Agreement No. CE 4/2009 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pit at Sha Chau (2009-2013) - Investigation

8th MONTHLY PROGRESS REPORT FOR CONTAMINATED MUD PITS AT SHA CHAU - February 2010

1.1                                      Background

Since 1992, the East of Sha Chau area has been the site of a series of dredged contaminated mud pits (CMPs) designed to provide confined marine disposal capacity for contaminated mud arising from the HKSAR’s dredging and reclamation projects.  CMP IVc is presently in operation for backfilling by contaminated mud and is anticipated to reach its capacity in 2010.  A series of four newly constructed seabed pits at the East of Sha Chau area, CMP Va-d, will be provided for the disposal of contaminated mud after CMP IVc is full.  Dredging operations are now taking place to construct CMP Va.  The environmental monitoring and audit (EM&A) programme for the CMPs at the East of Sha Chau area presently covers disposal operations at CMP IVc and dredging operations at CMP V.

1.2                                      Reporting Period

This Monthly Progress Report covers the monitoring period of February 2010.

1.3                                      Details of Sampling and Laboratory Testing Activities

Field sampling activities conducted in this monthly period for CMP IVc are listed below:

·       Routine Water Quality Monitoring was conducted on 4 February 2010;

·       Water Column Profiling was conducted on 5 February 2010; and,

·       Demersal Trawling was conducted on 25 and 26 February 2010.

For CMP V, sampling for Impact Monitoring during Dredging Operations and Water Column Profiling were conducted on 3 and 4 February 2010, respectively.  A summary of field activities are presented in Annex A.

A summary of laboratory analysis results submitted by the Contractor in this reporting month is presented on Table 1.1. 


Table 1.1        Summary of laboratory analysis results submitted by the Contractor during the reporting month

Key Task

Monitoring Component

Results Received from the Contractor

CMP IV

 

 

Water Sampling and Chemical Analysis

a) Water Column Profiling

February’s sampling:

18 February 2010

 

b) Routine water quality monitoring

February’s in situ sampling:

18 February 2010

 

Sediment Sampling and Chemical Analysis

a) Pit Specific Sediment Chemistry

December’s sampling:

3 February 2010

 

b) Cumulative Impact Sediment Chemistry

December’s sampling:

3 February 2010

 

Benthic Recolonisation Study

 

December’s sampling:

19 January 2010

 

Demersal Trawling and Tissue Analysis

a) Tissue and Whole Body Analyses

July and August’s sampling:

3 February 2010

 

CMP V

 

 

Water Sampling and Chemical Analysis

a) Water Column Profiling

February’s sampling:

8 February 2010

 

b) Impact Monitoring during Dredging Operations

February’s sampling:

8 February 2010

1.4                                      Details of Outstanding Sampling and / or Analysis

No outstanding sampling remained from February 2010.  However, Water Quality Monitoring during Capping which was scheduled on 5 February 2010 was not conducted as no capping at CMP IV was scheduled to be carried out on this day.

1.5                                      Brief Discussion of the Monitoring Results

Results of Water Column Profiling and Routine Water Quality Monitoring for February 2010; Pit Specific Sediment Chemistry, Cumulative Impact Sediment Chemistry and Benthic Recolonisation for December 2009; and, Tissue and Whole Body Analyses for July and August 2009 are presented for CMP IV.  Monitoring results presented for CMP V include Water Column Profiling and Impact Monitoring during Dredging Operations for February 2010.  Detailed results will be discussed in the relevant Quarterly Reports.

1.5.1                                CMP IV

Water Column Profiling for CMP IV in February 2010

Results of Water Column Profiling for February 2010 show that levels of Salinity, pH and Dissolved Oxygen (DO) compiled with WQOs at both Upstream and Downstream stations (Figures 2 to 4 of Annex B).  Levels of Total Suspended Solids (TSS) complied with WQO at the Upstream station, however, exceedance of WQO was recorded at the Downstream station (Figure 1 of Annex B).  TSS data collected from the Routine Water Quality Monitoring should be examined further when available from the Contractor in order to assess any adverse impacts to the marine water quality caused by the CMP IV operations.

