Agreement No. CE 4/2009 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pit at Sha Chau
(2009-2013) - Investigation
24th MONTHLY PROGRESS REPORT FOR CONTAMINATED MUD PITS AT SHA
CHAU June 2011
Since 1992, the East of Sha Chau area has been the site of a series of dredged
contaminated mud pits (CMPs) designed to provide
confined marine disposal capacity for contaminated mud arising from the HKSAR’s dredging and reclamation projects. CMP IVc is
presently in operation for backfilling by contaminated mud and is anticipated
to reach its capacity in 2011. A series
of four newly constructed seabed pits at the East of Sha
Chau area, CMP Va-d, will
be provided for the disposal of contaminated mud after CMP IVc
is full. Dredging operations were
completed for the construction of CMP Va and are now
taking place to construct CMP Vb. The environmental
monitoring and audit (EM&A) programme for the CMPs
at the East of Sha Chau
area presently covers disposal and capping operations at CMP IV and dredging
operations at CMP Vb.
This Monthly Progress Report
covers the monitoring period of June 2011.
Water Column Profiling and Water Quality Monitoring during Capping
Operations were conducted for CMP IV on 21 June 2011 and an additional round of
Water Column Profiling was carried out on 29 June 2011 as disposal was not
taking place during the previous monitoring day. For
CMP V, sampling for Impact Water Quality
Monitoring during Dredging Operations was conducted on
24 June 2011. A summary of field activities are presented in Annex A.
A summary of laboratory analysis results submitted by the Contractor in
this reporting month is presented in Table
1.1.
Table 1.1 Summary
of laboratory analysis results submitted by the Contractor during the reporting
month
Key
Task |
Monitoring
Component |
Results Received from the Contractor |
CMP V |
|
|
Impact
Monitoring during Dredging Operations |
Water Quality |
May 2011 sampling: 17
June 2011 |
|
|
|
No outstanding sampling and laboratory analysis remained from June 2011.
Results of Impact Water Quality
Monitoring during Dredging Operations for June 2011 are presented for CMP
V. Detailed results will be discussed in
the 8th Quarterly Report.
Impact
Water Quality Monitoring during Dredging Operations of CMP V was conducted
on 24 June 2011. On the survey day, sampling was
conducted during both mid-ebb and mid-flood tides at two Reference (Upstream) stations
upstream and five Impact (Downstream) stations downstream of the dredging
operations at CMP V. Monitoring was also
conducted at the Ma Wan station. At each
station, in-situ measurements of
water quality parameters as well as water samples were taken from three depths
in the water column (ie surface: 1 m below sea
surface, mid-depth and bottom: 1 m above the seabed).
Monitoring results are
presented in Table B1 of Annex B. Levels
of Dissolved Oxygen (DO), Turbidity and Total Suspended Solids (TSS) complied
with the Action and Limit Levels set in the Baseline
Monitoring Report ([1]). Therefore,
there appears to be no evidence of any unacceptable adverse water quality
impacts arising from the dredging operations of CMP V at ESC.
The following monitoring activities will be conducted in the next monthly period of July
2011:
·
Water Column Profiling for CMP IV;
·
Demersal Trawling for CMP IV; and
·
Impact Water Quality Monitoring during Dredging
Operations for CMP V.
The sampling schedule is presented in Annex A.
A summary of the Study programme is presented in Annex C.