Agreement No. CE 4/2009 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pit at Sha Chau (2009-2013) - Investigation

10th MONTHLY PROGRESS REPORT FOR CONTAMINATED MUD PITS AT SHA CHAU - April 2010

1.1                                      Background

Since 1992, the East of Sha Chau area has been the site of a series of dredged contaminated mud pits (CMPs) designed to provide confined marine disposal capacity for contaminated mud arising from the HKSAR’s dredging and reclamation projects.  CMP IVc is presently in operation for backfilling by contaminated mud and is anticipated to reach its capacity in 2010.  A series of four newly constructed seabed pits at the East of Sha Chau area, CMP Va-d, will be provided for the disposal of contaminated mud after CMP IVc is full.  Dredging operations are now taking place to construct CMP Va.  The environmental monitoring and audit (EM&A) programme for the CMPs at the East of Sha Chau area presently covers disposal operations at CMP IVc and dredging operations at CMP V.

1.2                                      Reporting Period

This Monthly Progress Report covers the monitoring period of April 2010.

1.3                                      Details of Sampling and Laboratory Testing Activities

For CMP IVc, sampling for Pit Specific Sediment Chemistry Monitoring was conducted on 21 April 2010.  For CMP V, sampling for Impact Monitoring during Dredging Operations was conducted on 20 April 2010.  A summary of field activities are presented in Annex A.

A summary of laboratory analysis results submitted by the Contractor in this reporting month is presented on Table 1.1. 


Table 1.1        Summary of laboratory analysis results submitted by the Contractor during the reporting month

Key Task

Monitoring Component

Results Received from the Contractor

CMP V

 

 

Water Sampling and Chemical Analysis

Impact Monitoring during Dredging Operations

April’s sampling:

20 April 2010

 

 

 

1.4                                      Details of Outstanding Sampling and / or Analysis

No outstanding sampling and laboratory analysis remained from April 2010. 

1.5                                      Brief Discussion of the Monitoring Results

Results of Impact Monitoring during Dredging Operations for April 2010 are presented for CMP V.  Detailed results will be discussed in the relevant Quarterly Reports.

1.5.1                                CMP V

Impact Monitoring during Dredging Operations of CMP V – April 2010

Impact Monitoring during Dredging Operations of CMP V was conducted on 20 April 2010.  Sampling was conducted during both mid-ebb and mid-flood tides at two Reference (Upstream) stations upstream and five Impact (Downstream) stations downstream of the dredging operations at CMP V.  Monitoring was also conducted at the Ma Wan station.  At each station, in-situ measurements of water quality parameters were taken as well as water samples from three depths in the water column (surface (1m below sea surface), mid-depth and bottom (1m above the seabed)).

Monitoring results are presented in Figures 1 to 4 of Annex B.  Levels of DO, depth-average Turbidity and TSS complied with the Action and Limit Levels set in the Baseline Monitoring Report ([1]) (Tables B1 and B2 of Annex B).  

1.6                                      Activities Scheduled for the Next Month

No monitoring activity will be conducted for CMP IVc.  Impact Monitoring during Dredging Operations for CMP V are scheduled in the next monthly period of May 2010.  The sampling schedule is presented in Annex A.

1.7                                      Study Programme

A summary of the Study programme is presented in Annex C.



([1])         ERM (2009)  Baseline Monitoring Report.  Environmental Monitoring and Audit for Contaminated Mud Pit at Sha Chau (2009-2013) – Investigation. Agreement No. CE 4/2009(EP).  Submitted to EPD in September 2009.