1.1 Purpose of the Manual
1.2 Review of EM&A Manual
1.3 Background to the EM&A Programme
1.4 Objectives of the EM&A Programme
1.5 The Scope of the EM&A Programme
1.6 Organisation and Structure of the EM&A
1.7 Structure of the EM&A Manual
2.1 Introduction
2.2 EM&A
2.3 Environmental Management Plan
(EMP)
3.1 Introduction
3.2 Monitoring Activities
3.3 Monitoring for Dredging Activities of CMP V
3.4 Monitoring for Backfilling Activities
3.5 Monitoring for Capping Activities
3.6 Sampling Procedure for Water Quality monitoring
3.7 QA/QC
4.1 Introduction
4.2 Objective
4.3 Hypotheses
4.4 Sampling Design
4.5 Statistical Treatment of Data
4.6 Use of Data
4.7 Sampling Procedure and Equipment
4.8 QA/QC
4.9 Data Quality Objectives
5.1 Introduction
5.2 Objective
5.3 Hypothesis
5.4 Sampling Design
5.5 Statistical Treatment of Data
5.6 Use of Data
5.7 Data Collection Parameters
5.8 Sampling Procedure and Equipment
5.9 QA/QC
6.1 Introduction
6.2 Objective
6.3 Hypothesis
6.4 Sampling Design
6.5 Statistical Treatment of Data
6.6 Use of Data
6.7 Data Collection Parameters
6.8 Sampling Procedure and Equipment
7 Human Health and Ecological
Risk Assessment
7.1 Introduction
7.2 Objective
7.3 Hypothesis
7.4 Sampling Design
7.5 Use of Data
8.1 Introduction
8.2 Objective
8.3 Hypothesis
8.4 Sampling Design
8.5 Statistical Treatment of Data
8.6 Use of Data
8.7 Laboratory Procedures
8.8 Benthic Macro-Infauna and Taxonomic Identification
9.1 Introduction
9.2 Sampling Design
10 Reporting
10.1 General
10.2 Reports
ANNEXES
Annex A Implementation Schedule for
CMP V
Annex B Complaints Proforma
Annex C Sampling Programme
This
Environmental Monitoring and Audit (EM&A) Manual (¡§the Manual¡¨) has been
prepared by ERM-Hong Kong, Limited
(ERM) on behalf of the Civil Engineering and Development Department
(CEDD) of the Hong Kong Special Administrative Region (HKSAR) Government.
The
purpose of the Manual is to provide information, guidance and instruction to
personnel charged with environmental duties and those responsible for
undertaking EM&A work during the construction and operation of Contaminated
Mud Pit V (CMP V) at East of Sha Chau (ESC). It provides systematic procedures for
monitoring and auditing of potential environmental impacts that may arise from
the works.
EM&A
works relating to CMP V have been prepared in accordance with the Environmental
Permit (EP) (EP-312/2008/A) (EP) for Disposal of Contaminated Sediment ¡V
Dredging, Management and Capping of Sediment Disposal Facility at Sha Chau
(hereafter referred as ¡§the Project¡¨) and the Technical Memorandum of the
Environmental Impact Assessment Process (EIAO TM).
The
EM&A Manual is an evolving document that should be updated to maintain its
relevance as the Project progresses to ensure the impacts predicted and the
recommended mitigation measures remain consistent and appropriate to the manner
in which the works are to be carried out at CMP V of ESC. This updated submission incorporates the
alternative monitoring stations for water quality (in Section 3), sediment quality (in Sections 4 and 9) and sediment toxicity (in Section 5)
due to the marine construction works of the Expansion
of Hong Kong International Airport into a Three-runway System. The alternative monitoring stations were
reported in the Proposal of
Alternative Monitoring Locations for the EM&A Activities ([1])
and were approved by the Environmental Protection Department (EPD) on 1
February 2017. In addition, this Updated EM&A Manual describes the
sampling design of benthic recolonisation study for
CMP V to verify the recolonisation of marine biota on
the capped pits at CMP V. The
latest EM&A programme for CMP V between April 2017 and March 2021 is also
presented in Annex C of this Updated EM&A Manual.
Further
reviews and subsequent updates of the EM&A Manual will be undertaken
whenever necessary to take into account the findings obtained during the Study
as the works progress and will be presented in separate documents.
i.
Dredging
of a series of seabed pits at CMP V within the proposed facility boundaries at
ESC (Figure 1.1);
ii.
Backfilling
each dredged pit at CMP V with contaminated mud that has been classified as
requiring Type 2 disposal in accordance with ETWB TCW No. 34/2002 ([2]);
and
iii.
Capping
each backfilled pit at CMP V with uncontaminated mud effectively isolating the
contaminated mud from the surrounding marine environment.
The
construction and operational impacts resulting from the implementation of CMP V
are specified in the EIA Report.
The EIA Report also specifies mitigation measures that need to be
implemented to ensure compliance with the required environmental criteria. These mitigation measures and their
implementation requirements are presented in the Implementation Schedule (Annex A). The EIA recommended that environmental
monitoring will be necessary to assess the effectiveness of measures
implemented to mitigate potential water quality, marine ecology and fisheries
impacts during the construction and operation of CMP V. Regular environmental auditing is also
recommended to ensure that potential impacts from other sources are adequately
addressed through the implementation of the mitigation measures defined in the
EIA Report.
An
EP (EP-312/2008) was issued by the EPD to the CEDD, the Permit Holder, on 9
September 2008 and varied on 28 November 2008 (EP-312/2008/A) for CMP V. Under the requirements of Condition 3 of the EP (EP-312/2008/A)
for CMP V, an EM&A programme as set out in the EM&A Manual is required
to be implemented. The current programme will assess the impacts resulting
from dredging, disposal and capping operations of CMP V.
The
objectives of the EM&A programme are as follows:
1. To
monitor and report on the environmental impacts of the dredging operations
associated with the construction of the disposal pits at CMP V.
2. To
monitor and report on the environmental impacts due to capping operations of
the exhausted pits at CMP V.
3. To
monitor and report on the environmental impacts of the disposal of contaminated
marine sediments in the active pits at CMP V, specifically to determine:
¡P
changes/trends caused by disposal activities in the
concentrations of contaminants in sediments adjacent to the pits;
¡P
changes/trends caused by disposal activities in the
toxicity of sediment adjacent to the pits;
¡P
changes/trends caused by disposal activities in the
concentrations of contaminants in tissues of demersal marine life adjacent to
and remote from the pits;
¡P
impacts on water quality and benthic ecology caused
by the disposal activities; and
¡P
the
risks to human health and dolphin of eating seafood taken in the marine area
around the active pits.
4. To
monitor and report on the environmental impacts of the disposal operation at
CMP V and specifically to determine whether the methods of disposal are
effective in minimising the risks of adverse environmental impacts.
5. To
monitor and report on the benthic recolonisation of
the capped pits at CMP V and specifically to determine the difference in
infauna between the capped pits and adjacent sites.
6. To
assess the impact of a major storm (Typhoon Signal No. 8 or above) on the
containment of any uncapped or partially capped pits at CMP V.
7. To
design and continually review the operation and monitoring programme and:
¡P
to make recommendations for changes to the operation
that will rectify any unacceptable environmental impacts; and
¡P
to
make recommendations for changes to the monitoring programme that will improve
the ability to cost effectively detect environmental changes caused by the
disposal activities.
8. To
establish numerical decision criteria for defining impacts for each monitoring
component.
9. To
provide supervision on the field works and laboratory works to be carried out
by contractors/laboratories.
The specific
objectives of each component are discussed in the relevant sections of this
EM&A Manual.
The
scope of this EM&A programme is to:
¡P
Establish
baseline water quality levels at specified locations prior to dredging
operations for the construction of CMP V at Sha Chau;
¡P
Implement
monitoring and inspection requirements for water quality monitoring programme
during dredging, backfilling and capping operations of CMP V;
¡P
Implement
monitoring and inspection requirements for sediment quality monitoring
programme during backfilling operations at CMP V;
¡P
Implement
monitoring and inspection requirements for sediment toxicity monitoring
programme during backfilling operations at CMP V;
¡P
Implement
monitoring and inspection requirements for the body burden (marine biota)
monitoring programme during backfilling operations at CMP V;
¡P
Liaise
with, and provide environmental advice (as requested or when otherwise
necessary) to site staff on the comprehension and consequences of the
environmental monitoring data;
¡P
Identify
and resolve environmental issues and other functions as they may arise from the
works;
¡P
Check
and quantify the Contractor's overall environmental performance, implementation
of Event and Action Plans (EAPs), and remedial actions taken to mitigate
adverse environmental effects as they may arise from the works;
¡P
Conduct
monthly reviews of monitored impact data as the basis for assessing compliance
with the defined criteria and to ensure that necessary mitigation measures are
identified and implemented, and to undertake additional ad hoc monitoring and auditing as required by special
circumstances;
¡P
Evaluate
and interpret all environmental monitoring data to provide an early indication
should any of the environmental control measures or practices fail to achieve
the acceptable standards, and to verify the environmental impacts predicted in
the EIA;
¡P
Manage
and liaise with other individuals or parties concerning other environmental
issues deemed to be relevant to the construction and operation process; and,
¡P
Conduct
regular site inspections of a formal or informal nature to assess:
-
the
level of the Contractor¡¦s general environmental awareness;
-
the
Contractor¡¦s implementation of the recommendations in the EIA;
-
the
Contractor¡¦s performance as measured by the EM&A;
-
the need for specific mitigation
measures to be implemented or the continued usage of those previously agreed;
-
to advise the site staff of any
identified potential environmental issues; and
-
submit
regular EM&A reports which summarise project monitoring and auditing data,
with full interpretation illustrating the acceptability or otherwise of any
environmental impacts and identification or assessment of the implementation
status of agreed mitigation measures.
CEDD will appoint an
Environmental Team (ET) to conduct the monitoring and auditing works and to
provide specialist advice on the undertaking and implementation of
environmental responsibilities.
The ET will have previous
relevant experience with managing similarly sized EM&A programmes and the
Environmental Team Leader (ET Leader) will be a recognised environmental
professional, preferably with a minimum of seven years relevant experience in
impact assessments and impact monitoring programmes, particularly with
reference to those to the marine environment and where possible related to
marine dredging / disposal activities.
To maintain strict control
of the EM&A process, CEDD will also appoint an Independent Auditor (IA) to
verify and validate the environmental performance of the Contractor and the ET.
The roles and
responsibilities of the various parties involved in the EM&A process are
further expanded in the following sections. The ET Leader will be responsible for,
and in charge of, the ET; and will be the person responsible for executing the
EM&A requirements.
Reporting to CEDD, the
Contractor will:
¡P
Work
within the scope of the construction contract and other tender conditions;
¡P
Provide
assistance to the ET in conducting the required environmental monitoring;
¡P
Participate
in the site inspections undertaken by the ET and / or IA, as required, and undertake
any corrective actions instructed by CEDD;
¡P
Provide
information/advice to the ET and IA regarding works activities which may
contribute, or be contributing to the generation of adverse environmental
conditions;
¡P
Implement
measures to reduce impact where Action and Limit levels are exceeded; and
¡P
Take
responsibility and strictly adhere to the guidelines of the EM&A programme
and complementary protocols developed by their project staff.
CEDD will:
¡P
Monitor
the Contractor's compliance with contract specifications, including the
effective implementation and operation of environmental mitigation measures and
other aspects of the EM&A programme;
¡P
Employ
Independent Auditor(s) to audit the results of the EM&A works carried out
by the ET;
¡P
Comply
with the agreed Event and Action Plan in the event of any exceedance; and
¡P
Instruct
the Contractor to follow the agreed protocols or those in the Contract
Specifications in the event of exceedances or complaints.
The duties of the ET and ET
Leader are to:
¡P
Monitor
the various environmental parameters as required by this or subsequent
revisions to the EM&A Manual;
¡P
Assess
the EM&A data and review the success of the EM&A programme determining
the adequacy of the mitigation measures implemented and the validity of the EIA
predictions as well as identify any adverse environmental impacts before they
arise;
¡P
Conduct
regular site inspections and to investigate and inspect the Contractor's equipment
and work methodologies with respect to pollution control and environmental
mitigation, monitor compliance with the environmental protection specifications
in the Contract, and to anticipate environmental issues that may require
mitigation before the problem arises;
¡P
Audit
the environmental monitoring data and report the status of the general site
environmental conditions and the implementation of mitigation measures
resulting from site inspections;
¡P
Review
Contractor¡¦s working programme and methodology, and comment as necessary;
¡P
Investigate
and evaluate complaints, and identify corrective measures;
¡P
Advice
to the Contractor on environmental improvement, awareness, enhancement matters,
etc, on site;
¡P
Report
on the environmental monitoring and audit results and the wider environmental
issues and conditions to the Contractor, CEDD and the EPD; and
¡P
Adhere
to the agreed protocols or those in the Contract Specifications in the event of
exceedances or complaints.
The ET will be led and
managed by the ET leader. The ET
leader will have relevant education, training, knowledge, experience and
professional qualifications subject to the approval of the Director of
Environmental Protection. Suitably
qualified staff will be included in the ET, and ET should not be in any way an
associated body of the Contractor.
¡P
Review
and audit the implementation of the EM&A programme and the overall level of
environmental performance being achieved;
¡P
Validate
and confirm the accuracy of monitoring results, monitoring equipment,
monitoring stations, monitoring procedures and locations of sensitive
receivers;
¡P
Audit
the EIA recommendations and requirements against the status of implementation
of environmental protection measures on site;
¡P
Adhere
to the procedures for carrying out complaint investigation;
¡P
Review,
when required, the effectiveness of environmental mitigation measures and
project environmental performance including the proposed corrective measures;
and
¡P
Report,
when required, the findings of audits and other environmental performance
reviews to CEDD, ET, EPD and the Contractor.
The
Independent Auditor will have relevant education, training, knowledge,
experience and professional qualifications subject to the approval of the
Director of Environmental Protection.
IA should not be in any way an associated body of the Contractor or the
ET.
The remainder of the Manual
is set out as follows:
¡P
Section 2 sets out the EM&A
general requirements;
¡P
Section
3 details
the methodologies, parameters to be tested and the requirements for the marine
water quality monitoring for the dredging, backfilling and capping operations
at the active pits;
¡P
Section
4 details
the methodologies, parameters to be tested and the requirements for sediment
quality monitoring for the backfilling activities at the active pits;
¡P
Section
5 details
the methodologies, parameters to be tested and the requirements for sediment
toxicity quality monitoring for the backfilling activities at the active pits;
¡P
Section
6 details
the methodologies, parameters to be tested and the requirements for marine
biota monitoring for the backfilling activities at the active pits;
¡P
Section 7 details the requirements
for Human Health and Dolphin Risk Assessment;
¡P
Section
8 details
the requirements for benthic re-colonisation assessment;
¡P
Section
9 details
the methodologies, parameters to be tested and the requirements for the
assessment of impacts due to major storms; and
¡P
Section 10 details the EM&A
reporting requirements.