Routine Water Quality Monitoring for CMP IV during February 2010

In situ Measurements

Levels of pH, DO and Salinity complied with WQOs at all stations during Routine Water Quality Monitoring in February 2010 (Figures 5, 8 and 9 of Annex B).  All in situ water quality measurements showed relatively minor variations between Impact, Intermediate and Reference stations (Figures 5 to 10 of Annex B).

Pit Specific Sediment Chemistry for CMP IV during December 2009

Concentrations of metals were generally below the Lower Chemical Exceedance Level (LCEL) at all stations, with the exceptions being Arsenic, Copper, Silver and Zinc (Figures 11 and 12 of Annex B).  Concentrations of Arsenic exceeded LCEL at all Near Pit and Pit Edge stations (Figure 11 of Annex B).  Concentrations of Copper, Silver and Zinc exceeded LCEL at the Active Pit station NCA and remained below the criterion at all other stations (Figures 11 and 12 of Annex B).  No metal concentrations exceeded the Upper Chemical Exceedance Level (UCEL; Figures 11 and 12 of Annex B). 

Concentrations of Total DDT were higher at the Near Pit station CNA and Active Pit station NCA (Figure 13 of Annex B).  Concentrations of 4,4” DDE, Tributyltin (TBT) in both interstitial water and sediment samples were higher at the Active Pit station NCA (Figures 13-15 of Annex B).  Concentrations of Low Molecular Weight (LMW) Polyaromatic Hydrocarbons (PAHs), High Molecular Weight (HMW) PAHs, Total PAHs and Polychlorinated Biphenyls (PCBs) were below detection limits at all stations.  

Sediment concentrations of Total Organic Carbon (TOC) were slightly higher at the Active Pit station NCA relative to other stations (Figure 17 of Annex B) and all sediment samples were mainly composed of silt and clay materials (68 – 98 %; Figure 18 of Annex B).

Cumulative Impact Sediment Chemistry for December 2009

Concentrations of all metals, except Arsenic, were below the LCEL (Figures 19 and 20 of Annex B).  Concentrations of Arsenic in sediment samples from all stations were above the LCEL (Figure 19 of Annex B).  Overall, there were only minor differences in metal concentrations between stations (Figures 19 and 20 of Annex B).  All metal concentrations remained below UCEL (Figures 19 and 20 of Annex B). 

The concentration of Total DDT was higher at Mid Field stations and Near Field station RNA compared to all other stations (Figure 21 of Annex B).  Concentrations of 4,4” DDE were generally similar between stations with no obvious spatial trend (Figure 21 of Annex B).  Concentrations of TBT in sediment samples were highest at the Far Field station RFA (Figure 22 of Annex B), whereas TBT concentrations in all interstitial water samples were below the detection limit.  Similarly, concentrations were below detection limit at all stations for LMW PAHs, HMW PAHs, Total PAHs and PCBs.

Concentrations of TOC in sediments were relatively similar between stations (Figure 23 of Annex B) and sediments were mainly composed of silt and clay materials (31.8 – 56.4 %; Figure 24 of Annex B).

Benthic Macro-Infauna and Taxonomic Identification for CMP IV

A benthic survey was conducted at the Capped Mud Pit stations and at the Reference stations to the south of Sha Chau in December 2009.  A total of 179 individuals, belonging to six animal phyla were obtained from the monitoring stations.  Table 1.2 summarises the results of the benthic survey.

Table 1.2         Summary of Benthic Survey Results during December 2009 Monitoring

 

Area

Station

No. of individuals

(Total)

Biomass (g)

(Total)

Average No. of Individuals (Per Station)

Biomass (g) (Per Station)

Average Biomass per individual (mg)

Average Number of Genera

Capped Stations

 

 

 

 

 

 

 

CPA

3

9

0.08

3.00

0.03

0.01

1.67

CPB

3

16

41.57

5.30

13.96

2.60

3.67

CPC

3

14

0.22

4.67

0.07

0.02

1.67

(Total)

 

39

41.87

-

14.06

-

-

8.44

 

 

 

 

 

 

 

RBA

3

42

2.37

14.00

0.79

0.06

5.67

RBB

3

66

557.16

22.00

185.72

8.44

6.00

RBC

3

41

2.14

13.67

0.71

0.05

7.00

(Total)

 

149

561.67

-

187.22

-

-

Total

18

188

603.54

-

201.28

-

-

Total number of individuals, total biomass, average biomass per individual and average number of genera were generally lower at the Capped Pit stations than at the Reference stations.

