during Dredging Operations of CMP V for October 2011 are presented for CMP V.  Detailed results will be discussed in the 10th Quarterly Report.

 

1.5.1                                CMP V

Impact Water Quality Monitoring during Dredging Operations of CMP V – October 2011

Impact Water Quality Monitoring during Dredging Operations of CMP V was conducted on 18 October 2011.  On the survey day, sampling was conducted during both mid-ebb and mid-flood tides at two Reference (Upstream) stations upstream and five Impact (Downstream) stations downstream of the dredging operations at CMP V.  Monitoring was also conducted at the Ma Wan station.  At each station, in-situ measurements of water quality parameters as well as water samples were taken from three depths in the water column (ie surface: 1 m below sea surface, mid-depth and bottom: 1 m above the seabed).

Monitoring results are presented in Table B1 of Annex B.  Levels of Dissolved Oxygen (DO), Turbidity and Total Suspended Solids (TSS) generally complied with the Action and Limit Levels set in the Baseline Monitoring Report ([1]).  Levels of TSS and Turbidity exceeded the Action and Limit Levels, respectively, in the downstream station DS1 during the mid-flood tide.  Station DS1 is located on the edge of the works area of CMP Vc and the compliance of Action and Limit Levels at other downstream stations outside the works area (ie DS2-4) would indicate that there is no evidence of any unacceptable adverse water quality impacts outside the dredging works area of CMP Vc.  In addition, level of TSS at upstream station US2, which is approximately 500 m from the works area and unlikely to be affected by the dredging works, was slightly higher than station DS1 during the mid-flood tide.  Similar TSS levels between the two stations would indicate that the high TSS levels are more likely to be caused by natural background fluctuations in water quality which affected both upstream and downstream area rather than indicating any adverse water quality impacts from the dredging operations. 

Overall, there appears to be no unacceptable water quality impacts causing by the dredging operations at CMP Vc and no additional measures are thus considered required.

1.6                                      Activities Scheduled for the Next Month

Impact Water Quality Monitoring during Dredging Operations will be undertaken for CMP V in November 2011.  No monitoring activities are scheduled for CMP IV in the next reporting month.

The sampling schedule is presented in Annex A.

1.7                                      Study Programme

A summary of the Study Programme is presented in Annex C.


 



([1])         ERM (2009)  Baseline Monitoring Report.  Environmental Monitoring and Audit for Contaminated Mud Pit at Sha Chau (2009-2013) – Investigation. Agreement No. CE 4/2009(EP).  Submitted to EPD in September 2009.