Agreement No. CE 4/2009 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pit at Sha Chau (2009-2013) - Investigation

 

21st MONTHLY PROGRESS REPORT FOR CONTAMINATED MUD PITS AT SHA CHAU (for MARCH 2011)


June 2011

1.1                                      Background

Since 1992, the East of Sha Chau area has been the site of a series of dredged contaminated mud pits (CMPs) designed to provide confined marine disposal capacity for contaminated mud arising from the HKSAR’s dredging and reclamation projects.  CMP IVc is presently in operation for backfilling by contaminated mud and is anticipated to reach its capacity in 2011.  A series of four newly constructed seabed pits at the East of Sha Chau area, CMP Va-d, will be provided for the disposal of contaminated mud after CMP IVc is full.  Dredging operations were completed for the construction of CMP Va and are now taking place to construct CMP Vb.  The environmental monitoring and audit (EM&A) programme for the CMPs at the East of Sha Chau area presently covers disposal and capping operations at CMP IV and dredging operations at CMP Vb.

1.2                                      Reporting Period

This Monthly Progress Report covers the monitoring period of March 2011.

1.3                                      Details of Sampling and Laboratory Testing Activities

No field sampling activities were scheduled for CMP IVc in this monthly period.  For CMP V, sampling for Impact Monitoring during Dredging Operations was conducted on 8 March 2011.  A summary of field activities are presented in Annex A.

A summary of laboratory analysis results submitted by the Contractor in this reporting month is presented on Table 1.1. 


Table 1.1        Summary of laboratory analysis results submitted by the Contractor during the reporting month

Key Task

Monitoring Component

Results Received from the Contractor

CMP IV

 

 

Demersal Trawling

Marine Biota

February 2011:

15 March 2011

CMP V

 

 

Impact Monitoring during Dredging Operations

Water Quality

March 2011:

15 March 2011

1.4                                      Details of Outstanding Sampling and / or Analysis

No outstanding sampling and laboratory analysis remained from March 2011. 

1.5                                      Brief Discussion of the Monitoring Results

Results of Demersal Trawling for February 2011 are presented for CMP IV and results of Impact Monitoring during Dredging Operations for March 2011 are presented for CMP V.  Detailed results will be discussed in the 7th Quarterly Report.

1.5.1                                CMP IV

Demersal Trawling in February 2011

The final Demersal Trawling samples for the 2011 dry season were collected at CMP IV on 16 and 17 February 2011.  Mean number of faunal species was relatively consistent between Impact and Reference stations (Table 1.2) but Number of Individuals, Biomass, Catch-per-Uni-Effort (CPUE) and Yield-per-Unit-Effort (YPUE) were notable higher at Impact station INA (Table 1.3).  These results will be analysed in greater depth together with results from Demersal Trawling carried out in December 2010 and January 2011 in the 8th Quarterly Report.

Table 1.2        Mean Number of Faunal Species caught February 2011 Monitoring.

Date of Sampling

IMPACT STATIONS

REFERENCE STATIONS

 

INA       

INB

TNA

TNB       

TSA

TSB

Feb 2011

42.2

33.8

38.8

39.0

42.7

37.6

Table 1.3        Summary of CPUE and YPUE during February 2011 Monitoring

Station

Impact / Reference Area

No. of Individuals

Total

Biomass (g)

Mean CPUE#1

per Tow

Mean YPUE#2

per Tow (g)

INA

Impact

38,468

343,150

7,694

68,630

INB

Impact

10,839

93,246

2,168

18,649

TNA

Reference

3,560

26,635

712

5,327

TNB

Reference

8,442

53,418

1,688

10,684

TSA

Reference

13,498

202,931

2,700

40,586

TSB

Reference

23,759

197,487

4,752

39,497

#1   CPUE is calculated by dividing the number of individuals with the trawling time and number of nets (in hour and number of nets)

#2     YPUE is calculated by dividing the weight (g) of fish with trawling effort (in hour and number of nets)

1.5.2                                CMP V

Impact Water Quality Monitoring during Dredging Operations of CMP V – May 2011

Impact Water Quality Monitoring during Dredging Operations of CMP V was conducted on 24 May 2011.  On the survey day, sampling was conducted during both mid-ebb and mid-flood tides at two Reference (Upstream) stations upstream and five Impact (Downstream) stations downstream of the dredging operations at CMP V.  Monitoring was also conducted at the Ma Wan station.  At each station, in-situ measurements of water quality parameters as well as water samples were taken from three depths in the water column (ie surface: 1 m below sea surface, mid-depth and bottom: 1 m above the seabed).

Monitoring results are presented in Table B1 of Annex B.  Levels of Dissolved Oxygen (DO), Turbidity and Total Suspended Solids (TSS) complied with the Action and Limit Levels set in the Baseline Monitoring Report ([1]).  Therefore, there appears to be no evidence of any unacceptable adverse water quality impacts arising from the dredging operations of CMP V at ESC.

1.6                                      Activities Scheduled for the Next Month

Pit Specific Sediment Chemistry Monitoring for CMP IV and Impact Monitoring during Dredging Operations for CMP V are scheduled in the next monthly period of April 2011.  The sampling schedule is presented in Annex A.

1.7                                      Study Programme

A summary of the Study programme is presented in Annex C.


 



([1])     ERM (2009)  Baseline Monitoring Report.  Environmental Monitoring and Audit for Contaminated Mud Pit at Sha Chau (2009-2013) – Investigation. Agreement No. CE 4/2009(EP).  Submitted to EPD in September 2009.