In this section, the
general requirements of the EM&A programme are presented with reference to
the EIA Study findings that have formed the basis of the scope and content of
the programme.
Key environmental issues
associated with the construction and operation of the Project will be addressed
through monitoring and controls specified in the EM&A Manual. Water and sediment quality, marine
ecology and fisheries issues will be subjected to EM&A, the details of
which are outlined in Sections 3 to
9.
Action and Limit (A/L)
Levels are defined levels of impact recorded by the environmental monitoring
activities which represent levels at which a prescribed response is
required. This process by which these
levels should be quantitatively defined are presented in the relevant sections
of this manual and described in principle below:
¡P
Action Levels: beyond which there is a
clear indication of a deteriorating ambient environment for which appropriate
remedial actions are likely to be necessary to prevent environmental quality
from falling outside the Limit Levels,
which would be unacceptable; and
¡P
Limit Levels: statutory and/or agreed
contract limits stipulated in the relevant pollution control ordinances, Hong
Kong Planning Standards and Guidelines (HKPSG) or Environmental Quality Objectives established by the EPD. If these are exceeded, works should not
proceed without appropriate remedial action, including a critical review of
plant and working methods.
The
purpose of an Event and Action Plan (EAP) is to provide, in association with
the monitoring and audit activities, procedures for ensuring that if any
significant environmental incident (either accidental or through inadequate
implementation of mitigation measures on the part of the Contractor) does
occur, the cause will be quickly identified and remediated, and the risk of a
similar event recurring is reduced.
This also applies to the exceedances of A/L criteria to be identified in
the EM&A programme.
Enquiries, complaints and
requests for information can be expected from a wide range of individuals and
organisations including members of the public, Government departments, the press
and media and community groups.
All enquiries concerning
the environmental effects of the Project (CMP V), irrespective of how they are
received, will be reported to CEDD and directed to the ET Leader who will set
up procedures for handling, investigation and storage of such information. The following steps will then be
followed:
1)
The
ET Leader will notify CEDD of the nature of the enquiry.
2)
An
investigation will be initiated to determine the validity of the complaint and
to identify the source of the problem.
3)
The
ET Leader will undertake the following steps, as necessary:
¡P
investigate
and identify source of the problem;
¡P
if
considered necessary by CEDD undertake additional monitoring to verify the
existence and severity of the alleged complaint;
¡P
liaise
with EPD to identify remedial measures;
¡P
liaise
with CEDD and the Contractor to identify remedial measures;
¡P
implement
the agreed mitigation measures;
¡P
repeat
the monitoring to verify effectiveness of mitigation measures; and
¡P
repeat review procedures to identify further
possible areas of improvement if the repeat monitoring results continue to
substantiate the complaint.
4)
The
outcome of the investigation and the action taken will be documented on a
complaint proforma (Annex B). A
formal response to each complaint received will be prepared by the ET Leader
within a maximum of five working days and submitted to CEDD, in order to notify
the concerned person(s) that action has been taken.
5)
All
enquiries which trigger this process will be reported in the EM&A reports
which will include results of inspections undertaken by the ET Leader, and
details of the measures taken, and additional monitoring results (if deemed
necessary). It should be noted that
the receipt of complaint or enquiry will not be, in itself, a sufficient reason
to introduce additional mitigation measures.
In all cases the
complainant will be notified of the findings, and audit procedures will be put
in place to ensure that the problem does not recur.
Monthly, Quarterly and
Annual reports will be submitted to CEDD, EPD and AFCD and will be prepared by
the ET. The reports will be
prepared and submitted within a specified period. Additional details on reporting protocols
are presented in Section 10.
To ensure effective
implementation and reporting on compliance with the stated mitigation measures,
as well as the monitoring and auditing requirements and remedial actions
defined in the EIA, an appropriate contractual and supervisory framework needs
to be established. The basis of the
framework within which implementation should be managed overall is through the
preparation of EMPs by the Contractor(s).
An EMP is similar in nature
to a quality plan and provides details of the means by which the Contractor
(and all subcontractors working to the Contractor) will implement the
recommended mitigation measures and achieve the environmental performance
standards defined in Hong Kong environmental legislation, the contract and in
the EIA documentation. The primary
reason for adopting the EMP approach is to make the Contractor aware of his
environmental responsibilities and to be pro-active about the commitment to
achieve the standards specified, rather than relying on the EM&A programme.
The EMP also provides
opportunities for the Contractor to draw upon the strength of other
institutional processes such as ISO 9000/14000 to ensure that the achievement
of the required standards and fulfilment of commitments are documented.
The
contractual requirement for an EMP would generally comprise appropriate
extracts from (and references to) the EIA Report and EM&A Manual, and
include such typical elements as the relevant statutory environmental
standards, general environmental control clauses and specific environmental
management clauses, as well as an outline of the scope and content of the
EMP. In drafting the documentation,
due consideration should be given to the predictive nature of the EIA process
and the consequent need to manage and accommodate the actual impacts arising
from the construction process. In
particular, the Contractor must be placed under a clear obligation to identify
and control any implications arising from changes to the working methods
assumed in the EIA, or to the progress rates and other estimates made during
the preliminary design phase.
This
Section provides details of the water quality monitoring to be undertaken during
the construction and operation of the active
pits. Water quality
modelling carried out for the EIA indicates that the potential water quality
impacts associated with the dredging, backfilling and capping works at CMP V
will be within acceptable levels and no adverse water quality impacts are
expected. However, the monitoring
programme is designed to verify the predictions of the EIA and ensure
compliance with the WQOs.
Water
quality monitoring for the Project can be divided into the following stages:
¡P
Dredging
Activities for CMP V;
¡P
Backfilling
Activities for CMP V; and
¡P
Capping
Activities for CMP V.
Each
of these is discussed in turn below.
Dredging
activities for CMP Va to Vd were completed in mid-2013. Maintenance dredging may be conducted at
CMP Vb and CMP Vc prior to
the commencement of disposal at these two sub-pits as and when necessary. Water quality monitoring will be
conducted during dredging at these sub-pits for CMP V at Sha Chau. Baseline water quality monitoring was
conducted between 28 July and 23 August 2009 prior to the commencement of
marine dredging works for CMP V.
The Baseline Monitoring Report ([3]) was submitted to EPD in
September 2009 to present the baseline monitoring requirements, methodology and
results. Readers should refer to
the Baseline Monitoring Report for details of the baseline water quality
monitoring.
Impact monitoring for the dredging
activities to form CMP V will be conducted at mobile stations around the
dredging area. Currently the impact
monitoring is conducted for three times per week and the monitoring frequency
may be revised upon agreement with the EPD. Monitoring will be carried out during
both mid-flood and mid-ebb tides on each monitoring day. The location of the mobile stations is
dependent on the location of the dredging activities. These mobile stations will be located at
an appropriate distance between each other along the up-current and
down-current transect for the dredging area. The following methodology will be
adopted to determine the precise location of the mobile stations on each sampling occasion:
¡P
Contact the CEDD barge one day before the survey day for every sampling
occasion to determine the dredging schedule for that particular survey day and
to determine the likely location of dredging at the proposed time of sampling;
¡P
Determine current direction at
mid-depth at one station upstream and one station downstream of the new
facility during both mid-flood and mid-ebb tide;
¡P
Determine a suitable location for the station transect (the first
down-current station will be located on the down current edge, and first
up-current station will be located on the up-current edge, of the CMP V
according to the current direction and the position of dredging at the time of
sampling); and,
¡P Collect
samples from the
stations located on a transect running up-current and
down-current of the dredging area.
There will be two stations located
up-current and five stations down-current of CMP V on the
transect. A 500 m separation
distance will be adopted between adjacent stations except between adjacent
upstream and downstream stations which are located on the pit edge. In addition, water samples will be
collected from the station MW1 as shown in Figure 3.1. Locations of upstream and downstream
stations are illustrated in Figure 3.1 based on
assumed current direction and dredging position during monitoring.
Each station will be sampled and measurements will be taken
at three depths, 1 m below the sea surface, mid depth and 1 m above the
seabed. Duplicate water samples and
measurements will be taken at each depth.
Where water depth is less than 6m the mid-depth station may be
omitted. If water depth is less
than 3m, only the mid-depth station will be monitored.
The
following suite of parameters should be measured as part of the impact
monitoring for dredging:
¡P
Dissolved
Oxygen (mg L-1) (in situ);
¡P
Salinity
(ppt) (in situ);
¡P
pH (in situ);
¡P
Turbidity
(NTU) (in situ);
¡P
Temperature
(¢XC) (in situ)
¡P
Current
Velocity and Direction (ms-1) (in
situ); and,
¡P
Suspended
Solids (mg L-1) (laboratory analysis).
In addition to the water
quality parameters, other relevant data will also be measured and recorded in
Water Quality Monitoring Logs, including the location of the sampling stations,
water depth, time, weather conditions, sea conditions, tidal stage, special
phenomena and work activities undertaken around the monitoring and works area
that may influence the monitoring results.
Impact
monitoring for dredging activities of CMP V will be evaluated against Action
and Limit Levels. The key
assessment parameters are dissolved oxygen (DO) and suspended sediment (SS) and
thus Action and Limit Levels based on the assessment criteria are identified
for these parameters. However,
turbidity can also provide valuable instantaneous information on water quality
and thus an Action Limit is measured for this parameter to facilitate quick
responsive action in the event of any apparent unacceptable deterioration
attributable to the works.
The
Action and Limit Levels for DO, turbidity and SS were determined in the Baseline Monitoring Report (1) according to the criteria shown in Table 3.2. The Action and Limit Levels of DO,
turbidity and SS were derived from the baseline monitoring data ([4]) and they are presented in
Table 3.3.
Action
and Limit levels are used to determine whether modifications are necessary to
mitigate impacts to water quality.
In the event that the levels are exceeded, appropriate actions in Event
and Action Plan (Table 3.4) should be
undertaken.
Table 3.2 Determination of Action
and Limit Level of Water Quality for Dredging, Capping and Backfilling
Activities of CMP V
Parameter |
Action Level |
Limit Level |
Dissolved
Oxygen |
|
|
Surface
and Middle Depth
Averaged |
The
depth average of the impact station readings are <5%ile of baseline data and Significantly
less than the reference stations mean DO (at the same tide of the same day) |
The
average of the impact station readings are <4mg/L and Significantly
less than the reference stations mean DO (at the same tide of the same day) |
Bottom |
The
average of the impact station readings are <5%ile of baseline data and Significantly
less than the reference stations mean DO (at the same tide of the same day) |
The
average of the impact station readings are <2mg/L and Significantly
less than the reference stations mean DO (at the same tide of the same day) |
Suspended
Solids |
|
|
Depth
Averaged |
The
depth average of the impact station readings are >95%ile of baseline data and 120%
or more of the reference stations SS (at the same tide of the same day) |
The
depth average of the impact station readings are >99%ile of baseline data and 130%
or more of the reference stations SS (at the same tide of the same day) |
Turbidity |
|
|
Depth
Averaged |
The
depth average of the impact station readings are >95%ile of baseline data and 120%
or more of the reference stations turbidity (at the same tide of the same
day) |
The
depth average of the impact station readings are >99% of baseline data and
130%
or more of the reference stations turbidity (at the same tide of the same
day) |
Table 3.3 Action and Limit Levels of
Water Quality for Dredging, Capping and Backfilling Activities of CMP V
Parameter |
Action Level |
Limit Level |
Dissolved Oxygen
(DO) (1) |
|
|
Surface
and Middle Depth
Averaged (2) |
5%-ile of baseline data for surface and middle layer = 3.76 mg L-1 and Significantly
less than the reference stations mean DO (at the same tide of the same day) |
1%-ile of baseline data for surface and middle layer = 3.11 mg L-1 (3) and Significantly
less than the reference stations mean DO (at the same tide of the same day) |
|
|
|
Bottom |
5%-ile of baseline data for bottom layers = 2.96 mg L-1 and Significantly
less than the reference stations mean DO (at the same tide of the same day) |
The
average of the impact station readings are <2 mg/L and Significantly
less than the reference stations mean DO (at the same tide of the same day) |
|
||
|
|
|
Depth-averaged
Suspended Solids (SS) (4) (5) |
95%-ile
of baseline data for depth average = 37.88 mg L-1 and |
99%-ile
of baseline data for depth average = 61.92mg L-1 and |
|
120% of control station's SS at the same
tide of the same day |
130% of control station's SS at the same
tide of the same day |
|
|
|
Depth-averaged
Turbidity (Tby) (4) (5) |
95%-ile
of baseline data = 28.14 NTU and |
99%-ile
of baseline data = 38.32 NTU and |
|
120% of control station's turbidity
at the same tide of the same day |
130% of control station's turbidity
at the same tide of the same day |
|
|
|
Notes: (1)
For
DO, non-compliance of the water quality limits occurs when monitoring result
is lower than the limits. (2)
The
Action and Limit Levels for DO for Surface & Middle layers were
calculated from the combined pool of baseline surface layer data and baseline
middle layer data. (3)
Given the Action Level for
DO for Surface & Middle layers has already been lower than 4 mg L-1, it
is proposed to set the Limit Level at
3.11 mg L-1 which
is the first percentile of the baseline data. (4)
¡§Depth-averaged¡¨
is calculated by taking the arithmetic means of reading of all three depths. (5)
For
turbidity and SS, non-compliance of the water quality limits occurs when
monitoring result is higher than the limits. |
Table 3.4 Water Quality Event and
Action Plan during Dredging Operations
Event |
Environmental Team (ET) |
Contractor |
Action Level |
|
|
Exceedance
for one sample |
¡P
Repeat
in-situ measurement to confirm findings; ¡P
Identify
the source(s) of impact; ¡P
Inform
contractor and contractor informs CEDD, EPD and AFCD and confirm notification
of the non-compliance in writing; ¡P
Check
monitoring data; ¡P
Discuss
potential mitigation measures if exceedance is attributed to the works with
contractor. |
¡P
Discuss
potential mitigation measures with ET and agree on mitigation measures to be
implemented if exceedance is attributed to the works; ¡P
Ensure
mitigation measures are implemented; ¡P
Assess
the effectiveness of the implemented mitigation measures. |
Limit Level |
|
|
Limit
level for one occasion |
¡P
Repeat
in-situ measurement to confirm findings; ¡P
Identify
source(s) of impact; ¡P
Inform
contractor and contractor informs CEDD, EPD and AFCD; ¡P
Discuss
further mitigation measures if exceedance is attributed to the works with
contractor; ¡P
Increase
the monitoring frequency to daily if exceedance is attributed to the works
until no exceedance of the Limit Level. |
¡P
Critical
review of working methods; ¡P
Check
plant, equipment and working methods; ¡P
Discuss
further mitigation measures with ET to be implemented if exceedance is
attributed to the works; ¡P
Ensure
mitigation measures are being implemented; ¡P
Assess
the effectiveness of the implemented mitigation measures. |
|
|
|
Limit
Level exceeded on two or more occasions |
¡P
Identify
source(s) of impact; ¡P
Inform
contractor and contractor informs, CEDD, EPD and AFCD. |
¡P
If
exceedance is attributed to the works consider and if necessary reduce works
until no exceedance of Limit Level. |
|
|
|
Impacts
attributable to works |
¡P
Inform
contractor and contractor informs, CEDD, EPD and AFCD. |
¡P
Comprehensive
review of works; ¡P
Reduce
works; and ¡P
Suspension
of works. |
The main objective of this
component is to determine the impacts, if any, of backfilling activities at CMP
V on water quality. Two separate
components of water quality monitoring are necessary during backfilling:
¡P
Routine Water Quality
Monitoring -
Conducted to examine the impacts of disposal activities on the level of
inorganic metal contaminants in marine waters; and,
¡P
Water Column Profiling - conducted to examine in situ the effects of backfilling
operations on water quality parameters within the water column.