Biota Tissues/Whole Body Contaminant Analysis for July and August 2009

Tissue Analysis

Graphical presentation for the tissue analysis of the demersal trawling samples which were collected in July and August 2009 is presented in Figures 25 to 38 of Annex B.  Analyses were only conducted on target species in which sufficient tissue samples were collected.  Generally, tissue concentrations of all metals remained below the relevant Maximum Permitted Concentrations (MPC) which are specified under the Food Adulteration (Metallic Contamination) Regulations (Cap. 132) of Hong Kong Law, except for Chromium concentrations in Gastropod tissues sampled at Impact station INA and Reference stations TNB and TSB (Figure 31).

Overall, concentrations of Inorganic Arsenic, Cadmium, Chromium, Copper, Lead, Mercury, Nickel, Silver and Zinc measured in tissues samples of target species were relatively similar between Impact and Reference stations (Figures 25, 27, 29, 31, 33, 35, 37, 39 and 41).  In addition, concentrations of organic contaminants measured in tissue samples of target species appeared similar between Impact and Reference stations (Figures 26, 28, 30, 32, 34, 36 and 38).  Statistical tests to detect any significant differences in tissue contaminant concentrations between stations will be presented in the relevant Quarterly Report.

Whole Body Analysis

Graphical presentation for the whole body analysis of demersal trawling samples which were collected in July and August 2009 is presented in Figures 39 to 48 of Annex B.  Analyses were only conducted on the target species with sufficient whole body samples available.  Concentrations of all metals measured in whole body samples remained below the relevant MPC standards.

Overall, concentrations of Inorganic Arsenic, Cadmium, Chromium, Copper, Lead, Mercury, Nickel, Silver and Zinc measured in whole body samples of target species were relatively similar between the Impact and Reference stations (Figures 39 to 48).  Concentrations of all organic contaminants measured in whole body samples of all target species also appeared similar between the Impact and Reference stations (Figure 22, 24, 26, 28 and 30).  

1.5.2                                CMP V

Water Column Profiling for CMP V during February 2010

Results of Water Column Profiling for February 2010 show that levels of Salinity, pH and DO compiled with WQOs at both Upstream and Downstream stations (Figures 50 to 52 of Annex B).  However, levels of TSS exceeded the WQO at both Upstream and Downstream stations (Figure 49 of Annex B). 

Impact Monitoring during Dredging Operations of CMP V – February 2010

Impact Monitoring during Dredging Operations of CMP V was conducted on 3 February 2010.  Sampling was conducted during both mid-ebb and mid-flood tides at two Reference (Upstream) stations upstream and five Impact (Downstream) stations downstream of the dredging operations at CMP V.  Monitoring was also conducted at the Ma Wan station.  At each station, in-situ measurements of water quality parameters and water samples were taken from three water depth levels of the water column which were surface (1m below sea surface), mid-depth and bottom (1m above the seabed).

Monitoring results are presented in Figures 53 to 56 of Annex B.  Levels of DO, depth-average Turbidity and TSS complied with the Action and Limit Levels set in the Baseline Monitoring Report ([1]) (Tables B1 and B2 of Annex B).  

1.6                                      Activities Scheduled for the Next Month

Impact Monitoring during Dredging Operations for CMP V is the only monitoring activity scheduled in the next monthly period of March 2010.  The sampling schedule is presented in Annex A.

1.7                                      Study Programme

A summary of the Study programme is presented in Annex C.



([1])         ERM (2009)  Baseline Monitoring Report.  Environmental Monitoring and Audit for Contaminated Mud Pit at Sha Chau (2009-2013) – Investigation. Agreement No. CE 4/2009(EP).  Submitted to EPD in September 2009.