Agreement No. CE 4/2009 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pit at Sha Chau
(2009-2013) - Investigation
21st MONTHLY PROGRESS REPORT FOR CONTAMINATED MUD PITS AT SHA
CHAU (for MARCH 2011)
June 2011
Since 1992, the East of Sha Chau area has been the site of a series of dredged
contaminated mud pits (CMPs) designed to provide
confined marine disposal capacity for contaminated mud arising from the HKSAR’s dredging and reclamation projects. CMP IVc is
presently in operation for backfilling b
This Monthly Progress Report
covers the monitoring period of March 2011.
No field sampling
activities were scheduled for CMP IVc in this monthly period. For CMP V, sampling for Impact Monitoring during Dredging Operations
was conducted on 8 March 2011. A summary of field activities are
presented in Annex A.
A summary of laboratory analysis results submitted by the Contractor in
this reporting month is presented on Table 1.1.
Table 1.1 Summary
of laboratory analysis results submitted by the Contractor during the reporting
month
Key
Task |
Monitoring
Component |
Results
Received from the Contractor |
CMP
IV |
|
|
Demersal Trawling |
Marine Biota |
February 2011: 15
March 2011 |
CMP
V |
|
|
Impact Monitoring during
Dredging Operations |
Water Quality |
March 2011: 15
March 2011 |
No outstanding sampling and laboratory analysis remained from March 2011.
Results of Demersal Trawling
for February 2011 are presented for CMP IV and results of Impact Monitoring during Dredging Operations for March 2011 are presented
for CMP V. Detailed results will be
discussed in the 7th Quarterly Report.
The final Demersal Trawling samples for the 2011 dry
season were collected at CMP IV on 16 and 17 February 2011. Mean number of faunal species was relativel
Table 1.2 Mean
Number of Faunal Species caught February 2011 Monitoring.
Date of Sampling |
IMPACT STATIONS |
REFERENCE STATIONS |
||||
|
INA |
INB |
TNA |
TNB |
TSA |
TSB |
Feb
2011 |
42.2 |
33.8 |
38.8 |
39.0 |
42.7 |
37.6 |
Table 1.3 Summary
of CPUE and YPUE during February 2011 Monitoring
Station |
Impact / Reference Area |
No. of Individuals |
Total Biomass (g) |
Mean CPUE#1 per Tow |
Mean YPUE#2 per Tow (g) |
INA |
Impact |
38,468 |
343,150 |
7,694 |
68,630 |
INB |
Impact |
10,839 |
93,246 |
2,168 |
18,649 |
TNA |
Reference |
3,560 |
26,635 |
712 |
5,327 |
TNB |
Reference |
8,442 |
53,418 |
1,688 |
10,684 |
TSA |
Reference |
13,498 |
202,931 |
2,700 |
40,586 |
TSB |
Reference |
23,759 |
197,487 |
4,752 |
39,497 |
#1 CPUE is calculated by dividing the number of
individuals with the trawling time and number of nets (in hour and number of
nets)
#2 YPUE is calculated by
dividing the weight (g) of fish with trawling effort (in hour and number of
nets)
Impact
Water Quality Monitoring during Dredging Operations of CMP V was conducted
on 24 May 2011. On the survey day, sampling was
conducted during both mid-ebb and mid-flood tides at two Reference (Upstream)
stations upstream and five Impact (Downstream) stations downstream of the
dredging operations at CMP V. Monitoring
was also conducted at the Ma Wan station.
At each station, in-situ
measurements of water quality parameters as well as water samples were taken
from three depths in the water column (ie surface: 1
m below sea surface, mid-depth and bottom: 1 m above the seabed).
Monitoring results are
presented in Table B1 of Annex B. Levels
of Dissolved Oxygen (DO), Turbidity and Total Suspended Solids (TSS) complied
with the Action and Limit Levels set in the Baseline
Monitoring Report ([1]). Therefore,
there appears to be no evidence of any unacceptable adverse water quality
impacts arising from the dredging operations of CMP V at ESC.
Pit Specific Sediment
Chemistry Monitoring for CMP IV and Impact Monitoring during Dredging Operations for CMP V are scheduled in the
next monthly period of April 2011. The
sampling schedule is presented in Annex A.
A summary of the Study programme is presented in Annex C.