The impact hypothesis for
this work component has been defined based on the predictions from the EIA
regarding impacts from the contaminated mud disposal operations and the
objectives for the study.
Backfilling
operations do not result in any exceedances of Northwestern
Water Quality Control Zone (NWQCZ) Water Quality Objectives (WQO).
As a consequence of
performing two separate tasks for assessing the impacts of disposal operations
on water quality, two null hypotheses will be tested:
Routine
Water Quality Monitoring
H0 There are no
differences in the levels of contaminants in water samples in the plume arising
from the disposal works and background levels in the vicinity of the
backfilling.
Water
Column Profiling
H0 There is no
change in the level of compliance with the NWWCZ WQOs of samples taken from the
plume arising from backfilling activities (EIA predicted location).
Routine water quality monitoring
will be undertaken during backfilling activities at mid-ebb or mid-flood
tide. Water samples will be
collected at specific stations at fixed location, which should be located in
three areas at increasing distances from the active facility; Reference,
Intermediate and Impact stations/areas.
The design for this component of the programme allows impacts, if any,
to water quality as a result of the backfilling activities in the vicinity of
CMP V to be assessed.
The number of monitoring
stations sampled depends on the state of the tide. During the ebb tide, water samples are
collected from five up-current Reference Stations, five down-current Impact
Stations and five down-current Intermediate Stations. During the flood tide, water samples are
collected from three up-current Reference Stations, three down-current Impact
Stations and three down-current Intermediate Stations. The approach will ensure that the impact
of temporal changes on the hydrodynamic conditions in the area is considered in
the sampling.
The
following suite of parameters should be measured as part of routine water
quality monitoring operations:
¡P
Dissolved
Oxygen (mg L-1) (in situ);
¡P
Salinity
(ppt) (in situ);
¡P
pH (in situ);
¡P
Turbidity
(NTU) (in situ);
¡P
Temperature
(¢XC) (in situ)
¡P
Current
Velocity and Direction (ms-1) (in
situ);
¡P
Suspended
Solids (mg L-1) (laboratory analysis);
¡P
Ammonia
(mg L-1) (laboratory analysis);
¡P
Total
Inorganic Nitrogen (TIN mg L-1) (laboratory analysis);
¡P
5-Day
Biochemical Oxygen Demand (BOD5) (mg L-1) (laboratory analysis)
¡P
Cadmium
(mg L-1) (laboratory analysis);
¡P
Chromium
(mg L-1) (laboratory analysis);
¡P
Copper
(mg L-1) (laboratory analysis);
¡P
Lead
(mg L-1) (laboratory analysis);
¡P
Mercury
(mg L-1) (laboratory analysis);
¡P
Nickel
(mg L-1) (laboratory analysis);
¡P
Silver
(mg L-1) (laboratory analysis);
¡P
Zinc
(mg L-1) (laboratory analysis); and
¡P
Arsenic
(mg L-1) (laboratory analysis).
In addition to the water
quality parameters, other relevant data will also be measured and recorded in
Water Quality Monitoring Logs, including the location of the sampling stations,
water depth, time, weather conditions, sea conditions, tidal stage, special
phenomena and work activities undertaken around the monitoring and works area
that may influence the monitoring results.
Sampling Locations
The locations of stations
during ebb and flood tides are shown in Figures 3.2 and 3.3,
respectively, and the coordinates are shown Table 3.5.
An additional monitoring station at Ma Wan will be sampled. Eight replicate samples should be
collected from each monitoring station for eight times per year, twice in the
dry season, twice during the wet season and twice in each of the two
transitional seasons. For a given
sampling event water samples and in situ measurements
should be taken at mid-depth of all stations during the same tidal state (ie mid-ebb or mid-flood tide). Sampling frequency and number of
replicates will be reviewed and adjusted accordingly based on power analyses in
each Annual Review Report.
Details
on the Sampling Programme are shown in Annex C.
Table 3.5 Coordinates of
Water Quality Monitoring Stations for Capping and Routine Water Quality
Monitoring
Monitoring
Stations |
Eastings |
Northings |
Ebb |
|
|
Reference
Stations |
|
|
ESC-RFE1 |
808527 |
822762 |
ESC-RFE2 |
808736 |
823066 |
ESC-RFE3 |
808956 |
823390 |
ESC-RFE4 |
809176 |
823715 |
ESC-RFE5 |
809427 |
824008 |
Impact
Stations |
|
|
ESC-IPE1A |
811791 |
822303 |
ESC-IPE2A |
810946 |
822252 |
ESC-IPE3 |
811763 |
821931 |
ESC-IPE4 |
812430 |
821717 |
ESC-IPE5 |
812894 |
822050 |
Intermediate
Stations |
|
|
ESC-INE1A |
814051 |
822440 |
ESC-INE2A |
813971 |
821801 |
ESC-INE3A |
814579 |
822626 |
ESC-INE4A |
814548 |
822128 |
ESC-INE5A |
814263 |
821209 |
Ma Wan Station |
|
|
MW1 |
823604 |
823654 |
Flood |
|
|
Reference
Stations |
|
|
ESC-RFF1A |
815060 |
822367 |
ESC-RFF2A |
814211 |
821746 |
ESC-RFF3 |
813233 |
821127 |
Impact
Stations |
|
|
ESC-IPF1 |
809862 |
823353 |
ESC-IPF2 |
809293 |
822799 |
ESC-IPF3 |
810432 |
823907 |
Intermediate
Stations |
|
|
ESC-INF1 |
808346 |
823213 |
ESC-INF2 |
809013 |
823843 |
ESC-INF3 |
809680 |
824473 |
Ma Wan Station |
|
|
MW1 |
823603 |
823653 |
Note: Coordinates are based on Hong Kong 1980 GRID
Coordinate System.
Water column profiling will
be undertaken during backfilling activities. There are two monitoring
stations for Water Column Profiling.
Their locations are mobile, and will be dependent on the position of the
disposal barge at the time of monitoring.
The two mobile monitoring stations will be approximately 100 m upstream
and downstream of the disposal area, respectively.
The following suite of parameters
should be measured as part of the water column profiling:
¡P
Salinity
(ppt) (in situ);
¡P
Dissolved
Oxygen (mg L-1) (in situ);
¡P
Turbidity
(NTU) (in situ);
¡P
Temperature
(¢XC) (in situ)
¡P
Current
Velocity and Direction (ms-1) (in
situ)
¡P
pH (in situ); and
¡P
Suspended
Solids (mg L-1) (laboratory analysis).
In
addition to the water quality parameters, other relevant data will also be measured
and recorded in Water Quality Monitoring Logs, including the location of the
sampling stations, water depth, time, weather conditions, sea conditions, tidal
stage, special phenomena and work activities undertaken around the monitoring
and works area that may influence the monitoring results.
Water
Column Profiling will be conducted monthly. Four replicate samples for SS will be
collected at mid-depth from each of the monitoring stations during each
sampling event. During each sampling event in situ measurements
should be taken at 1 m depth intervals through the water column for a period of
one hour at each station. All water
samples and in situ measurements
should be taken during the same tidal state (ie
mid-ebb or mid-flood tide) of a given sampling event. Sampling frequency and the number of
replicates will be reviewed and adjusted accordingly based on power analyses in
each Annual Report. Details
on the Sampling Programme are shown in Annex C.
The hierarchy of sampling
design should allow for the application of nested analysis of variance to
statistically test any changes or trends in the dataset. Under the nested design, differences
will be tested between stations in a particular area and between the three
areas (ie Impact, Intermediate and Reference). Once a time series of data has been
gathered temporal changes in water quality parameters can be analysed for
significant differences. In
addition, the data gathered will be examined against the water quality
objectives for the NWWCZ to determine if the relevant water quality objectives
have been exceeded.
The data gathered will be
examined graphically against the water quality objectives for the NWWCZ to
determine if the relevant water quality objectives have been exceeded for any
apparent impacts arising from the backfilling activities.
Should increases be detected
in the level of contaminants or exceedances of the NWWCZ WQOs be detected, a
review of the other monitoring parameters will be undertaken. This will focus on sampling stations in
the vicinity of the water quality stations where increases are detected to see
if these can be attributed to contaminant spread from the active pits. If so, consideration will be given to
revising the facility operations plan and backfilling activities to reduce the
spread of contaminants in the plume and achieve compliance with WQOs.
The design for this
component of the programme allows impacts to water quality as a result of the
overall capping activities of CMP V to be assessed. Replicate water samples will be collected
at specific stations, which should be located in three discrete areas: Impact,
Intermediate and Reference. The
number of monitoring stations sampled depends on the state of the tide. During the ebb tide, water samples will
be collected from five up-current Reference Stations, five down-current Impact
Stations and five down-current Intermediate Stations. During the flood tide, water samples
will be collected at three up-current Reference Stations, three down-current
Impact Stations and three down-current Intermediate Stations.
The
following suite of parameters should be measured as part of the impact
monitoring for capping:
¡P
Dissolved
Oxygen (mg L-1) (in situ);
¡P
Salinity
(ppt) (in situ);
¡P
pH (in situ);
¡P
Turbidity
(NTU) (in situ);
¡P
Temperature
(¢XC) (in situ)
¡P
Current
Velocity and Direction (ms-1) (in
situ); and,
¡P
Suspended
Solids (mg L-1) (laboratory analysis).
In addition to the water
quality parameters, other relevant data will also be measured and recorded in
Water Quality Monitoring Logs, including the location of the sampling stations,
water depth, time, weather conditions, sea conditions, tidal stage, special
phenomena and work activities undertaken around the monitoring and works area
that may influence the monitoring results.
The locations of stations
during ebb and flood tides are the same as Routine Water Quality Monitoring
which are shown in Figures
3.2 and 3.3, respectively, and the coordinates
are shown Table 3.5. Samples will also be collected
from an additional station at Ma Wan, for both ebb and flood tides. Samples should be collected four times
per year, twice in the dry season and twice during the wet season. Three
replicate samples of SS will
be collected from mid-depth at each monitoring station during each sampling
event. In addition, in situ measurements should be taken at
1 m depth intervals through the water column at each station during a sampling
event. All water samples and in situ measurements should be taken
during the same tidal state (ie mid-ebb or mid-flood
tide) of a given sampling event.
Sampling will be undertaken during capping activities for the CMP as detailed in Annex C. Sampling
frequency and number of replicates will be reviewed and adjusted accordingly
based on power analyses in each Annual
Report.
In situ water quality monitoring (salinity, temperature,
current velocity and direction) will be conducted using the equipment listed in
Section 3.6.1 and following the
testing protocols detailed in Section
3.6.2. In order to ensure the
reliability and quality of the data, the measuring instrument will be
calibrated regularly and the probe of the measuring instrument will be
maintained at a suitable distance from the seabed to avoid re-suspension of
bottom sediments from skewing the results.
Water quality profiling
will be conducted continuously for a one-hour period from a fixed point. After deployment, the probe of the
measuring equipment will be allowed to equilibrate with the surrounding
seawater for approximately 30 seconds.
Subsequently, average readings will be taken every few seconds to minimise
sampling noise arising from the sensitivity of the equipment.
In addition to in situ water quality monitoring, water
samples will be collected in a water sampler. Samples will be stored in sealed
sampling bottles and chilled, and on completion of the survey will be
transported to the laboratory for immediate analysis. Samples not for immediate analysis will
be stored at 4 ¡Ó 2¢XC.
The
following equipment will be supplied and used by the contractor for the water
quality monitoring:
¡P
Positioning
Device
- Horizontal positioning will be used and determined
by a differential Global Positioning System (dGPS)
with the differential signal being provided by a UHF differential
transmitter. The UHF system should
provide an accuracy of better than 3m at the 95% confidence level to ensure the
survey vessel is in the correct location before taking measurements. The dGPS will
be calibrated daily before each survey period or results reported. And all data will be printed and logged
on disc.
¡P
Electronic
data logging device
- A data logging device capable of storing measurement data will be used. The device will be able to read and
store the output from all electronic meters used for this project and will
record time and location as measured by the GPS.
¡P
Dissolved
Oxygen and Temperature Measuring Equipment - The instrument will be a
portable, weatherproof dissolved oxygen measuring instrument complete with
cable, sensor, comprehensive operation manuals, and will be operable from a DC
power source. It will be capable of
measuring: dissolved oxygen levels
in the range of 0 - 20 mg L-1 and 0 - 200% saturation; and a
temperature of 0 - 45 degrees Celsius.
It
will have a membrane electrode with automatic temperature compensation complete
with a cable of not less than 20 m in length. Sufficient stocks of spare electrodes
and cables will be available for replacement where necessary (for example, YSI
model 59 metre, YSI 5739 probe, YSI 5795A submersible stirrer with reel and
cable or an approved similar instrument).
¡P
Turbidity
Measurement Equipment
- Turbidity within the water will be measured in situ by the nephelometric method. The instrument will be a portable,
weatherproof turbidity-measuring unit complete with cable, sensor and
comprehensive operation manuals.
The equipment will be operated from a DC power source, it will have a
photoelectric sensor capable of measuring turbidity between 0 - 1000 NTU and
will be complete with a cable with at least 20 m in length (Hach
2100P or an approved similar instrument).
¡P
Salinity
Measurement Instrument
- A portable salinometer capable of measuring
salinity in the range of 0 - 40 ppt will be provided
for measuring salinity of the water at each monitoring location.
¡P
pH meter ¡V A portable pH meter
capable of measuring a range between 0.0 and 14.0 will be provided to measure
pH in marine waters.
¡P
Suspended
Solid Measurement Equipment - A
water sampler (eg Kahlsico
Water Sampler), which is a PVC cylinder (capacity not less than 2 litres) which
can be effectively sealed with latex cups at both ends, will be used for
sampling. The sampler will have a
positive latching system to keep it open and prevent premature closure until
released by a messenger when the sampler is at the selected water depth. Water samples for suspended solids
measurement will be collected in high density polythene bottles, packed in ice
(cooled to 4oC without being frozen), and delivered to the
laboratory in the same day as the samples were collected.
¡P
Water
Depth Gauge
- A portable, battery-operated echo sounder (Seafarer 700 or a similar approved
instrument) will be used for the determination of water depth at each
designated monitoring station. This
unit will either be hand-held or affixed to the bottom of the work boat if the
same vessel is to be used throughout the monitoring programme.
¡P
Water
Sampling Equipment
- A water sampler, consisting of a transparent PVC or glass cylinder of not
less than two litres which can be effectively sealed with cups at both ends,
will be used (Kahlsico Water Sampler 13SWB203 or an
approved similar instrument). The
water sampler will have a positive latching system to keep it open and prevent
premature closure until released by a messenger when the sampler is at the
selected water depth.
¡P
Current
Velocity Measuring Equipment ¡V An NE Sensortec A/S UCM-60
current meter or Valeport 108 MKIII current meter or
a similar approved instrument will be used for measuring current
direction. Current velocity is
measured by ADCP. Calibration of
ADCP is not likely to be necessary for these instruments as they are calibrated
for the life of the instrument.
The position of the survey
vessel will be positioned to within 3 m of the designated coordinates at each
monitoring station using a differential Global Positional System (GPS).
All
in situ
monitoring instruments will be checked, calibrated and certified by a
laboratory accredited under HOKLAS or any other international accreditation
scheme before use, and subsequently re-calibrated at three month intervals throughout
the stages of the water quality monitoring. Responses of sensors and electrodes will
be checked with certified standard solutions before each use.
On-site
calibration of field equipment will follow the ¡§Guide to Field and On-Site Test Methods for the Analysis of Waters¡¨,
BS 1427: 1993. Sufficient stocks of
spare parts will be maintained for replacements when necessary. Backup monitoring equipment will also be
made available so that monitoring can proceed uninterrupted even when equipment
is under maintenance, calibration etc.
Water samples for SS
measurements will be collected in high density polythene bottles, packed in ice
(cooled to 4¢X C without being frozen),
and delivered to a HOKLAS laboratory as soon as possible after collection.
At least
two replicate samples should be collected from each of the monitoring events
for in situ measurement and lab
analysis.
Using chain of custody
forms, collected water samples will be transferred directly to laboratory for
immediate processing of suspended solids, ammonia, nutrients and BOD5. Water samples will be analysed for pH
and BOD within 4 hours of their arrival at the laboratory. All other parameters will be analysed
within 48 hours of arrival. During
this period samples will be held at 4 ¡Ó 2ºC. Prior to subjecting the sample to metals
analysis, samples will be filtered to remove solids and colloidal matter. Filtration will be accomplished using
acid washed, single-use 0.45 micron membrane filters within a maximum of 8 hours
from sample collection. Where
necessary, samples will undergo further preparation involving preconcentration which allows lower method detection limits
to be achieved and removes some of the possible sources of interference.
Field logs will be maintained for all
survey work, noting the date of the survey, equipment used, survey manager and
a record of all activities and observations. Field logs will be retained for the
duration of the Project and archived on completion.
In-situ measured data will be digitally
recorded from the instruments and converted into Microsoft Excel format, or
manually noted. Both disc copy and
hard copy will be retained for the file records. Any deviation from the standard
procedure will be noted in the log and the reason for the deviation
recorded. In addition, field logs
will contain notes of events or activities in the vicinity of the monitoring
location which might give rise to anomalous data being recorded.
The
sampling, collection, storage and identification procedures are described in Section
3.6 of this Manual and the Contractor will record all data from in situ
testing and from any analysis carried out on the boat in a Field Log. All samples will be identified with a
unique date/time/location/depth/sample-type code which will be attached to the
sample container or written in indelible ink directly on the container. In order to avoid contamination of the
samples, all containers will be new and unused and of analytical grade
quality. Sources of contamination
will be isolated from the working area (for example, vessel fuel and exhaust
fames) and any sample contaminated by local material (such as printed circuit
boards) will be discarded and the sampling repeated. Low level metal analysis in seawater is
easily contaminated through inappropriate handling and sampling
techniques. Site staff involved in
seawater sample collection intended for dissolved metal analysis will ensure
that they wear non-contaminating disposable gloves if they have previously been
operating or have handled metallic equipment.
All
in situ monitoring instruments will be checked, calibrated and certified
and subsequently re-calibrated at three monthly intervals throughout all stages
of the water quality monitoring, or as required by the manufactures
specification. Certificate(s) of
Calibration specifying the instrument will be attached to the monitoring
reports.
All
samples transferred from one sub-contractor to another will be accompanied by
Chain of Custody (COC) forms. Any
missing or damaged samples require notification to ET Leader following logging
in the laboratory QA system. The number
of samples, the parameters to be tested and the time of delivery should be
clearly stated on the COC forms to ensure that samples are analysed for the
correct parameters and suitable time is provided to the analytical laboratory
for provision of resources required in the analyses.
For
details of the contaminants to be tested, the methods to be used, the
accreditation status of laboratory analytical methods, instruments and
procedures to be used, sample preparation information, method detection limits
(MDLs), QA/QC protocols and turnaround times, contractor should refer to the
previous monitoring programme for the ESC CMPIV ([5])
([6])([7]).
The
analytical techniques to be adopted for this Project must conform to HOKLAS (or
similar overseas) accreditation.
Data
Quality Objectives (DQOs) have been developed in the previous monitoring
programme for ESC CMPIV ([8])
([9])
to address precision, accuracy and analyte
recovery. The Contractor is
recommended to follow the DQOs developed for data analysis.
Details of quality control
specifications for inorganic testing should be included in the updated EM&A
Manual prior to commencement of disposal activities.
Precision
Duplicates (1 in every 20
samples) will be used to monitoring the precision of the analysis. Results should be flagged for reference
when:
¡P
In
water samples, for metals with a concentration >4x MDL, the duplicate
results have more than a 15% RPD
¡P
For
all analytes with concentration <4x MDL, the
duplicate results will be reported as analysed and no bounds should be quoted
Accuracy
Standard and certified
reference material (CRM) will be used to monitor accuracy and precision within
and between batches: Results should
be flagged for reference if:
¡P
The
variation of the standard from its true value is more than ¡Ó 15% (for mercury: ¡Ó 20%).
Recovery
Post digest spikes will be
used to determine the recovery of determinants in complex sample matrices. Results should be rejected if:
¡P
Spike
recoveries are more than ¡Ó 25% from the theoretical
recovery for water samples. An
exceptional case would be if the sample concentration is greater than four
times the spike value, the spike may be disregarded.
In
accordance with the recommendations of the EIA for the present Project, a
monitoring programme examining sediment quality will be instituted to verify
the EIA predictions and ensure that there is no build-up in contamination
adjacent to the pits. Sediment
chemistry has long been an important component of monitoring programmes at the
ESC mud disposal complex. A
comprehensive list of Contaminants of Concern (COCs) has been used since 1997,
comprising eight heavy metals and one metalloid, polycyclic aromatic hydrocarbons
(PAHs), polychlorinated biphenyls (PCBs), organochlorine pesticides (eg DDT) and Tributyltin (TBT). These contaminants (which correspond to
the list of COCs in ETWB TC(W) 34/2002) in
sediments should be measured in the present monitoring programme and changes
over time and distance should also be examined.
The
main objective of this task is to determine if there are any changes and/or
trends in the concentrations of contaminants in sediments adjacent to the pits
caused by disposal activities at CMP V.
This objective is most appropriately addressed through two separate but
intrinsically linked sub-tasks:
¡P
Pit Specific Monitoring of
Sediment Quality
- conducted to examine near field impacts of backfilling operations at CMP V on
the spread of contaminants from the pits and to allow for rapid detection of
any adverse environmental impacts and, if necessary, changes to the operations
plan.
¡P
Cumulative Impact
Monitoring of Sediment Quality - conducted to analyse the ambient conditions in the North Lantau region and to investigate
whether any impacts to marine sediments are occurring due to the dispersion of
contaminants from the active pits at
CMP V.
The
impact hypothesis for this task is as follows:
There is no
increase in sediment contaminant concentrations over time at individual
stations or a trend of increasing concentrations with proximity to the active
pit.
As
a result of the separation of this programme into two sub-tasks, two sets of
null hypotheses should be tested:
Pit
Specific Monitoring of Sediment Quality
H0 There is no
increase in sediment contaminant concentration in the area adjacent to the pits
during contaminated mud disposal works.
Cumulative
Impact Monitoring of Sediment Quality
H0 There is no
increase in sediment contaminant concentration over time in the area of contaminated mud disposal activity.
H0 There is no
increase in sediment contaminant concentration with proximity to the active pits.
The designs for assessing
the impacts of disposal of contaminated mud in the active pits at CMP V on the sediment chemistry of remote and
adjacent areas take into account the following factors:
¡P
The
null hypotheses being tested;
¡P
Background
levels of contaminants in the region;
¡P
Predictions
on sediment plume locations;
¡P
Spatial
variability in sediment chemistry;
¡P
Temporal
variability in sediment chemistry; and,
¡P
Expected
statistical treatment of the data.
As mentioned in Section
1.2, this EM&A Manual is an evolving document that should be updated to
maintain its relevance as the Project progresses. This includes the relocation of
monitoring stations to best suit the requirements of the monitoring programme
and to take into account other work that is occurring in the direct vicinity of
the active facility.
The
parameters that should be measured in sediments collected during the two
sub-tasks and the rationale for each are given below. Some of the contaminants listed are the
"Contaminants of Concern" for which Lower and Upper Chemical
Exceedance Limits (LCEL/UCEL) exist.
(a) Total Organic Carbon (TOC) - an
indicator of organic load and the impact on bottom layer dissolved oxygen. TOC is an important factor influencing
the chemical partitioning and toxicity of hydrophobic organic compounds such as
PAHs, PCBs and pesticides. High TOC
often infers that hydrophobic contaminants are less bioavailable;
(b) Inorganic
Contaminants - metals and metalloids present in the disposed sediments
which may be bioaccumulated;
(c) Polycyclic
Aromatic Hydrocarbons (PAH) - a class of organic compounds some of which
are persistent and carcinogenic.
These compounds may be bioaccumulated and
stored in the fatty body tissues of mammals;
(d) Total
Polychlorinated Biphenyls (PCB) - a class of persistent man-made chemicals
which tend to bioaccumulate through the food chain
and can cause reproductive failure and cancer;
(e) Organochlorine
Pesticides (DDE & DDT) - contaminants which are persistent, highly
lipophilic (can be accumulated and stored in fat), have high bioaccumulation
and biomagnification potential, and high toxicity to
aquatic organisms; and,
(f) Tributyltin (TBT) (in sediment and
interstitial water) - moderately persistent toxic compound found in marine
sediments which may be bioaccumulated and cause
growth abnormalities and reproductive failure.
(g) Percentage
of Silt/Clay (% < 63µm) ¡V measured in Cumulative Impacts Monitoring
only. Organic contaminants and
metals bind more readily to finer particles than coarser particles due to their
larger surface area and consequent larger number of binding sites;
Pit
specific monitoring of sediment quality will be undertaken during backfilling
activities. Sediment samples will
be collected from two stations in the active pit, two stations on the edge of
the active pits and two stations in close proximity to the pits. For pit specific monitoring, parameters (a) to (g) in Section 4.4.1 will
be analysed.
Sediment samples will be
collected on a monthly basis from any of the six stations shown in Figure 4.1 and Table 4.1. Locations of
the six sampling stations will be dependent on the location of the active pit
and will be adjusted accordingly. For
example when CMP Va is active, stations ESC-NNDA-B,
ESC-NEDA-B and ESC-NPDA-B will be monitored. Twelve replicates of composite samples
(i.e. 5 grab samples obtained using a cluster grab) will be collected from each
of the stations. Sampling frequency
and the number of replicates will be reviewed and adjusted accordingly based on
power analyses in each Annual Report.
Table 4.1 Coordinates of
Pit Specific Sediment Monitoring Stations
Monitoring
Stations |
Eastings |
Northings |
CMP
Va active |
||
Near-Pit |
|
|
ESC-NNDA |
809547 |
822778 |
ESC-NNDB |
810636 |
821839 |
Pit-Edge |
|
|
ESC-NEDA |
809748 |
822606 |
ESC-NEDB |
810398 |
822031 |
Active-Pit |
|
|
ESC-NPDA |
809976 |
822414 |
ESC-NPDB |
810203 |
822206 |
CMP
Vb active |
|
|
Near-Pit |
|
|
ESC-NNCA |
810110 |
822994 |
ESC-NNCB |
811003 |
822185 |
Pit-Edge |
|
|
ESC-NECA |
810288 |
822825 |
ESC-NECB |
810792 |
822364 |
Active-Pit |
|
|
ESC-NPCA |
810477 |
822665 |
ESC-NPCB |
810652 |
822509 |
CMP
Vc active |
|
|
Near-Pit |
|
|
ESC-NNBA |
810831 |
823066 |
ESC-NNBB |
811780 |
822183 |
Pit-Edge |
|
|
ESC-NEBA |
810965 |
822939 |
ESC-NEBB |
811549 |
822378 |
Active-Pit |
|
|
ESC-NPBA |
811156 |
822726 |
ESC-NPBB |
811367 |
822544 |
CMP
Vd active |
|
|
Near-Pit |
|
|
ESC-NNAA |
811851 |
822535 |
ESC-NNAB |
812735 |
821751 |
Pit-Edge |
|
|
ESC-NEAA |
812046 |
822372 |
ESC-NEAB |
812553 |
821917 |
Active-Pit |
|
|
ESC-NPAA |
812196 |
822239 |
ESC-NPAB |
812371 |
822080 |
Note: Coordinates are based on Hong Kong 1980 GRID
Coordinate System.
Sediment
samples should be collected from stations located in four discrete areas, with
two stations in each area. The
areas should be located at increasing distances from the disposal operations (ie. Near Field, Mid Field, Capped Pits
and Far Field). Sediment
samples should also be collected from the Ma Wan station MW1. For cumulative impacts monitoring
parameters (a) to (g) in Section 4.4.1
will be analysed.
Sediment samples should be
collected four times per year, twice during the dry season and twice during the
wet season at stations indicated on Figure 4.2 and
the coordinates are shown in Table 4.2. Twelve replicates
of composite samples (i.e. 5 grab samples obtained using a cluster grab) will
be collected from each station.
Sampling frequency and number of replicates will be reviewed and
adjusted accordingly based on power analyses in each Annual Report.
Table 4.2 Coordinates of
Cumulative Impact Sediment Monitoring Stations
Monitoring
Stations |
Eastings |
Northings |
Near-field |
||
ESC-RNA |
809547 |
822778 |
ESC-RNB1 |
812875 |
822069 |
Mid-field |
||
ESC-RMA |
807797 |
825010 |
ESC-RMB |
813278 |
820968 |
Far-field |
||
ESC-RFA |
806207 |
827812 |
ESC-RFB |
806307 |
817693 |
Capped Pits |
||
ESC-RCA1 |
810050 |
822436 |
ESC-RCB1 |
811770 |
822104 |
Ma Wan
Station |
|
|
MW1 |
823603 |
823653 |
Note: Coordinates are based on Hong Kong 1980 GRID
Coordinate System.
Observed
differences in the levels of contaminants should be tested using analysis of variance
(ANOVA) with factors area and station, followed by Student Newman Keuls (SNK) multiple comparison procedures to isolate which
treatments differ from others.
For
all of the analysis of variance techniques performed during the monitoring
programme, initial analyses should be performed to ensure that the data
complies with the specific assumptions of analysis of variance. These assumptions state:
¡P
the
data within and among samples must be independent of each other;
¡P
the
variance within samples must be equal (tested through the use of tests such as Levene's median test); and,
¡P
the data among the samples must be
normally distributed (tested through the use of tests such as the Kolgomorov-Smirnov test).
Should
the data not comply with these assumptions then the appropriate transformation
should be applied to the data (eg, arc-sin for
percentage data, log (x+1) for abundance data, or rank
transformation if necessary). If,
after transformation, the data are still non-compliant then non-parametric equivalents
to ANOVA such as Kruskal-Wallis tests should be
used.
The
design of the monitoring programme should allow nested analysis of variance
techniques to be employed. These techniques
will be used to analyse the data at different spatial and temporal scales of
replication. Statistical
differences should be tested at the following levels: between areas and between
sampling times. An advantage of
this sampling design is that it removes the possibility of detecting
differences simply due to inherent variation over spatial scales in the active area and thus facilitates
clearer attribution to disposal operations. By replicating within each area, ie by sampling two stations in one area, any statistically
significant differences detected between areas are more likely to be due to
factors other than spatial variation (eg disposal
operations). This approach is now
an internationally recommended technique for use in monitoring programmes ([10]).Multidimensional scaling
ordination techniques will also be applied to the data, if deemed necessary.
Should
significant increases be detected in the level of contaminants in sediment
samples, a review of the other monitoring parameters should be undertaken. This review will focus on sampling
stations in the vicinity of the sediment quality monitoring stations where
increases are detected to see if these can be attributed to contaminant migration
from the active pits. Assessment of the statistical
significance of the data, confidence in the data and the presence of supporting
data from other components of the monitoring programme should be jointly
assessed. If appropriate, changes
to the operations plan should be considered.
All
samples should be collected by an experienced sampling team, deployed on a
survey boat equipped with fully calibrated sampling equipment and precision
navigational instruments. All
vessel positioning should be accomplished with a calibrated Differential Global
Positioning System (DGPS), ensuring station location accuracy to < ¡Ó 1 m (95% confidence), with
sample position automatically logged and mapped by the navigation
computer. Where sample stations are
located in close proximity to the pit area, positioning should be further
validated by use of an echo sounder to detect whether the vessel is within the
boundaries of the pit.
At
each sampling station the top 5 cm of seabed sediment should be collected using
a 5-component cluster grab sampler which collects surface sediments with a
minimal disruption to the surface layer and is designed to work effectively in
soft sediment such as those found in the area. The cluster grab should be deployed once
at each of the stations located within each sampling area (eg
Pit-Edge). The grabs can be
customised and a fine mesh lid added, which ensures that the fine fluid
sediments on the surface of the seabed are retained in the sample. Utilisation of this cluster sampler
allows a large volume of sediment to be collected in a single deployment. Other similar samplers (eg Petit-ponar) collect less
sediment in each deployment may have difficulty in collecting adequate samples
in soft sediments, such as those within the study area, thereby reducing
efficiency and increasing collection time.
The five-cluster grab should be collected and combined, and the sample,
labelled, double-bagged and stored in an ice chest cooled to a temperature of 4oC
with ice packs. The sediment
sampler and all other utensils should be rinsed with seawater after each sample
has been collected to avoid cross contamination between samples. On completion of the survey, all samples
should be promptly transported, in chilled containers, to the testing
laboratory for analysis.
A
broad range of contaminants should be analysed in sediment samples including
metals, metalloids, PAHs, PCBs, pesticides and Tributyltin in both sediment and
interstitial water. The method
detection limits should be consistent with previous monitoring programmes at
ESC. Other QA/QC procedures to be
implemented for marine sediment analyses include:
¡P
Laboratory blanks - an analyte
free matrix to which all reagents will be added in the same volumes or
proportions as used in the standard sample preparation to monitor contamination
introduced in the laboratory (organics and inorganics);
¡P
Batch duplicates - an intralaboratory
split sample randomly selected from the sample batch to monitor method
precision (intrabatch) in a given sample matrix
(inorganics only);
¡P
Certified Reference
Materials
- analysis of a material with a known concentration of contamination to
determine the accuracy of results in a given matrix (inorganics only);
¡P
Single Control Samples - a known,
interference-free matrix spiked with target analytes
used to monitor laboratory preparation techniques (organics only);
¡P
Duplicate Control Samples - multiple single control
samples designed to monitor preparation technique reproducibility
(organics).
Data Quality Objectives
(DQOs) have been developed to address precision, accuracy and analyte recovery.
Duplicates (1 in every 20
samples) should be used to monitoring the precision of the analysis. Results should be flagged for reference
when:
¡P
For
all analytes, except metals, with concentration
>4x Method Detection Limit (MDL), the duplicate results have more than a 20%
Relative Percentage Deviation (RPD)
¡P
In
water samples, for metals with a concentration >4x MDL, the duplicate
results have more than a 15% RPD
¡P
In
sediment and biota samples, for metals with a concentration >4x MDL, the
duplicate results have more than a 25% RPD
¡P
For
all analytes with concentration <4x MDL, the
duplicate results should be reported as analysed and no bounds should be quoted
Standard and certified
reference material (CRM) will be used to monitor accuracy and precision within
and between batches: Results should
be flagged for reference if:
¡P
The
variation of the standard from its true value is more than ¡Ó 15% (for mercury: ¡Ó 20%).
Post digest spikes should
be used to determined the
recovery of determinants in complex sample matrices. Results should be rejected if:
¡P
Spike
recoveries are more than ¡Ó 25% from the theoretical recovery
for waters, sediment and marine biota.
An exceptional case would be if the sample concentration is greater than
four times the spike value, the spike may be disregarded.
Samples should be analysed
in lots of less than 20. In order
to measure the laboratory performance within each batch of samples, a single
control sample (SCS), a duplicate control sample (DCS) and a method blank (MB)
should be processed concurrently with the samples. A SCS or DCS consists of an interference
free control matrix that is spiked with a group of target compounds
representative of the method analytes.
Method blanks, also known
as reagent, analytical, or preparation blanks, should be analysed to assess the
level of contamination that exist in the analytical system and which might lead
to the reporting of elevated concentration levels or false positive data. For organic analyses, the concentration
of target analytes in the blank must be below the
reporting limit for that analyte in order for the
blank to be considered acceptable.
Accuracy
is expressed as the average percent recovery for the SCS and precision is
expressed as the relative percent difference (RPD) for the DCS pair. For control limits that are not established due
to insufficient data sets, the QC Acceptance Criteria of US EPA Method 8080 and
8270A should be used as a supplement.
Once enough data are collected, the in-house control limits should then
be calculated.
The accuracy and precision
data for SCS and DCS should be evaluated against laboratory established control
limits. QC results falling outside
the control limits should be automatically flagged. The acceptance criterion is that 100
percent of the precision and accuracy values must fall within the control
limits. If this criterion is not
met, corrective action must be taken.
This may include repeat sample analysis.
The average percent
recovery of the SCS should be compared to the limit set for each compound being
monitored (Table 4.3). For
DCS, an RPD of less than 20% is deemed to be acceptable in normal instances.
For multianalyte
organic tests, if greater than 20% of the accuracy or precision results for the
SCS/DCS are outside of the control limits, the data are considered suspect and
the samples associated with the unacceptable DCS are reprepared
and/or reanalysed.
Table
4.3 Quality
Control Acceptance Criteria for Organic Analyses
Target Analytes |
Percent Recovery Measured |
Naphthalene |
74 - 126 |
Acenaphthalene |
69 - 125 |
Acenaphthene |
73 - 119 |
Fluorene |
81 - 129 |
Phenanthrene |
74 - 131 |
Anthracene |
63 - 116 |
Fluoranthene |
73 - 134 |
Pyrene |
59 - 129 |
Benzo(a)anthracene |
77 - 136 |
Chrysene |
53 - 130 |
Benzo(a)pyrene |
51 - 103 |
Dibenzo(a,h)anthracene |
78 - 126 |
DDE |
73 - 121 |
DDT |
87 - 120 |
Total PCBs |
79 - 127 |
Tributyltin |
80 - 115 |
Result
must be greater than zero
The ecotoxicological
testing programme will feature a suite of tests that include three phylogenetically
distinct species that interact with bedded sediments in different ways. Unacceptable impacts may have occurred
if the levels of contaminants in the sediments collected in the adjacent area
of the active pits are shown to have caused toxicity to marine fauna. The findings of the sediment toxicity
tests will be compared to the results of the sediments chemistry.
The objective of this task
is to determine if there are any changes and/or trends caused by disposal
activities in the toxicity of sediments adjacent to the pits as a result of
disposal activities.
In accordance with the
objectives of the Study, the impact hypothesis for this task will be as
follows:
There
is no increase in sediment toxicity over time at individual stations or a trend
of increasing toxicity with proximity to the pit.
The null hypothesis which
should be statistically tested is as follows:
H0 There are no differences in the toxicity of
sediments collected at stations adjacent to the active pits when compared with reference sediments.
In order to determine
whether contaminated sediment placed in the active pits represents an ecological risk to biota in areas
adjacent to the mud pit, ecotoxicological evaluations
will be performed on sediment collected from these surrounding areas.
The toxicological testing
programme should feature a suite of tests that includes phylogenetically
distinct species which interact with sediments in different ways. The testing programme will include
whole-sediment, or solid-phase toxicity tests. The following three international
species should be tested:
¡P
Burrowing
amphipod (Leptocheirus plumulosus, Ampelisca abdita, Eohaustorius estuarius or
other equivalent species);
¡P
Burrowing
polychaete (Neanthes arenaceodentata or
other equivalent species); and,
¡P
Free
swimming larvae of bivalves (Crassostrea gigas, Mytilus spp. or other equivalent species).
In addition, two of the
following local species should also be tested:
¡P
Amphipod
Melita longidactyla;
¡P
Polychaete
Capitella capitata;
¡P
Juvenile
shrimp Metapenaeus ensis or Penaeus (Litopenaeus) vannamei; and,
¡P
Barnacle
larvae Balanus amphitrite.
The experimental designs
for assessing the impacts of disposal of contaminated mud in the ESC facility on the toxicity of
sediments in remote and adjacent areas take into account the following factors:
¡P
The
null hypotheses being tested;
¡P
Location
of other potential sources of contaminants in the North Lantau region, eg, Pearl River;
¡P
Predictions
taken from the EIA on sediment plume locations; and,
¡P
Expected
statistical treatment of the data.
Once
the pit is active (ie receiving contaminated mud),
sediment toxicity testing will be performed only when the level(s) of sediment
contaminant(s) in the Near-field station(s) exceed the LCELs as measured by the
Cumulative Impact Monitoring of Sediment
Quality. Sampling stations will be
sampled not more than twice per year (once in each of the wet and dry
seasons).
Sediment samples should be
collected from two treatment areas as well as at the Ma Wan station. The first treatment area is represented
by samples taken from two stations in an area close to the active pits (Near-Field) and the
second treatment area is represented by samples collected from stations in a
reference area (Far-Field). The
locations of stations are shown in Figure 5.1 and the
coordinates are presented in Table 5.1. Five replicates of composite samples will
be collected from each of the stations and used for the sediment toxicity
tests. Sampling frequency and
number of replicates for CMP V will be reviewed and adjusted accordingly based
on power analyses in each Annual Report. In addition, locations of sampling
stations will be amended based on location of the active facility.
Table 5.1 Sediment Toxicity
Testing Sampling Stations
Station |
Eastings |
Northings |
Reference |
|
|
ESC-TRA |
806207 |
827812 |
ESC-TRB |
806307 |
817693 |
Near-Field |
|
|
ESC-TDA |
809547 |
822778 |
ESC-TDB1 |
812875 |
822069 |
Ma Wan Station |
|
|
MW1 |
823603 |
823653 |
Note:
Coordinates are based on Hong Kong 1980 GRID Coordinate System.
Each of the toxicological tests
will be evaluated for statistically significant increases in toxicity. Statistically significant toxicity will
be determined by performing an analysis of variance (ANOVA) test that compares
the responses observed in the test treatments with those of the reference
treatments. At the end of the
monitoring programme changes in the toxicity of the sediments over time will be
evaluated through the use of two-factor ANOVA incorporating both spatial and
temporal scales of variation.
Once the data have been
evaluated for significance, it is important to identify potential causes of
toxicity and the biological significance of the observed effects. The cause of the observed effects needs
to be distinguished between 1) non-persistent contaminants, 2) persistent
contaminants, and 3) physical factors.
It is most important to determine if the cause of the toxicity is due to
persistent contaminants that are derived from the contaminated sediment placed
in the pits (eg metals, pesticides, PAHs, TBT), to
non-persistent contaminants (eg sulfides,
ammonia, salinity) or to physical factors (eg grain
size).
If the toxicity is due to
persistent contaminants that are associated with disposal operations, the
operations plan for the active pits
may not be effective enough at managing the containment of contaminated
sediment to acceptable levels and thus should be modified. If the observed toxicity is due to
non-persistent contaminants, the effects may be due to the pit but they are
transient. The toxicity of these
types of contaminants can be assimilated by the environment in relatively short
time periods, and are thus less harmful.
If the effects are related to physical factors, they are again of less
concern and would not likely require changes in the facility operations plan.
As non-contaminant factors
and physical factors can confound toxicity test interpretation, the ET will
monitor ammonia, sulfides, interstitial salinity, and
sediment-grain size. Each of these factors
has been observed to elicit a toxic response in test organisms, however, they
are not factors related to persistent contaminants of concern. This information will be used to
investigate any observed toxicity responses and determine whether the response
is due to persistent contaminants or to more transient factors.
The
amphipod toxicity test with burrowing amphipod (Leptocheirus plumulosus, Ampelisca abdita, Eohaustorius estuarius or other equivalent species as
agreed with EPD/AFCD prior to conduct of the toxicity test) will evaluate
survival following a 10-day exposure to test sediment. Procedures will follow those outlined in
PSEP (1995) ([11])
and/or USEPA (1994) ([12]), depending on the species
used for the test, and CEDD's Environmental Laboratory Guidance Document (1996)
([13]). The amphipod benthic test will be
conducted as a static test and will be performed with 175 ml of sediment and
800 ml of overlying seawater placed in a 1-L glass jar. At test initiation, each of five
replicate test chambers will be seeded with 20 amphipods. Test chambers will be maintained at 20¢XC and will be checked daily
throughout the test to establish trends in sediment avoidance. After the 10-day exposure, the benthic
tests will be terminated by sieving the sediments and enumerating the live and
dead amphipods.
The
test on Neanthes arenaceodentata
(or a equivalent species as
agreed with EPD/AFCD prior to conduct of the toxicity test) will evaluate
polychaete survival and growth following a 20-day exposure to test
sediment. Test methods will follow
those outlined in PSEP (1995) ([14]). The test will be conducted as a static
test, performed in 175 ml of sediment and 800 ml of overlying seawater in 1-L
glass jars. At test initiation,
each of five replicate test chambers will be seeded with five polychaetes. Test chambers will be maintained at 20¢XC and will be checked daily
to record mortality and sediment avoidance. To promote growth, worms will be fed
TetraMarin8 every third day throughout the test. After 20 days, the N. arenaceodentata test will be
terminated by sieving each test chamber and enumerating both live and dead
organisms. Surviving polychaetes
will be dried and weighed for each test chamber. Average dry weight will be compared to initial
biomass to determine mean growth for each test chamber.
The
larval-development toxicity test will be performed with fertilized bivalve
embryos (Crassostrea gigas, Mytilus galloprovincialis
or a equivalent species as agreed with EPD/AFCD prior
to conduct of the toxicity test) will evaluate larval survival and development
following a 48 to 96-hour exposure to test sediments. This procedure will follow those
outlined in PSEP (1995) ([15]). This test will be conducted in 20 mg of
test sediment with 800 ml of seawater in 1-L glass jars. At test initiation, test jars will be
seeded with 20 to 40 embryos per ml.
Test chambers will be maintained at 16¢XC. At termination, overlying water will be
decanted and subsamples drawn from the supernatant. Survival and normal larval development
will then be determined under an inverted compound microscope.
In each of the sediment
tests, a sediment/seawater control (consisting of clean sediment for amphipod
and polychaete or clean seawater for the bivalve larval test) will be tested
concurrently with the test sediments.
The control treatment should be included to determine the health of the
test organisms. Sediments collected
from the reference stations will also be tested concurrently with test
sediments to provide a basis for statistical comparison. For the larval tests, grain-size
controls will be tested concurrently with the test sediments to discern any
effects related to sediment grain size.
Additionally, a water-only reference toxicant test using cadmium (from
CdCl2) or copper (from CuNO3) will be conducted with each
batch of test organisms. This
reference-toxicant test provides a measure of relative sensitivity for each
group of test organisms. All toxicity
tests will be completed and reported within four months from collection of the
samples.
Procedures for sampling
will be as for the sediment chemistry for Sediment Quality Monitoring as
detailed in Section 4.8 of this Manual. Shipments of the sediments will be
packaged in ice-boxes in order to maintain the sediments at a constant
temperature of 4oC and dispatched by express courier for immediate
testing.
To ensure the quality and
integrity of the ecotoxicological data and subsequent
analyses, a QA/QC control program will be followed that meets or exceeds the
QA/QC program outlined in Chapter 4 of CEDD's Environmental Laboratory Guidance
Document (1996) ([16]). The QA/QC program for the facility ecotoxicological program is described below.
Upon sample receipt,
samples will be held at 4¢X ¡Ó 2¢X C in the dark until
required for testing. Sediment
holding times for biological testing begin the day of sample collection and
will be kept at a minimum. The
holding time for sediment intended for biological testing will be eight
weeks. Chain-of-custody forms will
accompany each batch of samples to track samples and to provide temperature
data before and after shipping.
Clean seawater for holding
test organisms will be sand-filtered seawater piped directly into the testing
laboratory. Seawater used for test
water and control water should be additionally gravity-feed filtered through a
0.45 -mm filter before use for all test species. Bioassay seawater should be continually
monitored for water quality and the presence of algal blooms.
Procedures for calibration
and maintenance of water quality equipment will follow Measurement Standards Laboratory (MSL) protocols. All measuring and testing equipment used
on this Project should be traceable to the data collected and should be
calibrated before use.
The pH meters used for
obtaining water quality data must be calibrated daily before use according to
MSL-M-045, Calibration and Use of pH Meters. The calibration will be documented on
the pH Meter Calibration Record sheet.
Maintenance on pH meters will be performed monthly. Maintenance should include visual
inspection, cleaning probes in 0.1 M HCl, and
cleaning any corroded contacts.
Refractometers used for
obtaining water quality data will be calibrated monthly using IAPO Standard
Seawater according to MSL-M-048, Calibration and Use of Refractometers. The calibration should be documented on the
Refractometer Calibration Record sheet.
Refractometers should be inspected visually and cleaned monthly.
Digital thermometer
calibrations will be performed monthly by comparison to a certified mercury
thermometer as specified in MSL-M-047, Calibration and Use of
Thermometers. The calibration will
be documented on a Thermometer Calibration Record. Maintenance should include visual
inspection and cleaning of salt and corrosion from connectors and contacts.
Dissolved oxygen meters
should be calibrated daily before use according to MSL-M-046, Calibration and
Use of Dissolved Oxygen Meters. The
calibration should be documented on the Dissolved Oxygen Meter Calibration
Record. Maintenance should be
performed once monthly and should include visual inspection, cleaning the
probe, and replacing of probe membrane.
The Fisher Accumet 1003 pH/selective ion electrode meter with ammonia
electrode should be maintained according to manufacturer¡¦s instructions. The meter should be calibrated on each
day of use with three concentrations of NH4Cl standards bracketing
the expected test concentrations of ammonia. The ammonia probe should be stored in
0.02 M NH4Cl when not in use.
In addition to QA/QC
mentioned above, a series of reviews by qualified laboratory personnel should
be implemented to ensure that the data generated for this Project meets the
data quality objectives. These
reviews should include the following:
¡P
Data
should be reviewed periodically by laboratory personnel to ensure that sample
testing activities are completely and adequately documented.
¡P
Sample
holding times, sample integrity, test animal handling and acclimation,
equipment calibration, water quality measurements, reference toxicity results,
observations, and control survival will be reviewed by qualified laboratory
personnel. The results of QC
measurements will be compared to pre-established criteria as a measure of data
acceptability.
¡P
A
final data audit by the Quality Assurance Officer will be performed prior to
submission of the data and report.
This audit will ensure that the data are accurate, traceable,
defensible, and complete, as compared to the Manual. The audit procedure (MSL-Q-005, Quality
Assurance Data Audits) is a statistical, randomized check which involves
comparing selected reported values to the original data. This procedure is designed to ensure a
95 percent chance of detecting whether one percent or more reported values
disagree with the original data.
The overall quality
assurance objective for this Project is to implement procedures that will
ensure the collection of representative data that is of acceptable and
defensible quality. The data
quality objectives for the ecotoxicological tests
will be devised with reference to the previous data quality objectives
established for the previous monitoring programmes for the ESC CMPs.
A negative control provides
a measure of test organism health.
Negative control treatment will be running concurrent to each toxicity
test as a measure of the test organism's health. For the amphipod (eg
Ampelisca sp) and polychaete (eg Neanthes sp) toxicity tests, the negative control should consist of
clean, native sediment that is to be collected from the test organism's natural
habitat. For the bivalve larval
test, the negative control should consist of clean seawater. Acceptable limits for the negative
controls will be defined with reference to the limits established for the ESC
CMP monitoring programmes. If
survival or normal development do not meet the acceptability criteria, all data
should be evaluated and the test may need to be repeated.
Water quality measurements
provide documentation of environmental conditions within the test chambers
during the exposure. Temperature,
dissolved oxygen, pH, and salinity will be measured daily throughout the
test. Conditions that are
acceptable to maintain the health of the test organisms will be defined with
reference to the acceptable conditions defined for the ESC CMP monitoring
programmes. If test conditions are
outside the acceptability criteria, the data will need to be qualified.
The positive control
provides a relative measure of test organism sensitivity. For each of the bioassays for the active
pits, a separate reference-toxicant test should be performed with each batch of
test organisms. The results of the
reference-toxicant tests will be compared with control charts generated by the
testing laboratory for that species and toxicant. Those results within two standard
deviations of the cumulative mean are considered to be similar in sensitivity
to previous test populations. For
amphipods (eg A.
abdita) the reference-toxicant test will be
performed with cadmium in the form of cadmium chloride; for polychaetes (eg N. arenaceodentata) and bivalve larvae reference-toxicant
tests will be performed with copper as copper nitrate. If the test results are outside the
control limits, the data will need to be qualified.
The
bioaccumulation of contaminants by prey organisms and consequent biomagnification of contaminants up the food chain has long
been an issue of concern for the disposal of contaminated mud at ESC. Although the public at large may not
appreciate the technical details of a biomonitoring programme, especially
concerning mobile populations, they are well aware of the potential for
contaminated mud disposal to taint seafood products. In recognition of these issues, a
comprehensive biomonitoring programme which will address public concerns about
contamination of seafood in the area through use of the data in a risk
assessment framework should be undertaken for the disposal activities at the active pits.
As
well as examining the influence of contaminated sediment disposal on
contaminant levels in demersal fisheries resources, the impact of disposal on
the abundance and structure of demersal fisheries should also be assessed. Consequently, there are two objectives
for this task:
¡P
Biomonitoring of
Contaminants
- To identify any increases in the concentrations of contaminants in tissues
and whole body burdens of demersal marine life adjacent to and remote from the active pits.
¡P
Trawling, Sorting &
Analysis -
To assess the impact of contaminated mud disposal at the active pits on the fisheries resources
of the North Lantau area.
In
accordance with the predictions of the EIA and the objectives for the Study,
the impact hypothesis for this task is as follows:
There is no increase in tissue or
whole body contaminant concentration over time in selected target species.
In
order to reflect the dual workstreams under this
task, two sets of null hypotheses should be tested:
H0 The
concentrations of contaminants in tissue and whole body samples of demersal
marine life adjacent to the active pits
are not greater than contaminant concentrations from samples collected at
stations remote from the active pits.
H0 The
concentrations of contaminants in tissue and whole body samples of demersal
marine life do not increase over time.
H0 There
are no differences in the composition or abundance of demersal fisheries
resources near to and remote from the active
pits.
H0 There
are no differences in the composition or abundance of demersal fisheries
resources over time.
Samples
for biomonitoring of contaminants will be selected from trawl samples described
in Section 6.4.2. Samples of the target species should be
collected twice per year (July/August in the wet season and January/February in
the dry seasons) specifically from six stations. The reference stations will comprise of
two stations located near Lung Kwu Chau and two
stations to the south west of the airport (Figure 6.1). These reference stations are the same as
those sampled in the ongoing monitoring programme (Agreements No. CE 64/99, CE
19/2004, CE 4/2009 and CE 23/2012).
The other two stations will be impact stations, located on the edge of
active pits. However, in order to
obtain sufficient tissue and whole body samples from impact and reference
stations, samples collected at different impact and reference stations will be
combined where necessary.
Due to concerns regarding
the collection of sufficient quantities of target species, catch from the first
trawl survey of each season (trawl for catch characterisation) should be
retained in a frozen state for joint processing with the biomonitoring samples
in the following month.
Five replicate tows (each
with six nets) should be conducted at each station and composite samples
prepared from all nets and tows at each station during each of the sampling
events. Replicate data points
should be obtained whenever the abundance of target species allows laboratory
analysis of more than one tissue/whole body sample for each target species at
each station. The design to be developed
should address the following key issues:
¡P
Rigour
of the dataset to allow for statistical testing of observed differences;
¡P
Data
required for the risk assessment;
¡P
Composite
samples to minimise the variance between fish and improve the reliability of
detecting any significant trends; and,
¡P
Analysing
replicate samples, whenever possible, to provide cost effective statistical
rigour.
The locations of biota
monitoring stations are shown in Figure 6.1 and
the coordinates are shown Table 6.1. Details on the Sampling
Programme are shown in Annex
C.
Table 6.1 Demersal Trawl
Sampling Station Coordinates (centre of the transect)
Station |
Eastings |
Northings |
Impact |
|
|
ESC-INA |
812651 |
822106 |
ESC-INB |
810730 |
823034 |
Reference North |
|
|
TNA |
806220 |
827674 |
TNB |
806366 |
825248 |
Reference
South |
|
|
TSA |
806366 |
816977 |
TSB |
805796 |
815951 |
Note: Coordinates are based on Hong Kong 1980 GRID Coordinate
System.
The design of the sampling
programme should encompasses the following key issues:
¡P
Temporal
variation in fisheries assemblages; and,
¡P
Spatial
variation of mobile assemblages of demersal fisheries resources.
Samples should be collected
for analysis four times each year (twice in the dry season and twice in the wet
season) to account for temporal variation in the fisheries assemblages. The samples should be collected from 5
replicate trawls (each with 6 nets) undertaken along a
transect at each of the six stations, in which two stations are located
at the impact area while four stations are located at the two reference areas (Figure 6.1). Samples for biomonitoring of
contaminants will be selected from the trawl samples.
The data should be analysed
using analysis of variance (ANOVA) techniques to test for differences between
the two sampling sites (Impact and Reference). Once a time series of data (sequential
sampling events) has been gathered, differences should be tested between sites
and between the different sampling events to examine any temporal trends in
contaminant levels in the target species.
Catch composition should be
analysed using partially nested analysis of variance (ANOVA) techniques to
account for changes in catches between and within sites in the North Lantau region and between different
sampling times.
If
significant increases are detected in the levels of contaminants in fisheries
resources in this programme it will indicate that bioaccumulation is
occurring. However,
as demersal fisheries resources are generally mobile (except burrowing species
such as the gobies Trypauchen and Oxyurichthys), increases may not
necessarily be due to disposal at the disposal
facility. Other contaminant
sources such as discharges from the Pearl River, the local sewage outfalls or non point source pollution may cause such increases. To account for these confounding
effects, the results from this Project¡¦s sediment and water quality monitoring
programmes along with the most recent sediment toxicity test results will be
examined so that the sources of any increases can be identified. Should there be evidence that effects
are due to the active facility,
the monitoring and disposal programmes will be reviewed and revised where
necessary as agreed with CEDD and EPD.
The
contaminants of concern for this project should be measured separately, firstly
in tissue samples (soft tissue) and secondly in whole body samples obtained
from the species list established for this project. The species to be examined should be
chosen based on two criteria:
¡P
The
degree to which the organisms are exposed to contaminants in the sediments;
and,
¡P
The
position of the organisms in the food chain and the trophic level of their
predators (ie, humans or Indo-Pacific Humpback
Dolphin).
The
species list (Table 6.2) has been
devised with reference to the previous biomonitoring programmes for the ESC
CMP¡¦s. Comparing to the monitoring
programme from February 2006 to April 2009, the analysis of whole body samples
of Cephalopods is suggested to be removed from the present monitoring programme
as according to Jefferson and Hung (2004) ([17]),
there is little evidence that Indo-Pacific Humpback Dolphin consumed
Cephalopods as a major prey item.
Therefore, it is considered unnecessary to analyze
Cephalopods for the risk assessment of Indo-Pacific Humpback Dolphin (please
refer to Section 7 for details of
risk assessment).
Table 6.2 List
of Target Species for Tissue and Whole Body Analysis
Type |
Tissue
Analysis Target Species ([18])
|
Alternative
Species ([19])
|
Whole Body Analysis
Target Species ([20]) |
Alternative Species ([21]) |
Prawn |
Metapenaeus ensis |
Metapenaeus joyneri |
Metapenaeus spp. |
Metapenaeopsis spp. |
|
Metapenaeus affinis |
Metapenaeopsis spp. |
|
|
Mantis Shrimp |
Oratosquilla oratoria |
Oratosquilla nepa |
Oratosquilla spp. |
|
|
|
Oratosquilla anomala |
|
|
Swimming Crab |
Charybdis cruciata |
Portunus sanguinolentus |
|
|
|
|
Scylla serrata |
|
|
|
|
Portunus pelagicus |
|
|
|
|
Portunus trituberculatus |
|
|
Flat Fish |
Cynoglossus macrolepidotus |
Cynoglossus trigrammus and Solea
ovata |
|
|
Burrowing Fish |
Trypauchen vagina |
Oxyurichthys tentacularis |
|
|
Demersal/Pelagic Fish |
Leiognathus brevirostris |
Collichthys lucida
|
Leiognathus spp. |
|
|
|
|
Collichthys lucida |
Johnius
belengeri |
|
|
|
|
Other Sciaenidae |
|
|
|
Mugil spp. |
|
|
|
|
Thryssa spp. |
|
Gastropod |
Turritella terbra |
|
|
|
Non-Commercial Crab |
|
|
Charybdis spp. |
|
In
the laboratory, each trawl sample should be sorted for target species and
target species selection should be based on the abundance and potential sample
mass available for each species captured.
In preparing composite samples for analysis, different species will not
be mixed. Each composite sample for
laboratory analysis should consist of three or more organisms, with priority
given to larger individuals with no more than 2 fold difference in length. Length and weight of all individual
organisms represented by the composite sample will be recorded and individuals
for tissue sample analysis dissected with a sterilised (with hexane) titanium
knife and a composite sample prepared. Care should be taken not to cross
contaminate any tissue samples with gut contents. For fish, the axial muscle should be
extracted for analysis. For
prawn/shrimp and crab, abdominal and claw/leg muscle should be used,
respectively. For gastropods,
tissue samples should be taken from the soft body tissue.
The analytical parameters
for tissue and whole body testing are given below:
¡P
Inorganic
Arsenic;
¡P
Cadmium;
¡P
Chromium;
¡P
Copper;
¡P
Lead;
¡P
Mercury
¡P
Nickel;
¡P
Silver;
¡P
Zinc
¡P
Total
Polychlorinated Biphenyls (PCBs);
¡P
Organochlorine
Pesticides (DDE & DDT);
¡P
Tributyltin
(TBT);
¡P
Polycyclic
Aromatic Hydrocarbons (PAHs) and,
¡P
Moisture
content.
For
each of the target species a total of five replicates from each station should
be analysed for each analytical parameter for tissue and whole body analysis,
respectively.
In
past monitoring programmes at CMP IV and CMP V there have been times when
insufficient biota are collected in the trawl samples for chemical analysis of
contaminants. In the event of a low
catch, it is possible to pool samples using the procedures shown in Table
6.3 and in the text below.
Table 6.3 Methodology for Pooling Samples to Obtain Sufficient
Tissue/Whole Body Samples for Analysis
Step |
Stations
to Be Combined |
Decision
Criteria (1) |
1 |
Impact (ESC-INA) + Impact (ESC-INB)
= Impact Reference (TNA) + Reference (TNB) =
Reference |
Proceed to step 2 unless tissue and
whole body samples are adequate for analysis |
2 |
Above + previous months Impact
(ESC-INA) = Impact Above + Reference (TSA) + Reference
(TSB) = Reference |
Proceed to step 3 unless Proceed to
step 2 unless tissue and whole body samples are adequate for analysis |
3 |
Above + previous months Impact
(ESC-INB) = Impact Above + previous months Reference
(TNA) = Reference |
Proceed to step 4 unless Proceed to
step 2 unless tissue and whole body samples are adequate for analysis |
4 |
Above + previous months Reference
(TSB) = Reference |
Proceed to step 5 unless Proceed to
step 2 unless tissue and whole body samples are adequate for analysis |
5 |
Above + Reference (TSA) and
Reference (TSB) = Reference |
N/A |
(1)
Note
that inter-seasonal pooling is not permitted.
The pooling of Reference and Impact
biota is not permitted. Pooling
biota from station in the same area should only be done as a last measure.
Wherever possible, samples from the
same station and of the same species should be pooled together ie pooling together Species X from TNA Trawl 1
January 2009 with TNA Trawl 2 January 2009 would be preferable to pooling
samples from TNA and TNB, this can sometimes be unavoidable due to low catch
rates. Pooling of totally different
taxa is not permitted, however, similar taxa can
sometimes be pooled when using ¡¥Alternative Species¡¦ e.g
Oratosquilla nepa
and Oratosquilla anomala
to form Oratosquilla spp.
If insufficient material is obtained
following pooling then, material should be kept and used in ¡¥Alternative
Species¡¦ pooling if they are of a similar group (e.g. if not enough Charybdis
cruciata are available after the pooling of
stations it is possible to pool with other Charybdis sp.). Contaminant uptake is dependent on the
salinity of the water, which is seasonal.
Typically greater uptake occurs during the wet season when salinity is lower
than in the dry season ([22]). For this reason, the pooling of samples
between different seasons should not be conducted.
Catches
from the trawl vessel should be processed to record the abundance and biomass
of individuals of commercial fisheries resources as well as the number of
species (or to the lowest possible taxonomic level) present.
Trawl
sampling should be conducted by a shrimp trawler equipped with a GPS system to
ensure accurate positioning of each trawl.
Five replicate trawls, with six nets deployed in each, should be
conducted for 10 minutes at each station.
If more than one of the six nets are retrieved
in a damaged condition, the samples should be rejected and the trawl repeated. To ensure the maximum quality of the
benthic trawl samples, several control measures have been incorporated into the
sampling programme, including:
¡P
no
more than three consecutive trawls should be conducted at a station and
resampling should only occur after a minimum of two hours has elapsed;
¡P
subsequent
trawls at each station should be shifted to avoid repetitive sampling over the
same area of seabed; and,
¡P
the first station sampled in each survey
should be selected at random to minimise the diurnal influences on
catches.
Catches from all six nets
in each trawl should be combined to form one sample. Each sample should be immediately washed
and stored in sterilised (with hexane) glass jars. All samples should be chilled to 4oC
and transported to the laboratory for further sorting and analysis.
The waters north of Lantau
have historically been important fishing grounds. These fishermen's catches comprise
mainly shrimps and crabs, as well as fish species of relatively low commercial
value such as pony fish, puffer fish and gobies ([23]). The North of Lantau area also is
recognized as the primary habitat of the Indo-Pacific Humpback Dolphin (Sousa chinensis) within Hong Kong waters. This species, which is listed as Near
Threatened on International Trade in Endangered Species (CITES), has a limited
distribution in Hong Kong waters due to its preference for shallow, coastal estuarine
habitat and is thought to be threatened by continuing development in the Pearl
River Delta.
Disposal operations at the
facility will be designed to minimize the dispersion of contaminated sediments
during disposal and to prevent the long-term migration of contaminants through
placement of a clean sand and mud cap.
However, as losses of contaminated sediment will nevertheless occur
during placement, and as the area serves as habitat for marine species which
may be consumed by humans and/or the Indo-Pacific Humpback Dolphin, the risk of
adverse impacts must be addressed by the monitoring programme. Pathways of contaminant release to
sensitive receivers (ie humans and dolphins) include
ingestion of contaminated sediment, ingestion of dissolved and suspended
contaminants in water, and ingestion of organisms with contaminant residues.
Consequently, a risk
assessment will be performed on an annual basis to verify that no unacceptable
risk are occurring to either human health or marine mammals as a result of
consuming prey species from the waters in the vicinity of the pits of North
Lantau. The details of the EM&A
programme for assessing hazard to health of humans and marine mammals are
presented below.
The objective of the risk
assessment component of the monitoring programme is to determine whether
disposal operations at the active pits are posing an unacceptable risk to
humans and dolphins through consumption of seafood/marine prey species from the
North Lantau area. This objective
should be addressed through a standardized risk assessment methodology which
cost effectively builds on existing risk assessment methodologies and databases
and overcomes some of the previous studies¡¦ limitations.
Given the above discussion
of objectives, the impact hypotheses for this component of the monitoring
programme are defined as follows:
For Human Health:
IH1: Risks to human health from
consumption of commercial species captured adjacent to the active pits are no greater
than risks associated with consumption of species remote from the active pits;
IH2: Risks to human health from
consumption of commercial species captured adjacent to the active pits are below the screening risk criterion (see Section 7.5).
For Dolphins:
IH1: Risks to dolphins from consumption
of prey species captured adjacent to the active pits are no greater than risks
associated with consumption of prey species remote from the active pits;
AND
IH2: Risks to dolphins from consumption
of prey species captured adjacent to the active pits are below the screening
risk criterion (see Section 7.5).
Data required for the risk
assessment should consist of:
¡P
contaminant
concentrations in commercial/prey species collected from stations adjacent to
and remote from the active pits;
¡P
toxicology
data for humans and dolphins;
¡P
literature-derived
human consumption rates and patterns for seafood;
¡P
literature-derived
data on exposure of humans from other food groups;
¡P
literature-derived
data on contaminant levels in marine mammals;
¡P
data
collected by AFCD on contaminant levels in stranded Sousa chinensis carcasses; and,
¡P
existing natural history
information for the Indo-Pacific Humpback Dolphin and related species (eg diet composition and feeding range).
The
primary data input to the risk assessment should derive from the bi-annual
trawl (ie tissue samples for human populations and
whole body samples for dolphins) monitoring events. The risk assessment will be performed on
an annual basis.
The risk assessment will
follow the guidelines of the US Environmental Protection Agency ([24])
([25])
and will incorporate a four-step approach involving problem formulation,
estimation of exposure, characterization of ecological or human health effects
(injury), and risk characterization.
Each of these steps is described below with reference to how each
applies to both human health and ecological risk assessment.
Problem
Formulation: Also known as hazard definition ([26]),
the problem formulation will describe the sensitive populations (eg the general Hong Kong population, subsistence fishermen,
the Indo-Pacific Humpback Dolphin) and identify biological effects of concern
potentially associated with the CMP operations at the active facility. Identification of these effects should
include a discussion of contaminants of concern, measurement endpoints and a
conceptual model embodying the mechanisms of contaminant migration.
Estimation
of Exposure: The purpose of the exposure estimation
is to determine the intake of each contaminant of concern by potentially
exposed individuals. This step will
consider the various routes of contaminant release and their migration from the
site to sensitive receivers.
Factors such as fate and transport processes, the concentrations in the
ambient environment, and the maximum short-term or average lifetime doses
should be assessed.
For human populations
exposure factors presented in previous reports ([27]) ([28])
will be critically evaluated to determine if further modification is
necessary. These factors, which
include amounts of seafood consumed, origin of seafood products, and methods of
preparation (eg raw versus cooked, whole body vs
tissue only) will be evaluated for the general population and any sensitive
subpopulations (eg subsistence fishermen fishing in
the ESC area).
Characterization
of Effects: The effects assessment is designed to
quantify the relationship between the degree of exposure to a substance and the
extent of toxic injury or disease.
This step in the assessment will use data derived from dose response
studies on laboratory animals or, less frequently, on exposed human populations
and clinical trials. For
non-carcinogenic substances, once the relationship between doses and responses
is established, a threshold which represents the highest contaminant
concentration that is not expected to result in an adverse effect, ie the reference dose (RfD) or a No Observed Adverse Effect Level (NOAEL)
can be established. This threshold
will then compare to the dose derived from the exposure assessment above to
produce the risk characterization.
For humans, dose-response
relationships must be considered separately for carcinogens and
non-carcinogens. When dealing with
carcinogens, a cancer potency factor (CPF) or Slope Factor (SF) for each
contaminant of concern will be used.
For non-carcinogens, the NOAEL or LOAEL (lowest observed adverse effect
level) will be used as the threshold value. Data on CPFs and NOAEL/LOAEL values are
available through the U.S. EPA's IRIS (Integrated Risk Information System) and
HEAST (Health Effects Assessment Summary Tables) databases. The relationship between contaminant
concentrations in toothed cetacean tissues and the concentrations in their prey
items will be assessed in this programme.
Risk
Characterization: The risk characterization
will integrate the results of the exposure and effects assessments to estimate
the risks and consequences of contaminant exposures. In this step, the estimated exposure
should be divided by the threshold value to obtain a Hazard Quotient (HQ). Generally HQ values below 1 are
considered to represent a very low risk of adverse effects, whereas HQ values
above 10 indicate a moderate to high level of risk.
For human populations, the
general approach to evaluating HQs can be applied to this Project. However, the human health risk
characterization produced for this Project should be updated through the use of
continually collected tissue and other environmental monitoring data to reflect
current conditions. This Study's
human health risk assessment will improve the robustness of previous studies
through a careful reconsideration of all exposure and effects parameters, with
particular focus on background doses and seafood consumption patterns.
The EIAs conducted have
indicated that benthic fauna are expected to recolonise the pits following
capping with uncontaminated mud. It
is expected that recolonisation of the natural
benthic assemblage will occur and eventually the benthic assemblage will
resemble that of the surrounding areas.
Recolonisation may be achieved by larval recruitment, influx of
juveniles or adults carried in water currents, or through the active swimming
or crawling of individuals.
However, other natural (eg storm events,
hypoxia, salinity fluctuations) or anthropogenic (eg
pollution, dredging activities and fisheries operations) activities may hinder recolonisation of capped pits. As a result, the factors contributing to
the composition of the benthic assemblage may be difficult to determine. It is also important for any recolonisation studies to be aware of any cap maintenance
(or "topping up") activities which may also impact the resident
benthic assemblages.
In
order to verify the recolonisation of marine biota on
the capped pits, a benthic recolonisation programme
is recommended. The full details of
the EM&A programme for benthic recolonisation are
presented in the following sections.
The objective for this component
of the Study is to monitor and report on the benthic recolonisation
of the capped pits including the previous ones and specifically to determine
the difference in infauna between the capped pits and adjacent sites.
The impact hypothesis for
this task is as follows:
Recolonisation
is occurring at the capped pits such that assemblages at the capped pits become
more similar to reference assemblages as time since capping increases.
The null hypothesis to be
tested for this work component is as follows:
H0 There is no difference in the structure of
benthic infaunal assemblages found at the capped pits
at the active facility and adjacent reference areas.
H0 Similarity of assemblage structures between
impact and reference stations does not change over time.
The sampling design of this
task involves two treatments: capped pits and reference areas. The capped pit treatment will involve
collection of samples from the capped mud pits at the active facility. The second treatment will involve
sampling at different reference sites, which are chosen to improve the balanced
nature of the design. Using
multiple controls is an effective way of ensuring that the extremely variable
nature of Hong Kong's marine benthos from one site to another does not overly
influence or alter the results.
Current ecological theory suggests that the use of multiple control
sites in sampling designs are statistically more robust and hence the
conclusions more reliable ([29])
([30]).
The benthic sediment
samples collected during this task will be analysed for the following
parameters:
¡P Faunal Abundance;
¡P Faunal Biomass;
¡P
Species
Composition; and,
¡P
Trophic
Structure
Sampling Locations
The locations of impact and
reference stations are shown in Figure 8.1 and the coordinates
are shown Table 8.1. Samples should be collected twice
per year, once in the dry season (i.e. February), once during the wet season
(i.e. August). Twelve replicate samples will be collected from each
of the monitoring stations.
Sampling will be undertaken after capping completed at CMP V as detailed in the Sampling Programme in Annex C. Sampling frequency and number of
replicates for CMP V will be reviewed and adjusted accordingly based on power
analyses in each Annual Review Report.
Table 8.1 Coordinates of
Benthic Monitoring Stations
|
Note:
Coordinates are based on Hong Kong 1980 GRID Coordinate System.
The data collected during
the monitoring programme will be analysed using two different but complementary
approaches as detailed below.
ANOVA: Simple, univariate measures will be
tested using an Analysis of Variance (ANOVA). The method is essentially a comparison
of the variability within a site to the variability between sites. If the ratio of these two variances
(that is, the between‑group‑variance over the within‑group‑variance) is large
enough, then any differences observed are due to true differences that exist
between the groups and not just to random
variation. ANOVA test is based on
several assumptions related to the underlying distribution of the data being
analysed (ie normality, homogeneity of
variances). If the data deviate
significantly from these assumptions, then the test is considered to be
inappropriate. If this situation arises,
alternative procedures (ie parametric tests with rank
transformed data or nonparametric analogues such as Kruskal
Wallis) which address similar hypotheses but do not require such stringent
assumptions will be adopted.
Observed differences between the sites and/or areas will be tested using
multiple comparison procedures such as the Student Newman Keuls
(SNK) or Tukey test.
Multi Dimensional
Scaling (MDS): Multi dimensional
scaling (MDS) will also be used to depict the similarities between stations
based on their benthic assemblages.
MDS is a method for creating a low dimensional picture of the
relationships between stations in a complex, multi
dimensional problem. The
Bray-Curtis distance metric will be used for both the clustering techniques and
the MDS. The dendrogram
from the cluster analysis and the MDS ordination plot will provide
complementary views of the same similarity information. The data for MDS and cluster analyses
should be standardised prior to analysis, to ensure that bias resulting from
including data in different forms (eg percent data
for silt clay composition, numerical data for abundances and biomass data in
mg) does not occur.
The detailed statistical
analyses described above will be used to comprehensively explore the benthic
assemblage patterns in the area of the active pits. This exploration should lead to
conclusions regarding the effectiveness of the cap material in promoting
post-dredging benthic assemblages.
The sampling team and
vessel will be deployed and accurate positioning attained as described in Section
4. The vessel will be equipped
with adequate fixed sieve stations to facilitate rapid processing of samples
and ensure the maximum number of samples are collected
in each survey. At each of the
designated benthic sampling stations, seafloor sampling will be carried out
with a modified Van Veen grab sampler (dimensions 30 cm H 30 cm H 15 cm) or
similar instrument approved by EPD/AFCD.
The remaining sediment from each sample will be used for sorting. Samples will be labelled and sieved
through a 1 mm and 0.5 mm sieve and all residues and organisms retained,
double-bagged and preserved in 4% buffered formalin in seawater. A vital stain (eg
Rose bengal) will be added
to distinguish organic materials and organisms from other non-living
residues. The grab and utensils
will be washed thoroughly with seawater after each deployment to avoid
cross-contamination between samples.
On completion of the survey all samples will be transferred to the laboratory
for sorting and identification. All
sediment sieving will be conducted by qualified marine scientists who will
oversee and coordinate all field operations.
Upon arrival at the
laboratory, all benthic samples should be re-inventoried and checked against
chain-of-custody forms. Sample
rescreening should be performed after the samples have been held in formalin
for a minimum of 24 hours to ensure adequate fixation of the organisms. Individual samples from the 500 mm and 1 mm2 mesh
sieves will be gently rinsed with fresh water into a 250 mm sieve to remove the
formalin from the sediments. Sieves
will be partially filled while rinsing a specific sample to maximize washing
efficiency and prevent loss of material.
All material retained on the 250mm sieve is placed in small
fractions into a labelled petri dish and preserved with 70% ethanol. The material is lightly agitated to
ensure complete mixing of the alcohol with the sediments. The sediment is then sorted to remove
all animals and fragments. Original
labels will remain with the rescreened sample material.
Standard and accepted
techniques will be used for sorting organisms from the sediments ([31]). Small fractions of a sample will be
placed in a petri dish under a 10-power magnification dissecting
microscope. The petri dish will be
scanned systematically and all animals and fragments removed using
forceps. Each petri dish will be
sorted at least twice to ensure removal of all animals. Organisms representing major taxonomic
groups including Polychaeta, Arthropoda, Mollusca, and miscellaneous taxa will
be sorted into separate, labelled vials containing 70 percent ethanol. All sorted samples will be
systematically checked to ensure compliance with QA/QC program requirements
before proceeding to the taxonomic identification, enumeration, and biomass
determination phases of the analysis.
Taxonomic identifications will be
performed by regional taxonomic experts using stereo dissecting and high-power
compound microscopes, to the family level except for dominants, which will be
identified, where possible, to species.
The careful sampling procedure employed in the Study will minimise
fragmentation of organisms, however should breakage of soft-bodied organisms occur, only anterior portions of organism fragments will be
counted. All fragments will be
retained and weighed during biomass determinations, described below. Rare or questionable taxa will be
compared against reference collection specimens for confirmation and
consistency of identification. The
nomenclature used in all reference collections referred to in this study should
be cross checked and differences or discrepancies should be noted. Biomass determinations will be made by
taking the blotted wet mass of each taxonomic fraction.
Sorting QA/QC will be
performed using 25-power magnification by someone other than the original
sorter. Twenty percent of each
sorted sample should be resorted to ensure 95 percent sorting efficiency. A sample passes QA/QC if the number of
organisms found during the QA/QC check does not represent more than 5 percent
of the total number of organisms found in the entire sample. If the number of organisms found is
greater than 5 percent of the total number, the entire sample will be
resorted. Any samples where the
identification of taxa is questionable will be sent out for independent reidentification by a qualified regional expert. Reference collections developed during
previous seabed and benthic studies in Hong Kong should be consulted as
necessary.
Based on the previous
experience with the development and approval for CMPs at ESC for use as a
confined disposal facility for contaminated mud, monitoring of the dispersion
of uncapped sediments during major storm events, such as typhoons of Signal
Number 8 or higher, is an important objective of the study. It is therefore considered necessary to
include this post-storm monitoring as part of the EM&A programme for the
mud disposal facility.
The
post-storm monitoring programme will mobilise within one week of a major storm
event (Typhoon Signal Number 8 or above) in order to determine whether the pits
retain disposed sediments during storms and whether there are any detectable
changes in sediment quality adjacent to the pits. Sediment samples will be collected
within one week of a major storm at stations of the cumulative impact sediment
quality monitoring programme (Section
4.4.3). Locations of the
sampling stations are depended on the location of the active pit; when CMP V is
active for disposal operations sediment samples will be taken from sampling
stations illustrated in Figure 4.2. Only inorganic contaminants and particle
size distribution (organic contaminants are not measured as inorganics can
provide a more cost-effective indicator of any sediment quality change) will be
analysed in the storm assessment.
The field, laboratory and
QA/QC procedures for sediment sample collection after major storm events will
be identical to those used for the Cumulative Impact Sediment Quality
Monitoring Programme (Section 4).
Reports will be provided in
both hard copy and electronic version upon agreeing the format with EPD. This would enable a transition from a
paper/historic and reactive approach to an electronic/real time proactive approach. All the monitoring data should also be
submitted on CD / DVD.
The
following documents will be submitted tas
part of the EM&A programme:
¡P
Environmental Monitoring and Audit Manual;
¡P
Monthly EM&A Reports;
¡P
Quarterly EM&A Reports;
¡P
Annual Review Report;
¡P
Annual Risk Assessment Report;
¡P
Draft Final EM&A Report;
¡P
Executive Summary Report; and
¡P
Final EM&A Report.
Monthly
EM&A Reports
will be required for the duration of the programme period and will be submitted
by the 10th working day of each month. Each report will contain:
• A list of the
activities, tests, analyses and assessments performed in the month according to
that detailed in the Monitoring and Audit Manual for the purpose of reporting
any significant findings resulting from monitoring and audit activities;
• A
list of outstanding activities, tests, analyses and assessments as well as the
schedule for completing these outstanding items; and,
• A
list of previously outstanding activities, tests, analyses and assessments that
are completed in the month.
Quarterly
EM&A Reports
will be required for the duration of the programme period and will be submitted
within 30 days from the end of every quarterly monitoring period. Each report will:
¡P
Confirm
that all activities, tests, analyses, assessments etc. have been carried out as
stated in this EM&A Manual;
¡P
Report
on the auditor's findings on the field events and laboratory tests and
analysis;
¡P
Report
on any trends resulting from disposal, dredging and capping activities at the
active facility.
An
Annual Review Report will be submitted
within 60 days from the end of every yearly monitoring period. Each report will:
¡P
Make
a clear statement on the acceptability of environmental impacts by reference to
the impact hypotheses;
¡P
State
how successful the monitoring programme has been in addressing the objectives
of the Assignment;
¡P
Make
recommendations for revisions to the monitoring programme and disposal
operation, as necessary, to ensure that the objectives are fully met in a cost
effective manner; and
¡P
Summarise
the monitoring results to illustrate whether any change or trend resulting from
the disposal, dredging and capping activities is detected or not.
A
Risk Assessment Report will be prepared within 60 days from the end of
every yearly monitoring period.
Each report will address the risk to the human health and dolphin of
eating seafood taken in the marine area around North Lantau area due to
disposal of contaminated marine sediments in the active pits.
A Draft Final EM&A Report will
be prepared within 90 days from the end of the monitoring period for this
Assignment. It will address how
each objective of the assignment has been met and should will
include a final version of the EM&A Manual as an appendix.
A
Final EM&A Report will be prepared within 3 weeks after the agreed
revisions on the Draft Final Report.
An English and Chinese Executive
Summary Report will be prepared within 3 weeks of receipt of comments on
the Draft Final EM&A Report. It
should highlight any issues of concern and the acceptability of the operations
at the active pits.
([1])
ERM (2017). Proposal of Alternative Monitoring Locations for the EM&A
Activities. Submitted to EPD under Agreement No. CE 23/2012 (EP)
([2])
DevB
(2002).
Management of Dredged/Excavated Sediment, Environment, Transport and
Works Bureau Technical Circular (Works) No. 34/2002
([3])
ERM (2009) Baseline Monitoring Report. Submitted to EPD under
Agreement No. CE 4/2009 (EP) Environmental Monitoring and Audit for
Contaminated Mud Pit at Sha Chau (2009-2013) ¡V Investigation
([5])
ERM (2001)
Environmental Monitoring and Audit for Contaminated Mud Pit IV at East of Sha
Chau: Monitoring and Audit
Manual. Submitted
to CED, February 2001.
([6])
Mouchel
(2001) Consultancy for Environmental Monitoring and Audit for Contaminated Mud
Pit IV at East of Sha Chau (2000-2005):
Monitoring and Audit Manual.
Submitted to CED, May 2001.
([7])
ERM (2005)
Environmental Monitoring and Audit for Contaminated Mud Pit IV at East of Sha
Chau (2005-2008): Monitoring and
Audit Manual. Submitted
to CED, May 2005.
([10])
AJ
Underwood (1997) Experiments in Ecology: their logical design and
interpretation using analysis of variance.
([11]) Puget Sound
Estuary Program (PSEP) (1995). Recommended guidelines for conducting laboratory bioassays on
([12])
Puget Sound Estuary Program (PSEP)
(1995). Recommended
guidelines for conducting laboratory bioassays on Puget Sound sediments. Prepared for the US
EPA.
([13])
EVS (1996). Testing
of Dredged material for Marine Disposal:
Environmental Laboratory Guidance Document. Prepared
for CED.
([16])
EVS (1996). Testing
of Dredged material for Marine Disposal:
Environmental Laboratory Guidance Document. Prepared for CED
([18])
In case sufficient samples of the target
species cannot be obtained, analysis of the alternative species should be
carried out.
([20])
In case sufficient samples of the target
species cannot be obtained, analysis of the alternative species should be
carried out.
([22])
Zhang L, Wang, W (2007) Alternation of dissolved cadmium and zinc uptake kinetics
by metal pre-exposure in the black sea bream Acanthopagrus
schlegeli. Environmental Toxicology
and Chemistry. 25: 1312-1321.
([23])
ERM
(1997) Fisheries Resources and Fishing Operations in Hong Kong Waters. Draft Final Report
prepared AFD.
([24])
U.S. Environmental
Protection Agency. 1992. Framework for
Ecological Risk Assessment. EPA/630/R‑92/001. Risk
Assessment Forum, U.S. EPA, Washington, DC.
([25])
U.S. Environmental
Protection Agency. 1996. Ecological Risk
Assessment Guidance for Superfund: Process for Designing and Conducting
Ecological Risk Assessments (Draft).
([27])
Shaw, B (1995)
Evaluation of risks to human health in Hong Kong from consumption of chemically
contaminated seafood: A risk
assessment approach, MSc thesis, Environmental Management Programme, University
of Hong Kong.
([28])
EVS (1996) Contaminated
Mud Disposal at East of Sha Chau:
Comparative Integrated Risk Assessment. Prepared for
CED.